Section 38, The Rajasthan Land Pooling Scheme Act, 2016: Apportionment of costs of scheme withdrawn or not sanctioned

The Rajasthan Land Pooling Scheme Act, 2016 (14 of 2018) - Section 38

Text of section 38

Apportionment of costs of scheme withdrawn or not sanctioned

In the event of a land pooling scheme being withdrawn or sanction to a preliminary scheme being refused by the State Government, the State Government may direct that the costs of the scheme shall be borne by the appropriate authority or be paid to the appropriate authority by the owners concerned in such proportion as the State Government may in each case determine.

Previous and next

All sections of The Rajasthan Land Pooling Scheme Act, 2016

Questions people ask

Is section 38 of the Rajasthan Land Pooling Scheme Act, 2016 still in force?

No repeal of the Rajasthan Land Pooling Scheme Act, 2016 is recorded.