Rule 18, TRIPURA BUILDING RULES — 2017: Time and manner of disposal of application under rule 13
TRIPURA BUILDING RULES — 2017 - Rule 18
Text of rule 18
Time and manner of disposal of application under rule 13
18. Time and manner of disposal of application under rule 13. -
Within 15(fifteen) working days from the date of receipt of an application with
building plan, the ULB may require the applicant -
a) to furnish him with any information on matters referred to in these rules which
has not already been given in the documents there under;
b) to satisfy, him that there are no objections which may lawfully be taken to the
approval of the building plans;
c) if any requisition made under these rules is not complied with within 1(one)
month, the application for approval of the building plans shall be treated as
cancelled.
Previous and next
Questions people ask
Is rule 18 of TRIPURA BUILDING RULES — 2017 still in force?
No repeal of TRIPURA BUILDING RULES — 2017 is recorded.