Form 4
Form 4
Abstract of admitted parameters for the existing transmission assets/elements under project
Name of the Petitioner: ______________________________
Name of the Region: ______________________________
Name of the Project: ______________________________
Name of the Transmission Element or ______________________________
Communication system:
(Amount in Rs Lakh)
Asset- 1 Asset- 2 ….
Name of the Assets
DOCO
Petition Number Total Gross
Tariff order date Block as on
Capital Capital
1st. April of the first year of
the control period
Particulars
Expenditure Expenditure
admitted as admitted as
on 1st. April of the first
year of the control peri-
od
on 1st. April of the
first year of the con-
trol period
Apportioned approved
Cost/Revised cost
estimates, if any (with
reference and date of
approval)
Freehold Land
Leasehold Land
Building & Other Civil
Works
Transmission Line
Sub-Station Equipments
PLCC
Total
Notional Loan
Notional Equity
Total
Debt-Equity Ratio
Debt
Equity
Total
Cumulative amount of
Depreciation
Cumulative Repayment of Loan
Initial Spares*
1 * Initial spares claimed for existing whose cut off date falls in current tariff period.
Details of remaining assets of the project yet to be commissioned needs to be included in Form -5B
Petitioner
168 DELHI GAZETTE : EXTRAORDINARY [PART III]
Previous and next
Questions people ask
Is form 4 of Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2017 still in force?
No repeal of Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2017 is recorded.