Regulation 22, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Subsidy or incentive or grant/budgetary support by the Central/ State Government
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 22
Text of regulation 22
Subsidy or incentive or grant/budgetary support by the Central/ State Government
22. Subsidy or incentive or grant/budgetary support by the Central/ State
Government.- (1) While determining the generic levellised or project specific levellised
tariff, as the case may be, for the renewable energy project(s) under these Regulations, the
Commission shall take into consideration any incentive and/or subsidy and/or grant available
under the schemes of the Central or State Government or its agencies, but excluding
accelerated depreciation benefit under the Income Tax Act:
1
Sub. for “CHAPTER-IV FINANCIAL PRINCIPLES” for vide not. No. HPERC/428 dated 28
th
January, 2019, published in R.H.P. dated 30
th
January, 2019 at p. 7835-7843.
Compendium of HPERC Regulations, March 2021 31
Provided that for tariff determination, only 75% of the capital subsidy available to
the project as per applicable scheme of the MNRE/State Government shall be considered:
Provided further that the Commission may evolve suitable mechanism(s) for
incorporating impact of the subsidy component for determination or adjustment of generic
levellised tariffs for various categories of projects:
Provided further that the capital subsidy under the schemes of the Central or State
Government or its agencies, shall, unless the circumstances otherwise warrant, be ordinarily
adjusted in the middle of first 12 months from the commencement of the tariff period against
the principal component of the loan amount as additional reduction apart from the normal
payment:
Provided further that where the Central Government or the State Government notifies
or has notified any generation based incentive (GBI) scheme for a particular kind of
renewable technology, such technology based generating station shall be assumed to have
availed the benefit of such a scheme and their tariffs shall automatically be treated as
reduced by the amount of generation based incentive (GBI) per unit for the period during
which such incentive remains applicable.
(2) Where any additional grant or budgetary support is available to any project, apart
from the incentive and/or subsidy and/or grant available under sub-regulation (1) of this
regulation, the Commission shall account for 100% of such budgetary support, while
determining project specific levellised tariff. (3) The amount of subsidy shall be considered
for each renewable source as per the applicable policy of the MNRE/State Government and
if the amount and/or mechanism of subsidy is changed by the MNRE/State Government,
consequent corrections in tariffs may be carried out by the Commission in accordance with
regulation 20.
Previous and next
Questions people ask
Is regulation 22 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.