Regulation 27, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Interest on working capital
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 27
Text of regulation 27
Interest on working capital
27. Interest on working capital.—(1) The working capital requirement in respect of wind
energy projects, small hydro power, solar PV and solar thermal projects shall be computed
in accordance with the following:—
(a) operation and maintenance expenses for one month;
(b) receivables equivalent to 2 (two) months of energy charges for sale of
electricity calculated on the net saleable energy corresponding to the CUF
considered for tariff determination on normative basis;
(c) maintenance spare @ 15% of operation and maintenance expenses.
(2) The working capital in respect of biomass power projects with Rankin Cycle
technologies, biomass gasifier based power projects, non-fossil fuel based cogeneration
projects, Municipal Solid Waste power projects and Refused Derived Fuel project shall be
computed in accordance with the following:—
(a) fuel cost for four months equivalent to normative Plant Load Factor (PLF);
(b) operation and maintenance expenses for one month;
(c) receivables equivalent to 2 (two) months of energy charges (fixed and
variable charges) for sale of electricity calculated on the net saleable design
energy on normative basis;
(d) maintenance spare @ 15% of operation and maintenance expenses.
(3) In case of the renewable technologies not covered in sub-regulations (1) and (2),
the Commission may adopt such norms, as it may consider appropriate, at the time of
determination of tariff.
(4) Interest on Working Capital shall be at interest rate equivalent to the normative
interest rate of three hundred (300) basis points above the average State Bank of India
Marginal Cost of Funds based Lending Rate (MCLR) (One Year Tenor) prevalent during the
34 Compendium of HPERC Regulations, March 2021
last available six months, prior to the respective date(s) from which the generic tariff(s) are
to be made applicable:
Provided that in case where the project specific tariff is to be determined, such
average rate for the last available six months prior to the date from which the project specific
tariff is to be made applicable, shall be considered.
Previous and next
Questions people ask
Is regulation 27 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.