Rule 7, Works of Licensees Rule, 2017: Alteration of the position of pipes, electric line, etc
Works of Licensees Rule, 2017 - Rule 7
Text of rule 7
Alteration of the position of pipes, electric line, etc
7. Alteration of the position of pipes, electric line, etc.- (1) Any licensee may
alter the position of any pipe (net forming part of a local authority's main sewer),
or of any wire under or over any place which he is authorised to open or break up,
if such pipe or wire is likely to interfere with the exercise of his powers under the
Act; and any person may alter the position of any electric supply-lines or works of
a licensee under or over any such place as aforesaid, if such electric supply-lines or
works are likely to interfere with the lawful exercise of any powers vested in him.
(2) The licensee or other person desiring to make the alteration, unless otherwise
agreed, shall, not iess than one month before commencing any alteration, serve
upon the person for the time being entitled to the pipe, wire, electric supply-lines
or works, as the case may be (hereinafter in this rule referred to as "the owner"), a
notice in writing, describing the proposed alteration, together with a section and
plan thereof on a scale sufficiently large to show clearly the details of the proposed
works, and not in any case smaller than on inch to eight feet vertically and sixteen
inches to the mile horizontally, and intimating the time when it is to be
commenced, and shall subsequently give such further information in relation
thereto as the owner may desire;
(3) The owner may, within fourteen days after the service of the notice, section and
plan, serve upon the operator a requisition to the effect that any question arising
upon the notice, section or plan, shall, unless settied by agreement, be determined
by Appropriate Commission, and thereupon the matter shall be determined by the
Appropriate Commission.
(4) The Appropriate Commission to whom a reference is made under Sub-rule (3),
shall have regard to any duties or obligations which the owner is under, and may
require the operator to execute any temporary or other works so as to avoid, as far
as possible, interference therewith.
(5) Where no requisition is served upon the operator under sub-rule (3) within the
time Iirnit, or where such a requisition has been served and the matter has been
settled by agreement or determined by the Appropriate Commission, the alteration
may, upon payment or securing of any compensation accepted or determined by
the Appropriate Commission, be executed in accordance with the notice, section
and plan and subject to such modifications agreed upon between the parties or as
may have been determined by the Appropriate Commission.
\ ,j~ ••./'
'.'-" 1/'-..-' .
\ .
--}
Page 6 of 11
(i) he may, at least ten days before the operator desiring to make the alteration of
pipes or wires is entitled to commence the alteration, serve upon the operator a
statement in writing to the effect that he desires to execute the alteration himself
and require the operator to give such security for the repayment of any expenses as
may be agreed upon or, in default of agreement, determined by the Appropriate
Commission;
(6) Where the operator desiring to make the alteration makes default in complying
with any of these provisions, he shall make full compensation for any loss or
damage incurred by reason thereof, and, where any difference of dispute arises as
to the amount of such compensation, the matter shall be determined by the
Appropriate Commission.
(7) Where the owner or occupier desires to carry out certain works himself,-
(ii) Where a statement is served upon the operator under clause (i), he shall, not
less than forty-eight hours before the execution of the alteration is required to be
commenced, furnish such security and serve upon the owner a notice in writing
intimating the time when the alteration is required to be commenced, and the
manner in which it is required to be made; and thereupon the owner may proceed
to execute the alteration as required by the operator.
(iii) where the owner declines to comply, or does not, within the time and in the
manner prescribed by a notice served upon him under clause (ii), comply with the
notice, the operator may hirnsel f execute the alteration;
(iv) all expenses incurred by the owner in complying with a notice served upon
him by the operator under clause (ii) may be recovered by him from the operator.