ANNEXURE - 1
ANNEXURE - 1
(Statement of particulars and specification)
1. Name in full(in block letters) of the owner :
Present Address
P.S. Mouza J.L.
C.S. Rehab/Plot No. of the site Ward No.
The purpose (Residence, Office, Godown, Restaurant, Hotel, Dharmasala, School,
College, Hostel, institution, Cinema, Shop, Factory, etc.) for which it is intended to be
used
(a) Basement
(b) Ground floor
(c) 1st floor
(d) 2nd floor
(e) 3rd floor
(a) Total area of the site (in square meters)
(b) Total plinth area of the building proposed to be erected/re-erected etc. (in square
meters)
(c) Site Plan Sanction No (with date)
(a) Number of floors
(b) Height of the building over road level
The materials to be used as specification of the constructions:
(a) Foundation
( b) Floors
(C) Walls
(d) Roofs
(e) Fire Places/chimneys
(a) Approximate number of inhabitants proposed to be accommodated: -
(b) The number, size and specification of latrine, kitchen, bath to be provided
Probable cost of construction of the proposed structure (and such
other information as required by the rules)
Signature of the Architect /Licensed Building Planner.
License No. Date
Full Address
93
!”?
Signature, name and address of the owner.
INSTRUCTIONS TO THE APPLICANT
The applicant must be owner of the land.
Before filling up the form please go through the provisions of the Building Rules.
The applicant is requested not to take up the building construction until and unless he is
permitted to do so. If any such construction is undertaken without permission, it will be
treated, as clear violation of the Building Rules and matter will be proceeded with
accordingly.
Page 92
The building shall not be considered within the restricted distance of the electric wire
running on any side of the side under the provisions of the Indian Electricity Rules.
The building plan must be prepared by the Architect / Licensed Building Planner and the
list of approved Building Planners available in the office.
If any information or document is required under the Building Rules or is, in the opinion
of the competent authority, incomplete, he may require further information or documents
to be furnished.
. If the Land Use controller, if any, refused to issue "No objection Certificate", in that
case the competent authority will not accord any sanction of Building Plan as per this rules.
In case of fees in respect of grant of permission to execute any work it would be
determined as per Rule 25. The said fees to be paid in the form of Account Payee
Demand Draft on any Schedule Bank of the area in favour of
along with duly filled in application Form B and other enclosures.
Applicant shall submit the application Form B as the case may be (in duplicate) duly
filled in, for permission to construct or re-construct masonry building and shall enclose
the following documents with the application, otherwise it will be rejected :-
(a) An approved site plan.
(b) A building plan in triplicate.
(c) Filled up Form B as the case may be, in duplicate
(d) Filled up Annexure of Form B (in duplicate).
(e) Attested copy / certified copy of allotment of land and possession
certificate of land.
(f) Attested copy of current holding tax receipt in case of old building / new
building for execution purpose.
(9) Account payee Demand Draft of Rs. as Fees for sanction of
Building Plan.
Page 93
FORM N0 — B-A
(Rule No. 15)
CERTIFICATE OF UNDERTAKING
FOR HAZARD SAFETY (REGULATION NO. ---) REQUIREMENT
To,
REF: Proposed work of
(Title of project)
Location:
Rule No. ----- of Tripura Building Rules
1. Certified that the building plans submitted for approval of the safety requirements as
stipulated under the information given therein is factually correct to the best of our
knowledge and understanding.
2. It is also certified that the structural design including safety from hazards based on
soil conditions, shall be duly incorporated in the design of the building and these
provisions shall be adhered to during the construction.
3. A check list is attached.
. . ' f h 1E 'Slgnature of Owner w1th date Signature 0 t e Structura nglneer
— w1th date
Name in Block letters
Address
Signature of the Developer
with date
Name in Block letters
Address
Page 94
Name in Block letters
Address
Signature of the Architect
with date
Name in Block letters
Address
Building information schedule
1 Encircle the applicable data point 2 * means ‘any other, specify’
1 Building Plot No. Scheme / Town: District:
address Colony:
2 Building 2.1 a b c d e f g h i NBC7.1.1
category Occupancy
Classification
2.2 Type of Type 1 Type 2 Type 3 Type 4 NBC & 1.2
Construction OF Part III
& 4 of Part
IV
3 3.1 Land use Bye Iaw
Location zoning
3.2 Seismic zone V IV III II Is 1893-
2000
Design IX VIII VII VI VuI.
intensity(MM/MSK) Atlas
3.3 Wind /Cyc|one Wind speed + Cyclone Max. storm VuI.
zone 55/50/47/44/39/33 prone surge = m Atlas
Yes/No
3.4 Flood River plain Low area Observed VuI.
proneness of site Unprotected/ inundation HFL about Atlas
Protected possible — GL = cm
Yes/ No
3.5 Prone to land
slides
4 4.1 Site and IS
Foundation sub-soil 1892,
investigation IS
5249
4.2 Soil type Rocky/ Medium Soft Liquefiable Expansive * IS
at site (Note Stiff (Black 1904,
2) cotton) IS
6403
in IS 1893)
Stiff— N>30; Medium- N=10 —30 ; Soft- N<10; Liquefiable — Poorly
graded sands with N<15, under water table ( see Note 5 of Table 1
4.3 Depth of
water table
below GL
Page 95
4.4 Bearing For With E0 = With wind With flood = IS
capacity at normal t/m2 =t/m2 t/m2 1888,
site (used in loads = IS
design) t/m2 1904
IS
6403
IS
8099
(Part
1&2)
4.5 Type of Strip Individual Bearing Friction
footing / column piles piles
Foundation footing/
used Raft
5 Super 5.1 Storeys Basements No. of Attic Lift Water
structure etc 0/1/2/3 storeys Yes/ No house tank on
Yes/ No roof
Capacity
1
5.2 Bearing Brick Stone Solid Hollow Adobe *
walls block block
5.2.1 C:S=1: C:L:S=1: L:S=1: ClayMud *
Mortar :
C= Cement S= Sand L= Lime
5.3 Frame RC columns & Steel Wood posts
work beams columns & &trusses
beams /
trusses
5.3.1 Infill Glass Brickwalls Wood
panels paneling
5.4 Floors RC slabs Stone slabs Prefab
on jists floring
elements on
breams
5.5 Roof Flat like floors/ Trussed / *
Pitched Raftered/ ‘A’
frame/Sloping
RC slab
5.6 Roof CGI AC Clay Wood *
covering sheeting sheeting tiles shingle
6 Building 6.1 Ordinary Important Hazardous IS 1893
importance Importance
7 7.1 Factor do: I: 5: 0th: IS1893
Design for E0
factors 7.2 Factor K1: K2: K3: Ph= Is 875 (Pt3)
forwind
Page 96
8 Flood Plinth Water Roof Yes / * Flood guide
protection protection proofing of No / NA
Yes/ No / walls Yes/
NA No/ NA
9 9.1 Bracing In plan In plane In plane of vertical IS 4326
Safety provided Yes / No of rafters columns Yes/No/NA Cyclone
of /NA Yes/No/ guide
pitched NA
roof 9.2 Roof To walls: To RC To wooden posts, steel Cyclone
where anchorage Bolt columns: straps&bolts/ nails... guide
used length = Bolt
cm length =
cm
9.3 Covering Purlins to Truss elements Cyclone
Connections to purlins rafters Welding/Bolts/Nails/Straps guide
J-bolt/ire Bolt/ Wire
10 10.1 A B C D E IS 4326
Load Building a h < a h =0_05 a h >0.06 a h = 0.08 to < a h > IS13828
bearin 0.05 to 0.06 &<0.08 0.12 0.12
9 wall
buildi . . .ng 10._2_ Plan shape Separation Plan proiection>0.2 IS 4326
Building L/T/Y/C/E prowded to get of length
configura rect. Yes / No
tion Blocks Yes /
No
10.3 Control used on Control used Strengthening IS 4326,
Opening sizes on location around IS 13828
in walls Yes/No/NA Yes/No/NA Yes/No/NA
10.4 Plinth Lintel Eave band Roof Gable Ridge IS
Bands band Band Yes/No/NA band band band 4326,
provided Yes/No/N Yes/No/N Yes/N Yes/No/ Yes/N IS
A A o/NA NA 0/ NA 13828
10.5 At corner of rooms At jambs of * IS 4326,
Vertical Yes/No/NA opening IS 13828
bars Yes/No/NA Cyclone guide
10.6 RC screed&band Peripheral Diagonal * IS 4326
Stiffening Yes/No/NA band and planks and
of floors/ connector alround
roof with s band
separate Yes/No/N Yes/No/NA
units A
Page 97
10.7 Bonding of columns with the wall IS 4326
Framed ensured Yes / No (Fig. 13 of IS
thin wall 4326)
construct
ion
11 11.1 Holding Sill beam Wood posts Framed, resting IS
Safety of down bolted anchored on pedestals 4326
wooden Yes/No/NA Yes/No/NA Yes/No/NA Cyclone
buildings guide
11.2 Bracing of Diagonal Diagonal / Stiff wall Brick IS 4326
wood frame bracing in knee panel noggin Cyclone
Vertical bracing in with guide
planes plan hold
Yes/No/NA Yes/No/NA fasts
11.3 Framed Bolted Nailed * Cyclone
Connections with iron guide
strips
12 12.1 Both axes One axis Unsymmetrical
Safety of Building symmetrical symmetrical in plan or
steel / shape section
RC 12.2 Equivalent Model Dynamic Torsional effects IS 1893
frame Analysis static considered
buildings used Yes / No
12.3 Work stress Limit state Plastic theory IS 456
Method of IS 800
design SP 6(6)
used
12.4 Infills Out of plane stability In-plane stiffness IS 1893
/ partitions check Yes/ No considered Yes/No IS 4326
Cyclone
guide
12.5 Beams Columns Beam- Shear IS
Detailing Yes / No Yes/No column joint wall 13920
of RC Yes / No Yes / No
frames
12.6 Beams Yes Columns Beam-column SP 6
Detailing / No Yes/No joint Yes / No
of steel
frames
Page 98
13 13.1 Provision Under ground Over head Adequate NBC
Fire for water tank : tank : pumping Part
safety Provided/Not Provided / Not system: IV
provided provided Provided/ Not
Capacity: 1 Capacity: 1 provided
Capacity
1/minute
Pressure:
13.2 Provision Provided / Not provided / Not applicable NBC
for first aid fire Part
fighting IV
13.3 Installation Provided / Not provided / Not applicable NBC
of systems Part
IV
14 14.1 Earthing design Designed / Not Provided / Not IS 3043
Electrical and provision designed provided
safety 14.2 Electrical lay out/ Designed : Yes/ No IS 4648
provision IS 732
15 Land 15.2 Land slide control Designed : Yes / No IS
slides 14680
15.3 Design and Designed : Yes / No IS
construction of retaining 14458
walls Part
1,2,3
Page 99