Rule 33, TRIPURA BUILDING RULES — 2017: Completion of work
TRIPURA BUILDING RULES — 2017 - Rule 33
Text of rule 33
Completion of work
33. Completion of work. —
After the completion of the erection of a building or the execution of any work, the owner
of the building shall submit a notice of completion in Form ‘G'. In case of deviation as stated in
clause (a) of sub-rule (2) of rule 30, the notice shall be accompanied by 3(three) sets of building
plan and marked 'completion plan’ with all revisions and modifications including those referred
to in sub-rule (2) of rule 30. The applicant shall duly sign the plans and also the concerned
technical personnel specified in rule 17;
Provided that for a residential or educational building in any municipal area, not
exceeding 8.0 metre in height on a plot of 200 Sq. metre in area, application of this rule may not
be insisted upon but the owner will have to intimate in writing to the ULB about the completion of
such building.
Previous and next
Questions people ask
Is rule 33 of TRIPURA BUILDING RULES — 2017 still in force?
No repeal of TRIPURA BUILDING RULES — 2017 is recorded.