Regulation 35, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Normative saleable energy
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 35
Text of regulation 35
Normative saleable energy
35. Normative saleable energy.—(1) The normative saleable energy at the
interconnection point for the purpose of generic levellised tariff shall be computed on the
following lines namely :—
1
Sub. for “CHAPTER-V TECHNOLOGY SPECIFIC PARAMETERS FOR SMALL HYDRO PROJECTS
“ for vide not. No. HPERC/428 dated 28
th
January, 2019, published in R.H.P. dated 30
th
January, 2019 at p.
7835-7843.
46 Compendium of HPERC Regulations, March 2021
(i) the normative annual capacity utilisation factor (CUF) for all the small hydro
projects upto 25 MW shall be 55%. The number of hours in a year for
calculations of CUF shall be 8766;
(ii) the normative annual energy worked out at the normative CUF under
preceding clause (i) for the installed capacity shall be adjusted for the
auxiliary consumption, transformation losses and the losses in the project
line(s) at the normative rates as per regulations 37 and 38;
(iii) the energy worked out under preceding clause (ii) shall be further reduced by
the permissible rate of the free power subject to a maximum of 13%, for any
year or part thereof, consistent with the National Hydro Policy, Tariff Policy
and the policy of the State Government for allotment of sites of small hydro
projects in the manner as laid down in regulation 36, so as to arrive at the
year wise normative net saleable energy at the interconnection point which
shall be taken into account for working out the generic levellised tariff:
Provided that in case the limit of 13% for the pass through of free power in the tariff
as per the National Hydro Policy/Tariff Policy is revised by the Central Government, or
staggered by the Government, at any stage, the Commission may review the tariff(s) as per
the provisions under regulations 20.
(2) The normative capacity utilization factor (CUF) under clause (i) of sub-
regulation (1) takes into account the impact of mandatory release of water discharge
immediately downstream of diversion structure of the project based on the existing
instructions of the State Government which provide that for the purpose of determination of
minimum discharge, the threshold value not less than 15% of the minimum inflow observed
in the lean season shall be considered.
(3) The normative year wise net saleable energy for the purpose of project specific
tariff determination shall also be worked out on similar lines given in sub-regulations (1) and
(2) but by taking into account the annual Capacity Utilisation Factor (CUF) in accordance
with clause (ii) of sub-regulation (1) of regulation 15, the normative auxiliary consumption
and transformation losses under regulation 37 and the energy losses in the project line under
regulation 38.
Previous and next
Questions people ask
Is regulation 35 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.