Rule 77, .lharkhand Building Bye-laws 2016: Restriction on Compounding

.lharkhand Building Bye-laws 2016 - Rule 77

Text of rule 77

Restriction on Compounding

77. Restriction on Compounding.- 77.1 Any deviation pertaining to unauthorized development shall not be compounded; 7.1.1 Where construction has been undertaken on Government land or land belonging to local body or land not owned by the person undertaking such development; CHAPTER IX COMPOUNDING, PENALTIES AND COMPLIANCE Jharkhand Building Byc-Laws-2016 81.1 Telecom Tower Permission with appropriate fees, should be obtained from the authority before erection on prescribed forms with certificate for structural safety from the competent Engineer. An application form for the erection of telecom/phone tower for obtaining N.O.C from Authority on form Annexure-lV. Fee shall be as per Jharkhand Communication Tower and Related Structure Policy, 2015. NOC shall be issued within maximum 60 days from date of application if relevant papers in order. Certificate of permission/NOC and related indemnity bond format shall be as per above mention policy, subject to approval from Airport Authority as and where required. ~ ~ f -105- 80. System for monitoring 80.1 A system for monitoring shall be put in place by all authorities to ensure that the Bye laws are followed and prompt action shall be taken in case of violation of these bye laws. 81. Telecom Tower Permission Compounding amount 79.1 At least 50% of the compounding amount shall be utilized for development of public utility services and protection of heritage sites and structures. 79. Note:-Where development has been undertaken in deviation to the approved plan, but within the framework of use, restriction and the provision of norms and stipulations of these Bye-Laws. Fees as the provision made in sub-section-9.7.3 . ... For Height deviation additional compounding fees shall be levied @ Rs. 2500 per sqm. on the area of the top most floor which height is increased. Compounding fees (in Rs.) per sqrn. for the violated area SI. Situations Residential/ Others Institutional 1 Where development has been undertaken without permission, but within the framework of use 10000 15000 restrictions and the provisions of the Bye laws applicable to concerned plot 2 Constructions beyond permission but within the 15000 25000 limit of 10% as mentioned as in section-77.3.3 in bye-laws of the gross areas on all floor thus in violation beyond the permitted setback line or beyond the permissible limit of FAR Table 25: Compounding rate 78. Compounding Rate 78.1 Compounding Rates for various categories shall be as per Table- 25; .. offending areas/part of the building. The owner/builder hall carry out the demolition and take all precautions to ensure the structural safety of the remaining part of the building and ensure that no damage is caused to life and property in any way. Jharkhand Building Bye-Laws-2016 - 106 - .,.. 82.1 The State Government shall set up an integrated E-Governance system to be used by all the authorities. All the applications and the associated documents to be submitted to the various authorities under these byelaws shall be submitted through the E-Governance system. 82.2 All notices shall be issued through the E-Governance system. 82.3 The E-Governance system shall have an inbuilt reminder mechanism to approve applications wherever provisions have been made for approval within a specified time limit under these bye-laws. 82.4 The E-Governance system shall periodically, generate reports of occasions where the Authorities have failed to perform their statutory duties within the prescribed time. The Authorities shall with their comments forward these reports to the State Government at periodic intervals specified by the State Government. 82.5 Single Window Clearance shall be facilitated through E-Governance system. 82.6 The contents of various forms used in this Bye-laws may be added/ modified for the purpose of "Ease of Doing Business" and or digitization/computerization/in process of installation of online ;system~r 82. E-Governance CHAPTER-X E-GOVERNANCE AND SERVICE DELIVERY Jharkhand Building Bye-Laws-2016 - 107 - numum se ac an e1g 0 rest en ia Ul mgs Building Height Upto Building Height Building Height Upto Average G+2 Maximum- tom Upto G+3 G+4 Maximum-lSm Maximum-12m SI. Depth of Minimu Minimu Minimu plot (In Minimum Minimum m Front m Rear m Front Minimum meters) Front set Rear set set back set back set back Rear set back (m) back (m) (m) (m) (m) back (m) (i) (ii) (iii) (iv) M (vi) (vii) (viii) Exceeding I 15m & 3.0 1.8 3.0 2.0 3.0 2.0 upto 33111 Exceeding 2 33111 & 4.0 3.0 4.5 3.0 4.5 3.5 upto 45 m 3 More the 4.0 3.0 4.0 4.0 5.0 5.0 45111 '"\ dY ,71~" id ti I b 'Id' tb ks d h . ht f 83 8 M" . Length of road limitation Maximum Length of the road in Minimum width of road of street in SI. Meter Meter (Inclusive of passive Development) (i) (ii) (iii) I Upto I 00 m 3 .6 meter 5 .1 2 Exceeding I 00 meter and upto 300 4.5 meter 6.6 meter 3 Exceeding 300 6.6 meter 7.5 83.4 Affordable housing shall consist of row houses, stand alone and multi storied low rise and high rise building. 83.5 o Affordable Housing shall be permissible on plots of area less than l 500sqm. 83.6 In order to facilitate affordable housing following deviations from Jharkhand Building Bylaws shall be permitted. 83.7 Means of access 83. "Affordable Housing Project" shall mean housing projects where 35% of the houses are constructed for EWS/LIG category. 83.1 "Affordable Housing Units" shall mean dwelling units for EWS and LIO households only; 83.2 Economically Weaker Section (EWS): EWS households are defined as households having an annual income up to Rs.3,00,000 (Rupees Three Lakhs) or state shall have the flexibility to re-define the annual income criteria as per local conditions in consultation with the Centre. 83.3 EWS House : An all-weather single unit or a unit in a multi-storied super structure having carpet area of up to 30 sqrn. with adequate basic civic ervice and infrastructure services like toilet, water, electricity etc. CHAPTER-XI AFFORDABLE HOUSING Jharkhand Building Bye-Laws-2016 - 108 - EWS LIG Living Room Flooring Dining Room Kitchen and Bed Room Ceramic Tiles Ceramic Tiles Skirting Verandah (30011101 x 300m111) (300mm x 300mm) ( I 0011101- Balcony ht) Passages Lobby Anti Skid Ceramic Anti kid Ceramic Flooring Toilet Tiles Tiles (300mm x300111111) (300111111 x300mm) Wall Tiles/ Kitchen Ceramic wall tiles Ceramic wall tiles Dado 600mm height on (300mm x 200mm) (300mm x 200mm) platform 83.16 Norms for Solar power and solar water heating shall not be applicable. 83.17 Minimum Specification of Affordable Housing shall be as follows- Carpet Area- 30sqm. Carpet Area- 60sqm. EWS LIG 86.15.1 86.15.2 83.11 Distance between the blocks shall not be less than l/41h the height of the building subject to minimum 4.5 meters. 83.12 Parking: EWS: car parking for 50% of the units, balance 2 wheeler parking LIG & MIG: car parking for I 00% of the units 83.13 FAR permissible-3.5 83.14 All Projections for Balcony shall not be part of Carpet Area and FAR. 83.15 Affordable Housing shall be within following criteria- ug rise UI mgs un ess o · 1crw1se spec1 1e Exterior open spaces to be left out on all I. Height of the Building Upto (m) sides in m. (front setback) Side and back 1 More than 15 and upto 18 6.5 4.5 2 More than 18 and upto 21 7.0 4.5 3 More than 21 7.5 4.5 83.10 Minimum exterior open spaces around the buildings for all type of I. h . b 'Id' I ti ifi d mrmum st e set ac s or rest cntia UI mgs Average Width Building Height Building Height Building Height SI. of plot (In Upto G+2 Upto G+3 Upto G+4 meters) Maximum-lOm Maximum-12m Maximum-IS m (i) (ii) (iii) <ivl (v) fvil (vii) (viii) 3 Exceeding I 5m 1.5 1.5 1.5 1.5 2.0 2.0 & upto 27m 5 Exceeding 27m 2.0 2.0 2.5 2.5 3.0 3.0 & upto 39m 7 Exceeding 39m 3.0 3.0 3.60 3.60 4.50 4.50 & upto 45m 8 More the 45m 3.60 3.60 4.00 4.00 5.00 5.00 id ' I b 'Id' b k f 'd 839 M' ' Jharkhand Building Bye-Laws-2016 - 109 - I Toilet Ceramic wall tiles Ceramic wall tiles 2000mm height (300mm x 200mm) (300mm x 200mm) Floor and Kota/ marble/ Kota/ marble/ taircase skirting( I OOmm) concrete paver/ concrete paver/ mosaic tiles mosaic tiles Parking Paver Tiles Paver Tile floor External Red Bricks/ Cone. Red Bricks/ Cone. Wall work (200111111 thick) Hollow Blocks/ Hollow Blocks/ Flyash Bricks Flyash Bricks Internal Cone. Hollow Blocks Cone. Hollow Blocks ( 15011 OOmm thick) External 20mm thick cement 20mm thick cement Plaster Plaster in I :4 with Plaster in I :4 with proper waterproofing proper waterproofing Internal 12/15 mm thick 12/15 mm thick Plaster cement Plaster in I :6 cement Plaster in I :6 Kitchen Width approx Kola Stone with Polished Granite Stone with Stainless Platform 525111111 Stainless Steel sink Steel sink 3 track Aluminium 2 track Aluminium Anodised with 2 track Windows Anodised with 4111111 -4mm thick glass and thick glass and I track stainless steel mosquito mesh) External-30mm Doors thick Wooden Commercial Wooden Commercial Internal-25mm Flush Doors Flush Door thick Sanitary White Vitrified/ White Vitrified/ ware porcelain porcelain CP Fittings As per JS! Mark As per ISi Mark Plumbing PVC/uPVC/cPVC PVC/uPVC/cPVC Pipes Pipes External Cement Based Paint Cement Ba ed Paint Paint Internal Oil bound distemper Oil bound distemper Paint over a coat or Plaster over a coat of Plaster of Paris of Paris Electrical work with Electrical work with copper wires in copper wires in concealed PVC concealed PVC conduits, Provision conduits, Provision shall be made for shall be made for sufficient lighting and sufficient lighting and power points. power points. Electrical Required switches Required switches and sockets, and sockets, telephone and TV telephone and TV points. Each bedroom points. Each bedroom shall have min 3 Nos- shall have min 3 Nos- 5 Amp points and 5 Amp points and I No- 15 Amp point, I No- 15 Amp point, MCB as required MCB as required Aluminium fittings Aluminium fittings Hardware including Aldrop, including Aldrop, Fittings tower bolt, handles as tower bolt, handles as per IS I fittings per ISi fittings ~ ~~ /r7!;." Jharkhand Building Bye-Laws-2016 - 110 - SL C.o,mp0:n ent of Buildin·g Requirement; ~0- 3.1 :Efabimble Room (i) In case of ons roomed l:Jouse- Are:JJ 2.5 sq.mr uicludiue' space :or co~ktug Width 2.{ mt. Hetgbt _ 15 mt. (ii) Two roomed i!iou;e- A,e:1 . .5 sq.nu Widt.h ·~ mt. HeLg.b 2. mt. (iii) Eetgt!J;: LU c:.se· of slopin ~ r«.>:';. A t--g. be-ig.bt ::!.6 nu, 1'·!La. height !.Omt. {at eaves) 3.~ Kitcaeu (i} Cooking alcove serving as. Are:JJ ::!.4 sq.m _ cooking space Width l._ mt. Heigh ::!:-4 mt. (ii) Two reemsd house Area 3.3 sq.mt Width 1. - mt. Hetghr -A mt. 3.3 Bathroom Area 1.:? sq.mr Widt.h 1.0 mt. Height _ _:! mt. 3.4 \V.C. Are:JJ 0.9 sq.mt Width 0.9mt. He1g;bt :?.2 mr, - .; Combined ba:h and W .C Area LS sq mt ~-~ Width .Omt. Hetgbr :? .2 nn, 3.6 Balcony 11:ln. WLdtb 0.9m 3.7 Staircase (i) - storeyed - S::.ii,ght Flight °Z<;'idth 0.60 m: (U'J.a) - ·v.r in dm g Width 0.75 :m_ (mm) Min. mad .... - ..:_ __ :, cm. (ii) :, s eoreysd or more Strait Flight Max riser '.::0.0 cm. \Vin ding \\!idth 0.75 m·. (mm) Width 0 .90 mt (min) Mta. TTead 1::5.0cm. Max riser zo O cm. Notes: 1) th« mmn11 nm clear Ji,:;ad 1'0om ::hai! O<' 2.1 111 r. 3.1? Phnth ::vfLD. beLgh 30 cm from me surrounding greund leve-l 3 .'? Lighnug and Yentil-l:jon (2.) one - t:,a~~h. of the room floor area to: dry bo· clim.Me- {b) one sixth of :he room floor a.rea;i foe- we:-bo1 climate ....._ ~ o 83.18 General Building Requirements for Low Income Housing As per I.S.8888-1978. Deep Bore wells/ Deep Bore wells/ Water Shallow wells/ Shallow wells/ Supply Municipal supply Municipal supply lines through Over lines through Over head tanks head tanks Jharkhand Building Bye-Laws-2016 - 111 - amended from time to time . . ~ 86.2 Words and expressions used in these bye laws, but not defined, shall have the ame meaning as respectively assigned to them in the Act or respective Rules and the National Building Code of India, 2005 86. J Where no express provision has been made in respect of any matter connected with planning and building standards by the Act, the Rules, the Development Plan, the Town Planning Schemes, or these Bye laws or by any resolution of the Authority, the provisions of the ational Building Code of India shall be mutatis mutandis. 86. Applicability of National Building Code 85.2 The Authority shall ensure that resources for land acquisition and cost of land are mobilized or are likely to be mobilized within the time frame projected for implementation of such Interim Development Plans. 85.1 The Authority may prepare Interim Development Plans (IDP) for newly included development areas including rayati land within a reasonable time frame so that development may not be held up in the name of pendency of Interim Development Plan. Where such IDP has not been prepared, the general provisions of these bye laws shall apply without any zonal restrictions. 85. Interim Development Plan 84.2 Notwithstanding such repeal, anything done or any action taken under the bye laws so repealed shall be deemed to have been done or taken under these bye laws; 84.1 The Jharkhand Planning Standards and Building Bye Laws 2002 with all its amendments, any other building byelaws framed under Mineral Area Development Authority Act Industrial Area Development Authority Act and associated executive orders are hereby repealed. 84. Repeal and Savings CHAPTER - XII SA VIN GS/REPEALS AND INTERPRETATION Jharkhand Building Bye-Laws-2016 - 112 - ***************************** A Building Bye Laws Review Committee shall be constituted by the Urban Development and Housing Department for periodic review and reconsideration and necessary modification of these Bye Laws. ~ ~/f The Authority may recommend to the Government for relaxation/modification of any of the clauses of these Bye laws in the general interest of the public pertaining to projects/schemes developed by the Govt. agencies and the decision of the Government in this regard shall be final. 89. Relaxation and modification by the Government In case of any dispute in interpretation of these bye Jaws, the decision of the State Government shall be final. 88. Decision of the Government to be final If any Department of Government/Statutory Authority has given any commitment for a project under PPP with the prior approval of Government, but the building plan of such project has not yet been approved by the Authority as on date of enforcement of these Bye laws, such commitment shall be treated to be made under these Bye laws. 87. Prior Commitments Jharkhand Building Bye-Laws-2016 construction non-hazardous, functioning of the services incorporated in the building and for making adequate prcv rsro n for services and equipment for protection from the fire hazards as per the stipulations of the National Building Code, 2005 in the buildings. /?,y,?71> 'v..;"' o/ i/ .>: ~ I j' - 113 - sound 2005 and the BIS standards for safe and C) Duties & Responsibilities:- i) He/She shall be responsible for making adequate arrangements to ensure not only that the work ts executed as per the approval plans but also 111 conformity with the stipulations of the National Code, The minimum qualification for an Architect shall be bachelor Degree in Architecture or equivalent, and registered with the Council of Architecture and not in arrears of subscription. 8) Competence:- The Architect shall be competent to carry out the work related to the building permit as given below and shall be entitled to submit: i) All plans and information connected with the building permit subject to section-16.3.1 ii) Certificate of supervision and completion of all buildings, iii) Preparation of sub-division/layout plans and related information connected with development permit of area upto 4 hectare. iv) Certificate of supervision for development of land area up to 4 hectare. ARCHITECr A) Qualification & Experience:- 1) QULIFICATION, EXPERIENCE & COMPETENCE OF TECHNICAL PERSON AND BUILDER

Previous and next

All provisions of .lharkhand Building Bye-laws 2016

Questions people ask

Is rule 77 of .lharkhand Building Bye-laws 2016 still in force?

No repeal of .lharkhand Building Bye-laws 2016 is recorded.