Rule 29, TRIPURA BUILDING RULES — 2017: Notice for completion of work up to plinth level
TRIPURA BUILDING RULES — 2017 - Rule 29
Text of rule 29
Notice for completion of work up to plinth level
29. Notice for completion of work up to plinth level.-
(1) After the completion of the structural work up to the plinth level or up to
1(one) metre above ground level, whichever is higher, the applicant shall give a notice
to the ULB in Form ‘F’ to enable him to inspect such work.
(2) An officer of the ULB duly authorized in this behalf shall inspect the work at the
site within 15(fifteen) days from the date of the receipt of the notice and within
7(seven) days of such inspection issue necessary direction, if any.
Previous and next
Questions people ask
Is rule 29 of TRIPURA BUILDING RULES — 2017 still in force?
No repeal of TRIPURA BUILDING RULES — 2017 is recorded.