Rule 80, TRIPURA BUILDING RULES — 2017: Requirements for special occupancies under any other law in force
TRIPURA BUILDING RULES — 2017 - Rule 80
Text of rule 80
Requirements for special occupancies under any other law in force
80. Requirements for special occupancies under any other law in force:-
Notwithstanding anything contained in these rules a building shall comply with
special requirements, if any, laid down in Factories Act, 1948 (63 of 1948) or in any other
law for the time being in force in relation to such building.
Page 51
PART VIII
Structural Design
81. Structural design -
(1) Structural design and safety
For any building under the jurisdiction of these regulations structural design/ retrofitting
shall only be carried out by an empanelled Structural Engineer. Proofchecking ofvarious
designs/reports shall be carried out by competent authority as per Table at clause (e)
below wherever applicable.
(a) Additionalprovisions in building regulations/bye—lawsfor natural hazardprone areas
Generally, the structural design of foundations, elements of masonry, timber, plain
concrete, reinforced concrete, pre-stressed concrete and structural steel shall confirm to
the provisions ofPart 6: Structural Design -
Section 7 I Loads, Forces and Effects
Section 7 2 Soils and Foundations,
Section 7 3 Timber and Bamboos,
Section 7 4 Masonry,
Section 7 5 Concrete &
Section 7 6 Steel
Section 7 7 prefabrication System, building and Mixed/ Composite Construction of
National Building Code ofIndia (NBC), taking into consideration the Indian Standards
as amended upto date as given below:
For General Structural Safety
I) IS: 456:2000 “Code ofPracticefor Plain and Reinforced Concrete. ”
2) IS: 800-2007 “Code ofPracticefor General Construction in Steel. ”
3) IS: 801-1975 “Code ofPracticefor Use ofCold Formal Light Gauge Steel
Structural Members in General Building Construction. ”
4) IS 875 (Part 2): I987 Design loads (other than earthquake)for buildings and
structures Part 2 Imposed Loads.
fleeference ofTable 4.1- ”Occupant Load ” may be consideredfor design load)
5) IS 875 (Part 3): I987 Design loads (other than earthquake)for buildings and
structures Part 3 Wind Loads.
6) IS 875 (Part 4): I987 Design loads (other than earthquake)for buildings and
structures Part 4 Snow Loads.
7) IS 875 (Part 5): I987 Design loads (other than earthquake)for buildings and
structures Part 5 special loads and load combination.
8) IS: 883:I994 “Code ofPracticefor Design ofStructural Timber in Building. ”
9) IS: 1904:1986 (R 2005) “Code ofPracticefor Design ofStructural Safety of
Buildings: Foundation ”
Page 52
10) IS: 1905:1987 (R 2005) “Code ofPracticefor Design ofStructural Safety of
Buildings: Masonry Walls ”
11) IS 2911 (Part 1): Section 1: 2010 “Code ofPracticefor design and Construction
ofPile Foundation Section 1
Part 1: Section 2 Bored Cast-in-situ Piles
Part 1: Section 3 Driven Precast Concrete Piles
Part 1: Section 4 Bored Precast Concrete Piles
Part 2: Timber Piles
Part 3: Under Reamed Piles
Part 4: Load Test on Piles
For Cyclone/Wind Storm Protection
12) IS 875 (3): 1987 “Code ofPracticefor Design Loads (other than Earthquake)
for Buildings and Structures, Part 3, Wind Loads ”
13) Guidelines (Based on IS 8 75 (3)-1987) for improving the Cyclonic Resistance ofLow rise
houses and other building.
For Earthquake Protection
14) IS: 1893 (Part I)- 2002 "Criteriafor Earthquake Resistant Design ofStructures
(Fifth Revision) ”
15) IS: 13920-1993 “ Ductile Detailing ofReinforced Concrete Structures subjected
to Seismic Forces 7 Code ofPractice”
16) IS: 4326-2013 “Earthquake Resistant Design and Construction ofBuildings 7
Code ofPractice (Second Revision) ”
1 7) IS: 13828-1993 “Improving Earthquake Resistance ofLow Strength Masonry
Buildings 7 Guidelines ”
18) IS: 1 382 7-1993 “Improving Earthquake Resistance ofEarthen Buildingsi
Guidelines ”
19) IS: 13935-2009 ”Seismic Evaluation, Repair and Seismic Strengthening of
Buildings 7 Guidelines ”
For Protection ofLandslide Hazard
20) IS 14458 (Part 1): 1998 Guidelinesfor retaining wallfor hill area: Part 1
Selection of type ofwall.
21) IS 14458 (Part 2): 1997 Guidelinesfor retaining wallfor hill area: Part 2
Design ofretaining/breast walls.
22) IS 14458 (Part 3): 1998 Guidelinesfor retaining wallfor hill area: Part 3
Construction ofdry stone walls.
23) IS 14496 (Part 2): 1998 Guidelinesforpreparation oflandslid -- Hazard
zonation maps in mountainous terrains: Part 2 Macro-Zonation.
Note: Whenever an Indian Standard including those referred in the National
Page 53
(’1)
Building Code or the National Building Code is referred, the latest revision
ofthe same shall befollowed except specific criteria ifany, mentioned
above against that code.
Structural Design Basis Report (SDBR)
In compliance of the design with the above Indian Standard, the empanelled Structural Engineer
will submit a structural design basis report in the Proforma attached herewith covering the
essential safety requirements specified in the standard.
((0
The “Structural Design Basis Report (SDBR) ” consists offourparts -
Part 1: General Information /Data
Part 2: Load bearing Masonry Buildings
Part 3: Reinforced Concrete Buildings
Part 4: Steel Buildings
1) Drawings and Documents to be submitted for approval of appropriate authorities shall
include SDBR as detailed bow:
Part 1: Completed
Part 2: (ifapplicable) , completed
Part 3: (if applicable) , undertaking that completed Part 3 will be submitted before
commencement ofconstruction.
Part 4: (if applicable) - undertaking that completed Part 4 will be submitted before
commencement ofconstruction.
ii) SDBR as detailed below shall be submitted to the appropriate authority as soon as design
offoundation is completed, but not later than one month prior to commencement of
construction.
Part 1: Completed
Part 2: Part 3: Part 4 (ifapplicable) Completed
Seismic strengthening /retrofitting
Prior to seismic strengthening /retrofitting of any existing structure, evaluation of the
existing structure as regards structural vulnerability in the specified wind/seismic hazard
zone shall be carried out. Ifas per the evaluation the seismic resistance is assessed to be
less than the specified minimum seismic resistance as given in the note below, action will
be initiated to carry out the upgrading of the seismic resistance of the building as per
applicable standard guidelines.
Note:
1. For masonry building reference shall be made to IS 4326 and IS 13935
2. For concrete buildings and structures reference shall be made to IS 15988: 2013 Seismic evaluation and
strengthening ofexisting RCC buildings.
Building with Soft Storey
In case ofbuildings with a flexible storeys, such as the ground storey consisting ofopen
spaces for parking that is “Still building” or any other storey with open halls, special
arrangements are to be made to increase the lateral strength and stifi’ness of the soft/open storey
such as Steel bracing/ Shear walls /Brick infills between columns.
Dynamic analysis of building is to be carried out including the strength and stiffness eflects of
infills and inelastic deformations in the members, particularly; those in the soft storey and the
structural members are to be designed accordingly. Alternatively, the following design criteria
Page 54
are to be adopted afier carrying out the earthquake analysis, neglecting the effect of infill walls
in other storeys:
a. The column and beams of the soft storey shall be designedfor 2.5 times the storey shears
and moments, calculated under seismic loads specified in the other relevant clauses: or
b. Besides the columns designed and detailedfor the calculated storey shears and moments,
shears walls shall be placed symmetrically in both directions of the building as far away
from the centre of the building as feasible; to be designed exclusively for 1.5 times the
lateral storey shear force calculated as before. For details of design and provisions, IS
1893, Part I shall be referred.
(e) Review ofstructural design
1) The Competent Authority shall review and suggest addendum to the certificate or a new
certificate in case ofsubsequent changes in structural design.
iii) Table below gives requirements of empanelled Structural Engineer for different seismic
zones namely III, IVand Vandfor structures ofdifferent complexities.
iv) In seismic Zone II, buildings & structures greater than 40m in height will require proof
checking as per details at Sl. No. 3 ofTable below.
ProofChecking Requirementsfor Structural Design
Sl. No. Type ofStructure Submission from To be Proof
empanelled Structural Checked
Engineer
I Load Bearing Buildings SDBR* Not to be
upto three storeys checked
2 Building upto seven storeys SDBR To be checked
m. C. C/Steel framed Preliminary design To be checked
structure)
3 Building greater than SDBR To be checked
seven storey (R. C. C/Steel Preliminary design To be checked
flamed structure) Detailed structural design To be checked
and structural drawings
4 Special Structures SDBR To be checked
Preliminary design To be checked
Detailed structural design To be checked
and structural drawings
* SDBR 7 Structural Design Basis Report
Notes:
I. Table 4.1 may be referredfor Occupant Load Live loadfor different building types.
2. At the preliminary proposal stage ofa project, the objective is to undertake feasibility study comparison of
a number ofpossible alternatives ofstructural schemes and determine the most cost effective one, detailed
structural calculations are not necessary for each alternative scheme. However, it is conservative
assumption it is possible to derive simplified calculations for analysis and design. This is called
”Preliminary or appropriate analysis, and design ”
After the most cost effective scheme is selected and signed-ofl by the Client, the detailed calculations are
performed on the selected scheme to determine the precise structural members and composition (size,
dimension and stress behavior), and this is called the “Detailed structural design”.
Page 55
In the aforesaid , the design of structural members is typically assumed to account for all the stress loads
identifiedfrom section xx to be applicable in the given project
3. Special structure means large span structures as stadium, assembly halls, or tall structures such as water
tanks. TV tower, chimney, etc.
0‘) Certification regarding structural safety in design
Empanelled Structural Engineer shall give a certificate ofstructural safety ofdesign
as per standardproforma.
(g) Constructional safety
(i) Supervision
All construction except load bearing building upto 3 storeys shall be carried out
under supervision under empanelled Construction Engineerfor various seismic zones.
(ii) Certification ofstructural safety in construction
Empanelled Construction Engineer shall give a certificate of structural safety of
construction at the time ofcompletion.
(h) Quality control and inspection
All material and workmanship shall be of good quality conforming generally to
accepted standards of Public Works Department and Indian standard specification
and codes as included in part-V Building Materials and Part— VII Construction
practices and safety ofNational Building Code OfIndia.
(1) Inspection
All the construction for high-rise buildings higher than seven storeys, public building
and special structures shall be carried out under quality inspection program prepared
and implemented under the empanelled Quality Auditor in seismic zones.
(ii) Certification ofsafety in quality ofconstruction
Empanelled Quality Auditor shall give a certificate of quality control. Quality
Inspection Programme to be carried on the site shall be worked out by empanelled
Quality Auditor in consultation with the owner, builder.
Note: Section (g) and (h) shall not be applicable government buildings that are designed and constructed under the supervision
of in house architect/ engineer.
(I) Control and signage & outdoor display structures, cellphone towers and telephone
towers.
Followingprovisions shall applyfor telecommunication infrastructure-
a) Location: The Telecommunication Infrastructure shall be either placed on the
building rooftops or on the ground or open space within the premises subject
to other regulations.
b) Type ofStructure
1) Steelfabricated towers or antennae ’s on MS. pole.
ii) Pre-fabricated shelters offiber glass or P. V. C. on the building rooftop/
terracefor equipment.
iii) Masonry Structure/ Shelter on the groundfor equipment.
iv) D. G set with soundproofcover to reduce the noise level.
0) Requirement:
1) Every applicant has to obtain/ procure the necessary permission from the
“Standing Advisory Committee on Radio Frequency Allocation ” (SACFA)
issued by Ministry ofTelecommunication.
Page 56
(2)
(3)
(4)
82.
83.
84.
ii) Every applicant will have to produce the structural safety & stability
certificate for the tower as well as the building from the empanelled
Structural Engineer which shall be the liability of both owner and
empanelled Structural Engineer.
iii) Applicant has to produce/submitplans ofstructure to be erected.
d) Projection: No pager and/ or Telephone tower shall project beyond the existing
building line ofthe building on which it is erected in any direction.
Structural requirements oflow income housing
Notwithstanding anything contained herein, for the structural safety and services for
development of low income housing, the relevant provision of applicable IS: 8888
part I shall be enforced along with Annex C ofpart 3 NBC.
Alternative Materials, Methods ofDesign and Construction and Tests
The provision of the Bye-Laws are not intended to prevent the use of any material or
method of design or construction not specifically prescribed by the bye-law provided
any such alternative has been approved. The building materials approved by B.I.S. or
any statutory body will form part of the approved building material and technology as
part ofthe Bye-Laws.
The Authority shall promote and encourage use ofPre-fabricatedfactory made building
components for medium to large scale projects that have significant impact. The use of
ready mix concrete (RMC) shall also be encouragedfor in-situ concrete constructions.
While submitting the plan for Ground Floor /Basementfloor ofthe building, the plan
should clearly specify the height of the buildingfor which foundation of the building
has been designed and all relevant provisions of the Rules related to that designed
height ofthe building should befollowedfrom the beginning i. e. from Ground Floor/
Basementfloor ofthe building.
Quality of materials and workmanship.-
All materials and workmanship shall be of good quality conforming generally to
the accepted standards of the Public Works Department of the Government of Tripura or
Indian Standard Specifications as indicated in part V on Building Materials and part VII
on Constructional practices and safety of the latest edition of the National Building code
of India.
Alternative materials, method of design and construction.-
The ULB may approve any alternative material or method of design or
construction if the competent authority of the ULB is satisfied that such alternative is
satisfactory and conforms to the provisions of the relevant parts of the National Building
Code of India regarding materials, method of design and construction and that materials,
methods of design or work are for the purpose intended equivalent to those specified in
the code in quality, strength, compatibility, effectiveness, fire and water resistance,
durability and safety.
Tests.-
Whenever there is insufficient evidence of compliance with the provisions of
these rules or there is evident that any claim for alternative materials, or design, the ULB
may require tests to be made sufficiently in advance or require performance certificate
from a body authorized by a state or central government, as proof of compliance and
such tests shall be made at the expenses of the owner and in such manner as the ULB
may direct.
Page 57
85.
86.
87.
PART IX
Building and Plumbing Services
Building Services. —
(1) The planning, design and installation of electrical fittings, air-conditioning and
heating work, installation of lifts and escalators shall be carried out in accordance with
the provisions of Lifts and Escalators on Building Services of the latest edition of the
National Building Code of India. For electrical aspects of building services the provisions
of the latest edition of National Electrical Code shall apply.
(2) The number of types of lifts to be provided in educational building shall be as
specified in the latest edition of National Building Code of India.
(3) Electrical installation in respect of any building exceeding 14.5 (fourteen point
five) meters in height shall conform to the provisions of the latest edition of National
Electrical Code.
Plumbing services.-
The planning, design, construction and installation of water supply, drainage and
sanitation and gas supply system shall be in accordance with provisions of the Water
Supply, Drainage and Sanitation, Gas supply on Plumbing Services of the latest edition
of National Building Code of India. Septic tank, pits of pit privy shall be so located in a
premises or holding, that the same is easily accessible from the means of access to the
plot.
Single and outdoors display structures. —
(1) The construction of advertising signs and outdoor display structure shall be in
accordance with the provisions of the latest edition of the National Building code of India.
(2) Every building shall display in a prominent place on the front side, the premises
number as assigned to it by the ULB and the street name, so as to be conveniently visible
from the street.
Page 58
88.
89.
90.
PART- X
Special Provision for ULBs in the Hill Areas
Special provision. —
(1) Notwithstanding anything contained elsewhere in these rules, the special
provisions of this part shall apply only to the ULB in the hill areas or to supplementing,
the other provisions elsewhere in this rule in there application to those ULBs in the hill
areas. Anything not covered under the special provisions shall be guided by the
provision made elsewhere in this rule or the Act.
(2) For provisions not specifically covered in this part related provisions of other
parts will apply.
Power to relax rules. -
Notwithstanding anything contained in these rules, a ULB or other concerned
authorities may for reasons to be recorded in writing and with the previous approval of
the State Government relax any provision of these rules for dealing with a case in a just
and equitable manner.
Criteria of using a piece of land as building site. —
(1) No piece of land shall be used as a building site unless the ULB is satisfied that -
(a) land record is in conformity with the proposed construction keeping in view
specified land use, if any;
(b) the site of such building abuts an all weather public street, a projected public
street or a private street/ footpath, passage and is not less than 1.50 meters wide
at any part, duly sanctioned and constructed and recorded in the Books of ULB in
accordance with the provisions of the Act or any other law in force immediately
before the commencement of the Act:
Provided that, no building shall be erected so as to deprive any other building or
buildings site of the means of access as specified above;
(c) the site is at least 100 sq. meters in area for residential purposes and 40.0 sq.m
in area for other than residential purposes.
(d) the land is capable of being well drained by means of drainage facilities leading
to the existing Public drainage, channel or natural jhora;
(e) the site is reasonably secured from danger from hillside slips from above, below,
or the sides;
(f) the soil of the site is likely to sustain the construction of a building thereon; and
for sites with inclinations of 30° and above or proposed building above 6.5 meters
in height or 500 sq. meters in coverage, such sustainability shall be justified, at
the cost of applicant, by prior testing of soil and certification of stability of slopes
and buildings conforming to the latest relevant codes of Bureau of Indian
Standards including
IS 12070: IS Code of practice for design and construction of shallow foundation
on rock.
IS 13063: IS Code of practice for structural safety of building on shallow
foundation on rock.
IS 14243 (Part I & II): Selection and development of site in hiII areas guidelines;
in addition to other relevant Indian Standards.
A competent geo-technical engineering organization or firm, recognized by the
ULB, shall carry out detailed geo—technical investigations, testing and certification in such
cases.
Page 59
Explanation: Soil will also include rocks, boulders laterite etc.
(g) the site does not contain any portion which forms a component of the open
spaces prescribed under the regulation for any other building site thereof.
(h) (i) no part of the land is located within 200 meters from the boundary of a
sinking or probable slip zone, designated in a meeting by the ULB.
(ii) within an area of distress or possible unequal settlements with wide
fissures, regular cracks, faults, voids , rock, debris or landslides caused
by subsidence or crosion, filling and disposal or organic materials, or;
(iii) it is located within an area showing high water table and fully saturated
soil with a possibility of liquefaction and settlement on exposure to
earthquakes or of water seepage in the foundations and crosion , or ,
(iv) any other vulnerable area identified by the ULB as unsafe for
environmental , geological, wind, drainage or any other reasons;
(i) no piece of land is located within five meters in any direction of the outside
edge of such water courses;
(j) adequate drainage measurement and protection work as specified in rules
shall be taken by the applicant at his own cost if it is located on the permanent
shadow zones of ridges and spurs, at the bottom of the valleys or gorges or
located by nature of its orientation in a zone as identified by the ULB to be
inadequately sunlit so as to make it unfit human habitation, if any;
(k) the side has not been subject to repeated blasting or, was a former quarry;
(l) where the side is within 5.0 (five) meters of any side of a tank, the owner will
take such measures as well prevent any risk of the drainage from such building
passing into the tank;
(m) where the site is within 5.0(five) meters of any side of a tank, water
reservoir, jhora/ natural spring, water source or natural drain or within 2.0(two)
meters from either side of water pipe, sewer line and / or other such underground
utilities, the owner shall take such measures at his own cost, which shall prevent
any risk of damage and / or landslide thereto by construction of such buildings.
The distance shall be measured from outside edge of the jhora/drain / pipeline
etc. as the case may be taken by the owner, at his own cost if the side is within
30 meters ofjhora;
(n) no piece of land shall be used as building site if it is located on the
permanent shadow zones of ridges and spurs at the bottom of the valleys or
gorges or located by the natural or its orientation in a zone as identified by ULB
to be inadequately sunlit so as to make it unfit for human habitation.
(2) No piece of land located in central business area as determined by the ULB or in
sinking zone or areas of distress with cracks caused by subsidence and /or slides
or any other areas identified by ULB with reasons to be recorded in writing, shall
be used as a building site without prior approval of the State Government.
(3) No piece of land where a closed, sick or other industry was located or is in
operation, shall be used as site for construction of any building, other than an
industrial building, without the prior approval of the competent authority.
Previous and next
Questions people ask
Is rule 80 of TRIPURA BUILDING RULES — 2017 still in force?
No repeal of TRIPURA BUILDING RULES — 2017 is recorded.