Regulation 12, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Tariff design
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 12
Text of regulation 12
Tariff design
12. Tariff design.—(1) The single part levellised tariff structure shall be followed for the
renewable energy technologies:
1
Ins. proviso vide Not. No. HPERC/428 dated 8
th
September, 2020, published in R.H.P. dated 15
th
September, 2020 at p. 3561-3570.
2
Omitted of Reg. 11 for vide not. No. HPERC/428 dated 28
th
January, 2019, published in R.H.P. dated
30
th
January, 2019 at p. 7835-7843 and before its omission read as under-
“11. Special provisions for Small Hydro Projects.—
(1) Where the first Implementation Agreement of a small hydro project has been executed on or before 31st December,
2014 and neither any joint petition for approval of the Power Purchase Agreement has been filed before, nor any power purchase
agreement, whether under REC Mechanism or otherwise, has been approved by, the Commission for such project prior to the date
of commencement of these Regulations, the norms, tariffs and osther associated terms and conditions as per Himachal Pradesh
Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for
Tariff Determination) Regulations, 2012, shall be applicable in the same manner as applicable to the small hydro projects covered
in the said Regulations:
Provided that for the purpose of this regulation, the date of signing the first Implementation Agreement of the small
hydro project shall only be taken into account and the Supplementary Agreement(s), if any, executed thereafter due to any reason,
but other than due to enhancement of capacity, whatsoever, viz for extension of the scheduled completion date, shall not be
considered:
Provided further that in cases where the power purchase agreements have already been approved by, or the joint
petitions for approval of the power purchase agreement(s) have been filed before, the Commission prior to the date of
commencement of these Regulations, the tariff(s) for such small hydro projects shall be governed as per the provisions of power
purchase agreements and relevant Regulations irrespective of the dates on which such agreement(s) are actually approved and/or
executed:
Provided further that if a Supplementary Implementation Agreement is executed on or after 1st January, 2015 to provide
for enhancement of capacity, the tariff and other terms and conditions as per regulation 14 and regulations 20 to 41 shall be
applicable only for the incremental energy generation as per the provisions under regulations 17.
(2) Save as provided in sub-regulation(1), the tariff determined under the regulation 14 and regulations 20 to 41 shall be
applicable only for such small hydro projects where—
(i) the 1st Implementation Agreement has been signed on or after 1st January, 2015;
(ii) no power purchase agreement, whether under REC Mechanism or otherwise, has been approved by the Commission
before the date of commencement of these Regulations; and
(iii) the RE generator implementing the small hydro project has neither filed joint petition for approval of PPA before the
Commission, nor has commenced the operation of its project, prior to the date of commencement of these
Regulations.”
Compendium of HPERC Regulations, March 2021 13
Provided that for renewable energy technologies having fuel cost component, like
biomass power projects and non-fossil fuel based cogeneration, single part tariff with two
components, i.e. fixed cost component and fuel cost component, shall be determined.
(a) The following fixed cost components shall be included for determining the tariff:-
(b) Return on equity;
(c) Interest on loan capital;
(d) Depreciation;
(e) Interest on working capital; and
(e) Operation and maintenance expenses.
(3) The generic or project specific tariff shall be determined on levellised basis for
the tariff period:
Provided that tariff for renewable energy technologies, having single part tariff with
two components, referred to in the proviso to sub- regulation (1), shall be determined on
levellised basis for the tariff period in respect of the fixed cost component and the fuel cost
component shall be specified on year of operation basis.
(4) For the purpose of levellised tariff computation, the discount factor equivalent to
the post tax weighted average cost of capital shall be considered.
Previous and next
Questions people ask
Is regulation 12 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.