Form R-3, Rajasthan Real estate Regulatory authority Regulations 2017: FORM R-3
Rajasthan Real estate Regulatory authority Regulations 2017 - Form R-3
Text of form R-3
FORM R-3
FORM R-3
[see Regulation3(4)]
CERTIFICATE BY CHARTERED ACCOUNTANT(On Letter Head)
withdrawal ofmoney from separate account)
Cost calculation ofReal Estate Project..............604
(to be uploaded by the Promoter on his webpage on the RERA website before
RERA Registration Number...............0cecsesecceaneees
Sr. Particulars Estimated Incurred amourat
No. Amount in Rs. in Rs.
(@) - (2) 3) (4)
1 1. (A) Land Cost :
(i) | revenue or area snare given to land
owner in lieu of land under any kind
of agreement such as Joint Venture,
Joint Development etc, in case the
Promoter is not the owner of the land,
(ii) |amount paid to land owner,
(iii) incidental costs related to acquisition
of land such as stamp duty,
brokerage, settlement costs of
litigation, premiums paid to
government authorities related to
land,
(iv) interest on finance for purchase of
land,
(v) litigation costs incurred for land
acquisition,
(vi) property and other taxes, fees,
premiums paid.
Sub-Total of LAND COST
(B) Development Cost/ Cost of
Construction:
(a)(i) Total cost incurred by promoter
towards the on site expenditure for
physical development of the project,
(ii) Fees payable to the architects,
consultants, project manager/staff
including engineers, marketing
agents,
Actual Cost of construction incurred
us per the books of accounts as
’ verified by the CA.
Note: (for adding to total cost of
construction incurred,
15
minimum of (i) or (ii) is to be
considered).
(iii) On-site expenditure —_— for
development of entire project
(excluding cost of constructionas
per (i) or (ii) above), i.e. salaries,
consultants fees, site Overheads,
development works, - cost of
services (including water,
electricity, Sewerage, drainage,
layout roads eic.), cost of:
mochineries and equipment
including its hire andmaintenance
Costs, consumables etc. All costs
directly incurred to complete the
construction of the entire phase of
the project registered,
b.. Payment of Taxes, cess, fees, charges,
Approval cost for construction — etc.
premiums, interest etc. to any statutory
Authority.
c. Principal sum and interest payable to
financial institutions, scheduled banks,
non-banking financial institution CNBFC)
or money lenders on constructionfunding
or money borrowed for construction &
Project.
Sub-Total ofDevelopment Cost
2. Total Estimated Cost of the Real Estate
Project 1(A) + 1(B)] of Estimated
Column.
3. Total Cost Incurred of the Real Estate
Project [1(A) + 1(B)] of Incurred
Column.
4. Percentage completion of construction
work (as per Project Architect’s
Certificate)
5. Percentage of the Cost incurred on Land
Cost to the Total Estimated Cost.
6. Percentage of the Cost incurred on
Construction Cost to the Total Estimated
Cost.
7. Amount which can be withdrawn from the
Separate Account. (to_be calculated as
16
below)
Total Estimated Cost (item 2 above)xtotal
é percentage of cost incurred (as mentioned at
item 5 & 6)
8. Less: Amount withdrawn till date of this
certificate as per the Books of Accounts
and Bank Statement.
9. Net Amount which can be withdrawn
from the Separate Bank Account under
this certificate.
This certificate is being issued for the Project.................... (RERA Registration
INOvecessoeces) in compliance of the provisions of section 4 (2) (1) (D) of the Act and is
based on the records and documents produced before me and explanations provided to
me by the management of the Promoter.
Yours Faithfully,
Signature of Chartered Accountant
17,
(Membership Number............. )
Name
Previous and next
All provisions of Rajasthan Real estate Regulatory authority Regulations 2017