Rule 20, TRIPURA BUILDING RULES — 2017: Sanction of building Plan and permission to execute work
TRIPURA BUILDING RULES — 2017 - Rule 20
Text of rule 20
Sanction of building Plan and permission to execute work
20. Sanction of building Plan and permission to execute work.-
(1) within 30 (thirty) days of the receipt of any application with building plan or of any
information or documents which the ULB may reasonably require the applicant to furnish before
deciding whether permission shall be granted to execute any work, the competent authority
shall, by written order -
a) accord sanction, in Form ‘C’, to the building plan conditionally or
unconditionally give permission to execute the work, or
b) refuse in Form ‘D’ on one or more of the grounds mentioned in section
126 of the Act to accord such sanction, or
c) accord sanction but impose conditions for permission to execute the
work, or
d) accord provisional sanction under the proviso in section 125 of the Act :
Provided further that in the case of a provisional sanction, the applicant shall furnish a
statement to the effect that, if he is unable to produce the license or permission as required, the
provisional sanction would be at his own risk and cost and shall not be made final and the
Page 2 5
occupancy certificate under Rule 34 of this Rules shall not be issued in respect of the use other
than that specified in the Building Plan.
(2) The Building permit shall not be issued till a duly authenticated copy of a receipt
showing payment to the ULB of the Building Permit Fees payable under rule 25 of these rules
for the sanction of the buildings is produced before the Mayor/Chairperson of the Local Body.
Previous and next
Questions people ask
Is rule 20 of TRIPURA BUILDING RULES — 2017 still in force?
No repeal of TRIPURA BUILDING RULES — 2017 is recorded.