Circular_no_1920018 24 05 19
Circular - THE UTTAR PRADESH GOODS AND SERVICES TAX ACT, 2017
- Kind: Circular
- Under: THE UTTAR PRADESH GOODS AND SERVICES TAX ACT, 2017
Text of this circular
F. No. 354/32/2019-TRU
Government of India
Ministry of Finance
Department of Revenue
(Tax Research Unit)
Dated the 14"° May, 2019, New Delhi
Subject: FAQs (Part Il) on real estate- reg.
A number of issues have been raised regarding the new GST rate structure notified for
real estate sector effective from 01-04-2019, A compilation of Frequently Asked Questions
(FAQs) containing 41 questions was issued on 7 May, 2019. Part II of the FAQ is presented
below. The answers to the FAQs have been given in simple language for guidance and easy
understanding of all stakeholders in the real estate sector. They do not have force of law. In
case of conflict, the gazette notifications, which have legal force, shall have precedence,
SI.
No,
Question Answer
ls In case of an area sharing
arrangement between a
Landowner-Promoter and a
Developer-Promoter, where the
Project qualifies to be considered
an “Ongoing Project”, whether
an option of 1% or 5% (without
ITC) vis-a-vis 8% or 12% (with
ITC) as prescribed in
Notification No, 3/2019 can be
exercised by the Developer-
Promoter and Landowner-
Promoter independently?
The legal and operational harmony necessitates
that both the Landowner-Promoter and the
Developer-Promoter exercise identical option for a
project.
In case of an area sharing
arrangement between a
Landowner-Promoter and a
Developer-Promoter in a New
Project undertaken on or after
1/4/2019, whether the new rate
of 1% or 5% is applicable in case
of the Landowner-Promoter who
sells the under-construction
premises before completion of
the project?
Will the Landowner-Promoter be
entitled to ITC in respect of tax
The new effective rates of 1% and 5% without ITC
are applicable to the apartments booked by the
land owner promoter in an ongoing project as well
as a new project which commences on or after 01-
04-2019. The land owner promoter shall be
entitled to ITC in respect of tax charged to him by
the developer promoter on construction of such
apartments. However, the land owner promoter
shall not be entitled to avail ITC on any other
services or goods used by him.
charged to him by _ the
Developer-Promoter on such
supply?
Whether the —Landowner-
Promoter shall be entitled to
avail ITC on any other services
or goods used by him in
furtherance of his business (such
as brokerage on sales etc.)?
Residential Real Estate Project
(RREP) shall mean a REP in
which the carpet area of the
commercial apartments is not
more than 15% of the total carpet
area of all the apartments in the
REP (Clause xix), “Carpet area”
shall have the same meaning as
assigned to it in clause (k) of
Section 2 of the RERA, 2016.
Whether non-saleable areas such
as society office, club house,
etc., are to be taken into
consideration for determining
15% for deciding whether the
project is RREP or not?
The term “Residential Real Estate Project (RREP)
has been defined in the notification to mean a REP
in which the carpet area of the commercial
apartments is not more than 15 per cent. of the
total carpet area of all the apartments in the REP.
Apartments shall be taken as commercial or
residential apartments as declared to RERA
authority,
For the purpose of determining
the threshold of Rs.45 lakhs in
case of “affordable residential
apartment”, whether the
following charges generally
recovered by the developer from
the buyer shall be included?
* Amenity Charges
* Society formation charges
+ Advance maintenance
* Legal Charges
For the purpose of determining the threshold of the
gross amount of Rs.45.00 lakh for affordable
residential apartments, all the charges or amounts
charged by the promoter from the buyer of the
apartments shall form part of the gross amount
charged. Clause xvi, sub-clause (a)(iiXC) of
paragraph 4 of notification No. 11/2017-CT(R)
dated 28.06.2017, reproduced below, refers.
“C. Any other amount charged by the promoter
from the buyer of the apartment including
preferential location charges, development
charges, parking charges, common facility
charges etc."
However the value shall not include stamp duty
payable to the statutory authority, maintenance
ey
charges / deposits for maintenance of apartment or
maintenance of common infrastructure.
In case of a Real Estate Project,
comprising of Residential as well
as Commercial portion (more
than 15%), how is the minimum
procurement limit of 80% to be
tested, evaluated and complied
with where the Project has single
RERA Registration and a single
GST Registration and it is not
practically feasible to get
separate registrations due to
peculiar nature of building(s)?
n ins
The promoter shall apportion and account for the |
procurements for residential and commercial
portion on the basis of the ratio of the carpet area
of the residential and commercial apartments in
the project.
ee ee
In an area sharing model, @
promoter has to handover
constructed flats/ apartments to
the land owner who supplied
TDR for the project. Value of
TDR at the time when the
landowner transferred it to the
promoter is not known. How
would the promoter determine
GST on TDR?
Value of TDR, shall be equal to the amount
charged by the promoter for similar apartments
from the independent buyers booked on the date
that is nearest to the date on which such
development rights or FSI is transferred by the
land owner to the promoter.
In the formula prescribed unde
r
first proviso to Entry 41A of the
Notification 12/2017- CT (R), as
amended by Notification 4/2019
CT (R), what rate shall be taken
to determine the value to be
ascribed to the “GST Payable on
TDR or FSI of both for
construction of the residential
apartments in the project but for
exemption contained therein” as
no specific rate has been
prescribed = in Notification
11/2017 CT-Rate or any other
notification?
What is the mate applicable to
output supply of TDR or FSI?
The GST on transfer of development rights or FSI
(including additional FSI) is payable at the rate of
18% (9% + 9%) with ITC under SI. No. 16, item
Whether the quantum of TDR or
(iii) of Notification No. 11/2017 - Central Tax
(Rate) dated 28-06-2017 (heading 9972).
There is no exemption on TDR or FSI (Addl. FSI)
for construction of commercial apartments.
Therefore, GST shall be payable on TDR or FSI
(including additional FSI) or both used in respect
of
(i) carpet area of commercial apartment and
(ii) un-booked residential apartments as on the
date of issuance of Completion Certificate or
first occupation of the project for the purpose
of formula.
Yee
FSI (including additional FSI) or
both shall be taken only in
respect of un-booked apartments
as on the date of issuance of
Completion Certificate or first
occupation of the project for the
purpose of formula?
In case of Redevelopment, Slum
Rehabilitation or similar
arrangements, the Developer will
be constructing two types of
units i.e. one which is allotted to
existing occupiers for no
monetary consideration and
second which is sold in the
market to outside buyer. Price at
which the unit is being sold to
the outsider is determined in a
manner to factor cost of
construction of both type of units
so that the unit to existing
occupiers may be allotted free of
monetary consideration. It may
be clarified whether the Input
Tax Credit in relation § to
construction of units to be
allotted to existing occupiers, in
case of residential project opted
for old rates or commercial
projects, shall be allowed to the
Developer.
The apartments given to the original inhabitants or
the slum dwellers in redevelopment project or
slum rehabilitation project are given by the
promoter against consideration received by them
in the form of TDR/ FSI/ monetary consideration
from the original inhabitants in case of
redevelopment projects and from the Government
in case of slum rehabilitation projects. The supply
of service by way of construction of such
apartments against construction wholly or partly in
the form of TDR/FSI is a taxable supply subject to
GST.
Wherever tax is paid on construction of such
apartments at the effective rates of GST of 8%/
12% with ITC, the promoters shall be cligible for
ITC, including ITC in relation to construction of
units to be allotted to the existing occupiers even
though there may not be a monetary consideration
but the consideration is in the form of grant of
TDR/FSI.
In case of redevelopment or slum
rehabilitation project, (new or an
existing project) whether the
constructed units supplied to
existing occupiers by the
developer free of monetary
consideration are taxable?
In case of ongoing project in
respect of which the promoter
has opted for new rates of 1% /
5%, it may be clarified whether
Yes, units supplied free of cost also attract GST as
their consideration is not money but TDR/ FSI or
rights relatable to land on which construction takes
place.
In such an ongoing project, the units sold in open
market would be eligible for GST rate of 1%
(without ITC), if such units are covered under
Credit Linked Subsidy Scheme, as provided in the
definition of “affordable residential apartments”
given in notification no 11/ 2017- CTR dated
28.06.2017 as amended by notification No.
3/2019- CTR dated 29.03.2019 .
4
the units being supplied free of
monetary consideration _to
existing dwellers will fall within
the definition of affordable
housing when certain units being
sold in the open market are
eligible for concessional rates
under the category of Credit
Linked Subsidy Scheme i.e, sub-
item (da) of item (iv) of SL. No. 3
of notification No, 11/2017-
CTR?
The apartments being constructed in such ongoing
project, for existing slum dwellers/ occupiers shall
be eligible for 1% rate if they meet the definition
of affordable residential apartment, as under-
{a) They have carpet area of Jess than 60 sqm in
specified metropolitan cities or 90 sqm in places
other than the specified metropolitan cities and the
gross amount charged for similar apartments from
independent buyers is not more than rupees 45
lakhs. (Please refer to para 2A of notification No.
11/2017- CTR dated 28.06.2019 as amended vide
notification No. 3/2019- CTR dated 29.03.2019),
or
(b) They are being constructed under any of the
schemes specified in sub-item (b), sub-item (c),
sub-item (d), sub-item (da) and sub-item (db) of
item (iv); sub-item (b), sub-item (c), sub-item (d)
and sub item (da) of item (v); and sub-item (c) of
item (vi), against serial number 3 of the said
notification.
10. What shall be the rate of GST
applicable on projects in respect
of which OC has been issued
prior to 01.04.2019, but the
balance demands are pending?
Such projects are neither projects
which commence on or after
01.04.2019 nor ongoing projects,
Time of supply of the service by way of
construction of apartments in such projects falls
prior to 01.04.2019 and accordingly the rates as
existed prior to 01.04.2019 would apply to such
balance demands.
IL. The affordable residential
apartment should not have a
carpet area exceeding 60 sqm in
metropolitan cities and 90 sqm in
other places. Will the internal
walls of the apartment, balcony
or verandah be included 60/90 sq
meter?
“Carpet area" is defined in clause (k) of section 2
of the RERA, 2016 and the same has been adopted
in the notification.
12. If an un-registered person
transfers development right to a
developer-promoter, then it is
apparently not covered by the
fourth proviso applicable to Promoter shall be liable to pay GST on TDR
transferred by any person whether registered or not
on RCM basis.
clause (i) to clause (id) of serial 3
of Notification No. 11/2017 (as
amended). Will the promoter be
liable to pay GST on TDR
received from an unregistered
land owner?
13. Whether the ITC availed as per
the second proviso applicable to
clause (i) to clause (id) of serial 3
of Notification No. 11/2017 (as
amended) can be adjusted
against the output liability of 5%
11%?
No. GST on services of construction of an
apartment by a promoter at the rate of 1%/ 5% is
to be discharged in cash only.
ITC, if any, may be used for discharging any other
supply of service.
14. If a developer-promoter opts to
pay tax for the ongoing project
of affordable residential
apartment at the new rate, can he
use the ITC available to him
under the second proviso
applicable to clause (i) to clause
(id) of serial 3 of Notification
No. 11/2017 (as amended) for
payment of tax at 1%/5%?
Reply as in Q. No. 13 above.
IS, The condition in Notification No.
3/2019 specifies that 80% of
inputs and input services should
be procured from registered
person, What about expenditure
such as salaries, wages, etc.
These are not supplies under
GST [Sh 1 of Schedule III].
Now, my question is, whether
such services will be included
under input services for
considering 80% criteria?
Services by an employee to the employer in the
course of or in relation to his employment are
neither a goods nor a service as per clause | of the
Schedule Il of CGST Act, 2017, Therefore,
salaries and wages paid by promoter to his
employees will not be relevant for the minimum
purchase requirement of 80% .
16. A buyer has booked an
apartment prior to Ist April,
2019 and paid part consideration
to the developer. The developer
decides to opt for the new
scheme for this ongoing project.
Will the buyer be required to pay No. For the past payments made before the
transition date (01.04.2019), no additional GST is
required to be paid.
any additional tax for such
payment he has made prior to
31st march, 2019?
17. Whether the condition of
receiving 80% of inputs and
input services from the registered
person shall be applicable if the
developer opts to continue to pay
tax at the old rates of 12%/8% in
respect of an ongoing project?
No, if the developer opts to continue to pay tax at
the old rates of 12%/8% in respect of an ongoing
project. the condition of receiving 80% of inputs
and input services from the registered person
doesn’t apply.
18. Whether the inward supplies of
exempted goods / services shall
be included in the value of
supplies from unregistered
persons while calculating 80%
threshold?
Yes. Inward supplies of exempted goods / services
shall be included in the value of supplies from
unregistered persons while calculating 80%
threshold.
19; Whether the purchase of Land
from an unregistered person shall
be required to be included in the
value of Input and Input Services
for the purpose of calculation of
80% threshold?9
No. As per Schedule II, Entry No 5, of CGST
Act, sale of land is not a supply, In addition, as
per Sth proviso to entries at SI. No. (i), (ia), (ib),
(ic) and (id) against Serial No 3 in the Notification
No.1] / 2017-CTR dated 28.06.2017 as amended
by Notification No. 3 / 2019-CTR dated
30/03/2019, transactions by way of grant of
development rights, long term lease, FSI etc. are
not required to be included in the value of Input
and Input Services for evaluation of criteria of
80% from registered persons.
20.
When a developer prefers the
option of paying tax at 1%/ 5%,
without ITC, for an ongoing
project, whether the apartments
which were not considered as
affordable in the earlier scheme
(though certain apartments in
such project were considered as
affordable in the earlier scheme)
will be considered as affordable
after Ist April, 2019, if such
apartments fit the definition of
affordable residential apartments
as provided in notification No.
3/2019- CT(R) dated
29.03.2019?
Yes, in case of an ongoing project in respect of
which the promoter has not opted to pay GST at
the old rate, he shall pay tax at the effective rate of
1% without ITC on apartments which meet the
new definition of affordable residential apartment.
21. Whether the amended rule 42
shall apply to all RREPs
including ongoing projects?
In case of an ongoing RREP, in respect of which
promoter opts for the new rates of 1% / 5% and
which underwent transition of ITC consequent to
change of rates of tax on 01.04.2019, ITC
determined under sub- rule (1) of rule 42 shall not
be required to be calculated finally on the
completion or first occupation of the RREP.
22. Whether separate Form
(Annexure IV) shall be filed by
the Developer in respect of each
of the Ongoing Projects?
Yes.
The promoter has to exercise the option for
payment of tax at the old rates of 8%/ 12% with
ITC for each of the ongoing projects separately.
23. On what basis a Contractor /
Sub-contractor executing 4
composite supply of works
contract in terms of clause (va)
ie. 12% for affordable
residential apartments, — shall
satisfy himself as regards
condition of 50% of the total
carpet area?
The contractor may charge tax on the works
contract service provided by him to a promoter at
the concessional rate of 12% under notification
No. 11/2017- CTR dated 28.06.2019, S. No.3,
entry (va) on the basis of a declaration by the
promoter to the contractor that the project meets
the conditions prescribed for concessional rate of
GST on works contract service prescribed under
the said entry.
24. Whether the condition to make
payment within 180 days by
Land Owner — Promoter to
Developer — Promoter as
provided in second proviso to
section 16 (2), shall be
applicable for reversal of input
tax credit ?
The apartments given to the Land Owner —
Promoter are given by the Developer — Promoter
against consideration received by him in the form
of TDR from the Land Owner — Promoter.
Therefore, the payment by Land Owner —
Promoter for service of construction of apartments
received from the Developer — Promoter is made
even before the service is provided.
Therefore, Land Owner — Promoter shall not be
required to reverse input tax credit of tax charged
from him by the Developer — Promoter on the
ground that he has not made payment for the
service received from the Developer — Promoter.
25. Whether the exemption given by
way of Entry 41A / 41B of
Notification No. 12/2017-CTR
shall be available in respect of
development rights etc,
transferred to a person other than
promoter? Please clarify whether The exemption is available only on TDR/ FSI
transferred on or after 1" April, 2019 for
construction of residential apartments by a
promoter in a real estate project.
sub-clause (v) in clause (zk) in
section 2 in RERA Act, 2016
covers a person who purchases
TDR as developer?
26, How to determine value of
construction services provided
by the promoter to land owner in
lieu of transfer of development
rights, when land owner is not
registered?
Value of construction services provided by the
promoter to land owner in such cases shall be
determined based on the total amount charged by
the promoter for similar apartments in the project
from independent buyers, other than the land
owner, nearest to the date on which such
development right etc. is transferred to the
promoter, less the value of transfer of land, if any,
as prescribed in paragraph 2 of Notification No.
11/2017-CT(R) dated 28.06.2017,
27,
In case of a project, where
completion certificate has been
received prior to 31-03-2019 but
some part of the consideration in
relation to the apartment is due
after 31-03-2019, it appears that
such project will not qualify as
ongoing project.
What will be the applicable tax
rate on such amount received on
or after 01.04.2019 — old rate or
new rate?
Time of supply of service of construction of such
apartments is prior to 01.04.2019 and the same
shall be subject to tax at the old rates of 12%/8%.
F. No. 354/32/2019-TRU
eevee