Text of regulation 32
Ceiling norms
32. Ceiling norms.—The financial norms, except for capital cost, as specified in this
Chapter of these Regulations, shall be considered as ceiling norms and the same shall
notpreclude the licensee or renewable energy generator from agreeing to improved
norms,including operation and maintenance norms, which may lead to overall reduction in
the levellised tariff and in case the improved norms are agreed to, such improved norms
shall beapplicable for determination of the project specific levellised tariff.
1
[PART-II]
1
Consequential amendments in the Regulations “PART-II” vide not. No. HPERC/428 dated 11
th
November, 2019, published in R.H.P. dated 18
th
November, 2019 at p. 7983-7995.
Compendium of HPERC Regulations, March 2021 35
FINANCIAL PRINCIPLES
(APPLICABLE FROM 01.10.2019 TO 31.03.2020)
21-A. Capital Cost.—(1) The norms for the capital cost in case of small hydro projects shall
be as specified in Part-II of the Chapter-V of these Regulations and in case of other
renewable technologies, shall be as stipulated under relevant orders of the Commission
under regulation 18.
(2) The norms for the capital cost shall be inclusive of all the expenses required to be
incurred as per prudent practices upto the commissioning of the project, including, but not
limited to, the cost of capital works, land, preparation of the Detailed Project Report, Survey
and Investigation, plant and machinery, civil works, erection and commissioning, financing
and interest during construction, land acquisition, resettlement and rehabilitation,
contribution towards Local Area Development Fund (LADF), statutory and non-statutory
clearances and evacuation infrastructure up to inter-connection point (also including
interconnection facilities), insurance charges against the risks during construction stage etc.
and also all taxes, levies and duties on all such components/works capital works:
Provided that any cost pertaining to allotment of the project, including upfront
premium and any other amount charged by the State Government while granting extension
or capacity enhancement and/or any liquidated damages/penalty imposed by the State
Government in accordance with the implementation agreement and/or those imposed by the
licensee in accordance with the power purchase agreement, will not form part of the capital
cost:
Provided further that for project specific tariff determination, the renewable energy
generator shall submit the itemwise break-up of capital cost along with its petition in the
manner specified under regulation 19 and the capital cost admitted by the Commission shall
be taken into consideration.
22-A. Subsidy or incentive or grant/budgetary support by the Central/State
Government.—(1) While determining the generic levellised or project specific levellised
tariff, as the case may be, for the renewable energy project(s) under these Regulations, the
Commission shall take into consideration any incentive and/or subsidy and/or grant available
under the schemes of the Central or State Government or their agencies, but excluding
accelerated depreciation benefit under the Income Tax Act:
Provided that the Commission may evolve suitable mechanism(s) for incorporating
impact of the subsidy component for determination or adjustment of generic levellised tariffs
for various categories of projects:
Provided further that the capital subsidy under the schemes of the Central or State
Government or their agencies, shall, unless the circumstances otherwise warrant, be
ordinarily adjusted in the middle of first 12 months from the commencement of the tariff
period against the principal component of the loan amount as additional reduction apart from
the normal payment:
Provided further that where the Central Government or the State Government
notifies, or has notified, any generation based incentive (GBI) scheme for a particular kind
of renewable technology, such technology based generating station shall be assumed to have
availed the benefit of such a scheme and their tariffs shall automatically be treated as
36 Compendium of HPERC Regulations, March 2021
reduced by the amount of generation based incentive (GBI) per unit for the period during
which such incentive remains applicable.
(2) Where any additional project specific grant or budgetary support is available to
any project, apart from the incentive and/or subsidy and/or grant available under sub-
regulation (1) of this regulation, the Commission shall account for such budgetary support
also, while determining project specific levellised tariff.
(3) The amount of subsidy shall be considered for each renewable source as per the
applicable policy of the MNRE/State Government/Central Government and if the amount
and/or mechanism of subsidy is changed by the MNRE/State Government/Central
Government, consequent corrections in tariffs may be carried out by the Commission in
accordance with regulation 20.
23-A. Debt-Equity Ratio.—(1) The normative debt equity ratio shall be 70:30.
(2) For generic levellised tariff, the Commission shall adopt debt equity ratio of
70:30.
(3) For project specific levellised tariff, the following provisions shall apply.—
(i) if the equity actually deployed is more than 30% of the capital cost admitted
by the Commission under regulation 15, the equity deployed in excess of
30% limit shall be treated as normative loan in accordance with the National
Tariff Policy and shall be deemed as advanced at the weighted average rate of
interest and for a weighted average tenor of the long term debt component of
the project after ascertaining the reasonableness of the interest rates and
taking into account the effect of debt restructuring, if any;
(ii) in case the equity deployed is equal to or below the normative level of 30%,
the actual equity would be used for determination of Return on Equity in
tariff computations;
(iii) the equity invested in foreign currency, if any, shall be designated in Indian
rupees on the date of each investment.
Explanation.—For the purposes of return on equity, any resources available to the
renewable energy generator from its share premium account or from its internal resources
that are used to fund the equity commitments of the project under consideration shall be
treated as equity subject to the limitations contained in this regulation and regulation 26-A.
(4) The Commission shall treat any incentive or subsidy and/or grant/budgetary
support available from the MNRE/State Government/Central Government, to have been
utilized towards pre-payment of debt in such phases as it may deem fit, leaving balance loan
to be considered for determination of tariff.
24-A. Loan and Finance Charges.—(1) For the purpose of determination of tariff, loan
tenure of 13 years, inclusive of moratorium period, if any, shall be considered:
Provided that the capital subsidy admissible to the renewable energy generator shall
normally be considered for the reduction of loan period and such reduced loan tenure shall
be considered for the purpose of tariff determination.
(2) Interest Rate.—
Compendium of HPERC Regulations, March 2021 37
(a) The loans arrived at in the manner indicated in the regulation 23-A shall be
considered as gross normative loan for calculation of interest on loan. The
normative loan outstanding as on 1st April of every year shall be worked
out by deducting the cumulative repayment up to 31st March of previous
year from the gross normative loan.
(b) For the purpose of computation of tariff(s) under these Regulations,
normative interest rate of two hundred (200) basis points above the
average State Bank of India Marginal Cost of Funds based Lending Rate
(MCLR) (one year tenor) prevalent during the last available six months,
prior to the respective date(s) from which such tariff(s) the respective
generic levellised tariffs are to be made applicable, shall be considered:
Provided that in case where the project specific tariff is to be
determined, such average rate of SBI, as prevalent during the respective
periods in which the loan has been availed, shall be taken into account on
weighted average basis and the rate so worked out on this basis or the
weighted average rate at which the loan has been availed, whichever is
lower, shall be considered.
(c) Notwithstanding any moratorium period availed by the renewable energy
generator, the repayment of loan shall be considered from the first year of the
tariff period and shall be equal to the annual depreciation allowed.
(d) Apart from the adjustment of subsidy in accordance with regulation 22-A, the
loan repayment for a financial year or the relevant part period thereof shall
be considered to have been done in the middle of that financial year or the
relevant part period thereof, as the case may be.
25-A. Depreciation.—For the purpose of tariff determination, depreciation shall be
computed in the following manner, namely:—
(a) the value base for the purpose of depreciation shall be the normative capital cost (for
generic tariff) or the capital cost of the project as admitted by the Commission (for
project specific tariff), as the case may be;
(b) the salvage value of the asset shall be considered as 10% and depreciation shall be
allowed up to maximum of 90% of the capital cost of the asset;
(c) depreciation per annum shall be based on 'Differential Depreciation Approach'. For
tariff purposes, the depreciation shall be allowed @ 5.28% per annum till such time
the requirement for repayment of loan component of the capital cost as per
regulations 21-A, 23-A and 24-A after adjusting the amount of subsidy as per
regulation 22-A, is fully provided and the remaining depreciation shall be spread
over the residual useful life of the project on straight line method;
(d) depreciation shall be chargeable from the first year of commencement of operation of
the project:
Provided that in case of operation of the asset for part of the year,
depreciation shall be charged on pro rata basis for the purposes of project specific
determination of tariff.
26-A. Return on Equity.—(1) The value bases for the equity shall be 30% of the normative
capital cost as determined under regulation 21-A:
38 Compendium of HPERC Regulations, March 2021
Provided that in case of project specific determination, the value base of equity shall
be restricted to the actual amount of equity or 30% of the capital cost admitted by the
Commission, whichever is lower, in accordance with the provisions of regulation 23-A.
(2) The normative return on Equity shall be 17% per annum on pre tax basis and
shall not be subject to any adjustment on account of any taxes, or changes in the tax rates,
under the Income Tax Act.
27-A. Interest on working capital.— (1) The working capital requirement in respect of
wind energy projects, small hydro power, solar PV and solar thermal projects shall be
omputed in accordance with the following:—
(a) operation and maintenance expenses for one month;
(b) receivables equivalent to 2 (two) months of energy charges for sale of
electricity calculated on the net saleable energy corresponding to the CUF
considered for tariff determination on normative basis;
(c) maintenance spares @ 15% of operation and maintenance expenses.
(2) The working capital in respect of biomass power projects with Rankin Cycle
technologies, biomass gasifier based power projects, nonfossil fuel based cogeneration
projects, Municipal Solid Waste power projects and Refused Derived Fuel project shall be
computed in accordance with the following:—
(a) fuel cost for four months equivalent to normative Plant Load Factor (PLF);
(b) operation and maintenance expenses for one month;
(c) receivables equivalent to 2 (two) months of energy charges (fixed and
variable charges) for sale of electricity calculated on the net saleable design
energy on normative basis;
(a) maintenance spares @ 15% of operation and maintenance expenses.
(3) In case of the renewable technologies not covered in sub-regulations (1) and (2),
the Commission may adopt such norms, as it may consider appropriate, at the time of
determination of tariff.
(4) Interest on Working Capital shall be at interest rate equivalent to the normative
interest rate of three hundred (300) basis points above the average State Bank of India
Marginal Cost of Funds based Lending Rate (MCLR) (One Year Tenor) prevalent during the
last available six months, prior to the respective date(s) from which the generic tariff(s) are
to be made applicable:
Provided that in case where the project specific tariff is to be determined, such
average rate for the last available six months prior to the date from which the project specific
tariff is to be made applicable, shall be considered.
28-A. Operation and maintenance expenses.—(1) Operation and maintenance expenses
mean the expenditure incurred on operation and maintenance of the project, or part thereof,
and includes, without limitation, the expenditure on manpower, establishment (including
employees expense, administrative and general expenses), repairs, spares, consumables,
insurance and overheads as well as the taxes, duties and other levies on any or all such
activities.
Compendium of HPERC Regulations, March 2021 39
(2) Operation and maintenance expenses shall be determined for the tariff period
based on normative operation and maintenance expenses specified in Part-II of Chapter-V of
these Regulations for the small hydro projects and as stipulated in relevant orders of the
Commission for other renewable technologies.
(3) Normative O&M expenses allowed under these Regulations shall be escalated at
the rate of 5.72% per annum over the tariff period.
29. Taxes and duties.— Tariff determined under these Regulations shall be inclusive of all
taxes and duties and shall not be subject to any change except for the provisions specified
under regulation 20.
30-A. Rebate.—(1) The due date for payment of bills shall be 60 days from the date of
billing.
(2) For payment of bills of the renewable energy generator through letter of credit, a
rebate of 2% shall be allowed.
(3) Where payments are made, other than through letter of credit, within a period of
one month of presentation of bills by the renewable energy generator, a rebate of 1% shall be
allowed.
31-A. Late payment surcharge.—The distribution licensee shall make timely payments of
energy bills of the renewable energy generators by assigning priority over and above all
other payments. In case the payment of any bill for charges payable under these Regulations
is delayed beyond a period of 60 days from the date of billing, a late payment surcharge at
the simple interest rate of 1.25% per month shall be levied by the renewable energy
generator for the actual number of days by which the payment is delayed.
32-A. Ceiling norms.—The financial norms, except for capital cost, as specified in this
Chapter of these Regulations, shall be considered as ceiling norms and the same shall not
preclude the licensee or renewable energy generator from agreeing to improved norms,
including operation and maintenance norms, which may lead to overall reduction in the
levellised tariff and in case the improved norms are agreed to, such improved norms shall be
applicable for determination of the project specific levellised tariff.
32-AA. Applicability.—The provisions of this Chapter shall be applicable for all the RE
technologies for the matters to be dealt under second control period irrespective of the
intervals at which Generic levellised tariffs are determined under this control period.”.
1
[PART-III
FINANCIAL PRINCIPLES
(APPLICABLE FROM 01-04-2020 TO 30-09-2023)
21-B. Capital Cost.—(1) The norms for the capital cost in case of small hydro projects shall
be as specified in Part-III of Chapter-V of these Regulations and in case of other renewable
technologies, shall be as stipulated under relevant orders of the Commission under
regulation 18.
1
Ins. Regulations “21-B to 32-BB” of “PART-III” vide not. No. HPERC/428 dated 8
th
September,
2020, published in R.H.P. dated 15
th
September, 2020 at p. 3561-3570.
40 Compendium of HPERC Regulations, March 2021
1
[Provided that in case of small hydro projects upto 100 kW capacity, such norms
shall be as fixed in the relevant orders of the Commission under Regulation 14.]
(2) The norms for the capital cost shall be inclusive of all the expenses required to
be incurred as per prudent practices upto the commissioning of the project, including, but
not limited to, the cost of capital works, land, preparation of the Detailed Project Report,
Survey and Investigation, plant and machinery, civil works, erection and commissioning,
financing and interest during construction, land acquisition, resettlement and rehabilitation,
contribution towards Local Area Development Fund (LADF), statutory and non-statutory
clearances and evacuation infrastructure up to inter-connection point (also including
interconnection facilities), insurance charges against the risks during construction stage etc.
and also all taxes, levies and duties on all such components/works capital works:
Provided that any cost pertaining to allotment of the project, including upfront
premium and any other amount charged by the State Government while granting extension
or capacity enhancement or/and any liquidated damages/penalty imposed by the licensee in
accordance with the power purchase agreement executed with it, or by the State Government
in accordance with the implementation agreement executed with it, will not form part of the
capital cost:
Provided further that for project specific tariff determination, the renewable energy
generator shall submit the item wise break-up of capital cost alongwith its petition in the
manner specified under regulation 19 and the capital cost admitted by the Commission shall
be taken into consideration.
22-B. Subsidy or incentive or grant/budgetary support by the Central/State
Government.—(1) While determining the generic levellised or project specific levellised
tariff, as the case may be, for the renewable energy project(s) under these Regulations, the
Commission shall take into consideration any incentive and/or subsidy and/or grant available
under the schemes of the Central or State Government or their agencies, but excluding
accelerated depreciation benefit under the Income Tax Act:
Provided that the capital subsidy under the schemes of the Central or State
Government or their agencies shall be adjusted in the normative capital cost and the cost so
arrived, after such adjustment, shall be considered for computing Debt-Equity Components
for the purposes of determination of generic levellised tariffs:
Provided further that where the Central Government or the State Government
notifies, or has notified, any generation based incentive (GBI) scheme for a particular kind
of renewable technology, such technology based generating station shall be assumed to have
availed the benefit of such a scheme and their tariffs shall be reduced by the amount of
generation based incentive (GBI) per unit for the period during which such incentive
remains applicable.
(2) Where any additional project specific grant or budgetary support is available to
any project, apart from the incentive and/or subsidy and/or grant available under sub-
regulation (1) of
1
Ins. proviso vide Not. No. HPERC/428 dated 20
th
November, 2020, published in R.H.P. dated 24
th
November, 2020 at p. 5421-5423.
Compendium of HPERC Regulations, March 2021 41
this regulation, the Commission shall account for such budgetary support also, while
determining
project specific levellised tariff.
(3) The amount of subsidy shall be considered for each renewable source as per the
applicable policy of the MNRE/State Government/Central Government and if the amount
and/or mechanism of subsidy is changed by the MNRE/State Government/Central
Government, consequent corrections in tariffs may be carried out by the Commission in
accordance with regulation 20.
23-B. Debt-Equity Ratio.—(1) The normative debt equity ratio shall be 70:30.
(2) For generic levellised tariff, the Commission shall adopt debt equity ratio of
70:30:
Provided that for arriving at the amount of debt and equity, the debt equity ratio shall
be considered after deducting, from the normative capital cost, the amount of incentive,
grant and
capital subsidy available for the project.
(2) For project specific levellised tariff, the following provisions shall apply—
(i) if the equity actually deployed is more than 30% of the net capital cost
arrived at after subtracting the incentive, grant and capital subsidy from the
capital cost admitted by the Commission under regulation 15, the equity
deployed in excess of 30% limit shall be treated as normative loan in
accordance with the National Tariff Policy and shall be deemed as advanced
at the weighted average rate of interest and for a weighted average tenor of
the long term debt component of the project after ascertaining the
reasonableness of the interest rates and taking into account the effect of debt
restructuring, if any;
(ii) in case the equity deployed is equal to or below the normative level of 30%,
the actual equity would be used for determination of Return on Equity in
tariff computations;
(ii) the equity invested in foreign currency, if any, shall be designated in Indian
rupees on the date of each investment.
(iv) for arriving at the amount of equity in cases involving project specific
determination of tariff, the debt equity ratio shall be considered after
deducting, from the capital cost admitted by the Commission under
Regulation 15, the amount of incentive, grant and capital subsidy available
for the project.
Explanation.—For the purposes of return on equity, any resources available to the
renewable energy generator from its share premium account or from its internal
resources that are used to fund the equity commitments of the project under
consideration shall be treated as equity subject to the limitations contained in this
regulation and regulation 26-B.
42 Compendium of HPERC Regulations, March 2021
(4) The Commission shall treat any incentive or subsidy and/or grant/ budgetary
support available from the MNRE/State Government/Central Government, to have been
availed and shall adjust the same as per the provisions of these regulations.
24-B. Loan and Finance Charges.—(1) For the purpose of determination of tariff, loan
tenure of 15 years shall be considered:
(2) Interest Rate.—
(a) The loan amount (i.e. the debt component) arrived at in the manner indicated in the
regulation 23-B shall be considered as gross normative loan for calculation of
interest on loan. The normative loan outstanding as on 1st April of every year shall
be worked out by deducting the cumulative repayment up to 31st March of previous
year from the gross normative loan.
(b) For the purpose of computation of tariff(s) under these Regulations, normative
interest rate of two hundred (200) basis points above the average State Bank of India
Marginal Cost of Funds based Lending Rate (MCLR) (one year tenor) prevalent
during the last available six months, prior to the respective date(s) from which such
tariff(s) the respective generic levellised tariffs are to be made applicable, shall be
considered:
Provided that in case where the project specific tariff is to be determined,
such average rate of SBI, as prevalent during the respective periods in which the loan
has been availed, shall be taken into account on weighted average basis and the rate
so worked out on this basis or the weighted average rate at which the loan has been
availed, whichever is lower, shall be considered.
(c) Notwithstanding any moratorium period availed by the renewable energy generator,
the repayment of loan shall be considered from the first year of the tariff period and
shall be equal to the annual depreciation allowed.
(d) The loan repayment for a financial year or the relevant part period thereof shall be
considered to have been done in the middle of that financial year or the relevant part
period thereof, as the case may be.
25-B. Depreciation.—For the purpose of tariff determination, depreciation shall be
computed in the following manner, namely:—
(a) the value base for the purpose of depreciation shall be equal to sum total of the debt
and equity components as per the provisions of regulation 23-B;
(b) the salvage value shall be considered as 10% and depreciation shall be allowed up to
maximum of 90% of the value base as per clause (a) of this regulation:
Provided that no depreciation shall be allowed to the extent of incentive, grant and
capital subsidy available for the project.
(c) depreciation per annum shall be based on “Differential Depreciation Approach”. For
tariff purposes, the depreciation shall be allowed @ 4.67% per annum of the value
base as per clause (a) of this regulation till such time the requirement for repayment
of loan component of the capital cost as per regulations 21-B, 23-B and 24-B is fully
Compendium of HPERC Regulations, March 2021 43
provided and the remaining depreciation shall be spread over the residual useful life
of the project on straight line method;
(d) depreciation shall be chargeable from the first year of commencement of operation of
the project:
Provided that in case of operation of the asset for part of the year,
depreciation shall be charged on pro rata basis for the purposes of project specific
determination of tariff.
26-B. Return on Equity.—(1) The value base for the equity (on which return on equity
shall be calculated) shall be equal to the equity component computed in accordance with the
provisions of regulation 23-B.
(2) The normative Return on Equity shall be 14%. The normative Return on Equity
shall be grossed up by the latest available notified Minimum Alternate Tax (MAT) rate for
the first 20 years of the Tariff Period and by the latest available notified Corporate Tax rate
for the remaining Tariff Period.
27-B. Interest on working capital.—(1) The working capital requirement in respect of
wind energy projects, small hydro power, solar PV and solar thermal projects shall be
computed in accordance with the following:—
(a) operation and maintenance expenses for one month;
(b) receivables equivalent to 45 days of energy charges for sale of electricity calculated
on the net saleable energy corresponding to the CUF considered for tariff
determination on normative basis;
(c) maintenance spare @ 15% of operation and maintenance expenses.
(2) The working capital in respect of biomass power projects with Rankin Cycle
technologies, biomass gasifier based power projects, non-fossil fuel based cogeneration
projects, Municipal Solid Waste power projects and Refused Derived Fuel project shall be
computed in
accordance with the following:—
(a) fuel cost for four months equivalent to normative Plant Load Factor (PLF);
(b) operation and maintenance expenses for one month;
(c) receivables equivalent to 45 days of energy charges (fixed and variable charges) for
sale of electricity calculated on the net saleable design energy on normative basis;
(d) maintenance spare @ 15% of operation and maintenance expenses.
(3) In case of the renewable technologies not covered in sub-regulations (1) and (2),
the Commission may adopt such norms, as it may consider appropriate, at the time of
determination of tariff.
(4) Interest on Working Capital shall be at interest rate equivalent to the normative
interest rate of three hundred and fifty (350) basis points above the average State Bank of
India Marginal Cost of Funds based Lending Rate (MCLR) (One Year Tenor) prevalent
44 Compendium of HPERC Regulations, March 2021
during the last available six months, prior to the respective date(s) from which the generic
tariff(s) are to be made applicable:
Provided that in case where the project specific tariff is to be determined, such
average rate for the last available six months prior to the date from which the project specific
tariff is to be made applicable, shall be considered.
28-B. Operation and maintenance expenses.—(1) Operation and maintenance expenses
mean the expenditure incurred on operation and maintenance of the project, or part thereof,
and includes, without limitation, the expenditure on manpower, establishment (including
employees expense, administrative and general expenses), repairs, spares, consumables,
insurance and overheads as well as the taxes, duties and other levies on any or all such
activities.
(2) Operation and maintenance expenses shall be determined for the tariff period based on
normative operation and maintenance expenses specified in Part-III of Chapter-V of these
Regulations for the
1
[small hydro projects exceeding 100 kW Capacity] and as stipulated in
relevant orders of the Commission for other renewable
1
[energy projects.]
(3) Normative O&M expenses allowed under these Regulations shall be escalated
over the tariff period at the rate of 3.84% per annum.
29-B. Taxes and duties.—Tariff determined under these Regulations shall be inclusive of
all taxes and duties and shall not be subject to any change except for the provisions specified
under regulation 20.
30-B. Rebate.—(1) The due date for payment of bills shall be 45 days from the date of
billing.
(2) For payment of bills of the generating company through revolving and valid letter
of credit on presentation or through National Electronic Fund Transfer (NEFT) or Real Time
Gross Settlement (RTGS) payment mode within a period of 5 days of presentation of bills, a
rebate of 1.5% on bill amount shall be allowed.
(3) Where payments are made on any day after 5 days within a period of thirty (30)
days from date of presentation of bills by the generating company, a rebate of 1% shall be
allowed.
Explanation.—For computing the “5 days” and other cutoff dates for the purposes
of this regulation and regulation 31-B, the number of days shall be counted consecutively
without considering any holiday. However, in case the last day is official holiday, the last
day for these purposes shall be construed as the immediate succeeding working day.
31-B. Late payment surcharge.—The distribution licensee shall make timely payments of
energy bills of the renewable energy generators by assigning priority over and above all
other payments. In case the payment of any bill for charges payable under these Regulations
is delayed beyond a period of 45 days from the date of billing, a late payment surcharge at
1 Subs. the words and figures “small hydro projects” and the words “technologies” for
vide not. No. HPERC/428 dated 20
th
November, 2020, published in R.H.P. dated 24
th
November, 2020 at p.
5421-5423.
Compendium of HPERC Regulations, March 2021 45
the simple interest rate of 1.50% per month shall be levied by the renewable energy
generator for the actual number of days by which the payment is delayed.
32-B. Ceiling norms.—The financial norms, except for capital cost, as specified in this
Chapter of these Regulations, shall be considered as ceiling norms and the same shall not
preclude the licensee or renewable energy generator from agreeing to improved norms,
including operation and maintenance norms, which may lead to overall reduction in the
levellised tariff and in case the improved norms are agreed to, such improved norms shall be
applicable for determination of the project specific levellised tariff.
32-BB. The provisions of this Chapter shall be applicable for all the RE technologies for the
matters to be dealt under third control period irrespective of the intervals at which the
generic levellised tariffs are determined under this control period.]
______________
1
[CHAPTER –V
PART-I
TECHNOLOGY SPECIFIC PARAMETERS FOR SMALL HYDRO PROJECTS
(APPLICABLE FROM 01.10.2017 TO 30.09.2019)]
Previous and next
Questions people ask
Is regulation 32 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.