Repairs and works during emcrgency

5. Repairs and works during emcrgency.- The licensee may, In case of emergency due to the breakdown of an underground electric supply-line, after informing the repairing authority or the works authority, as the case may be, of his intention to do so, place an overhead line without complying with provisions of ruie 4: Provided that such overhead line shall be used only until the defect in the underground electric supply-line can be made good, and in no case (unless with the written consent of the repairing authority, works authority or occupier as the case may be) for a period exceeding six weeks, and shall be removed as soon as may be after such defect is removed.

Previous and next

All provisions of Works of Licensees Rule, 2017

Questions people ask

Is rule 5 of Works of Licensees Rule, 2017 still in force?

No repeal of Works of Licensees Rule, 2017 is recorded.