Regulation 37, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Auxiliary consumption and transformation losses
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 37
Text of regulation 37
Auxiliary consumption and transformation losses
37. Auxiliary consumption and transformation losses.—Normative auxiliary
consumption and transformation losses for the small hydro projects shall be 0.5% of the
gross generation and the same for transformation losses at the switchyard linked to the
generating station of the projects shall also be 0.5%:
Provided that for the sake of simplicity, these two factors shall be clubbed together
and accounted for as 1% of the gross generation.
Previous and next
Questions people ask
Is regulation 37 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.