Form VI, The Jharkhand Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2015: FORM- VI
The Jharkhand Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2015 - Form VI
Text of form VI
FORM- VI
FORM- VI
Government of Jharkhand
Revenue & Land Reforms Department
(Directorate of Land Acquisition)
or
Collector or appropriate Government
Preliminary Notification
(Under Section-11(1) and 15(1) of the Act-30/2013)
Whereas it appears to the Government of Jharkhand/Collector that a total of............. acre land is
required in the Village .............................. P.S. ............................. P.S. No.------------- Circle-----------------
District----------------- for public purpose, namely, project ................................, ------------------
------------------------------------------------------------------------- ----------------------------------------------------------
----- Social Impact Assessment Study was carried out by State SIA Unit and a report submitted.
The summary of the Social Impact Assessment Report is as follows:-----------------------------------------------
----------- ---------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------- A total of ...............
families are likely to be displaced due to the land acquisition. The reason necessitating such displacement is
given below. Additional Collector or officer appointed under Rule 2(b) is appointed as Administrator for
the purpose of Rehabilitation and Resettlement of the affected families. Therefore it is notified that for the
above said project in the Village of ----------------------------------------------------- P.S.------ ------ P.S.
No.-------------------- Circle---------------- District ------------------------ a piece of land measuring, more or
less ------------------ acre viz, ----------------------------------- hectare of standard measurement, whose detail
description is following, is under acquisition:
This notification is made under the provisions of section-11(1) of The Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act no.
30/2013), to all whom it may concern.
Sl.
no.
Survey
plot
no.
Type of
Title
Type
of
Land
Area under
Acquisition
(in acre)
Name & Address
of person
interested
Boundary (Plot No.)
N. S. E. W.
-48-
A plan of the land may be inspected in the office of the District Land Acquisition Officer ---------
----------------- on any working day. The Government of Jharkhand/Collector -cum- appropriate
Government is pleased to authorize the District Land Acquisition Officer.........................and his
staff.................... to enter upon and survey land, take levels of any land, dig or bore into the sub-soil and
do all other acts required for the proper execution of their work as provided and specified in section-12
of the said Act.
Under section- 11(4) of the Act, no person shall make any transaction or cause any
transaction of land i.e. sale/purchase, specified in the preliminary notification or create any
encumbrances on such land from the date of publication of such notification without prior
approval of the Collector.
Objections to the acquisition, if any, may be filed by the person interested within 60 (sixty days)
from the date of publication of this notification as provided under section- 15 of the Act before District
Land Acquisition Officer ………………………………………………………
Date………… Director/Collector
-49-
Form – VI A
Revenue & Land Reforms Department
(Directorate of Land Acquisition)
or
Collector or appropriate Government
Preliminary Notification
(Under Section-11(1) and 15(1) of the Act-30/2013)
Whereas it appears to the Government of Jharkhand/Collector that a total of............. acre
land is required in the Village .............................. P.S. ............................. P.S. No.---------------
Circle----------------District----------------- for public purpose, namely, project --
-----------------------------------------------------------------------------------------------------------------------
----Additional Collector or officer appointed under Rule 2(b) is appointed as Administrator for
the purpose of Rehabilitation and resettlement of the affected families. Therefore it is notified that
for the above said project in the Village of ----------------------------------------------------- P.S.------
------ P.S. No.--------------------- Circle---------------- District------------------------- a piece of
land measuring, more or less ------------------ acre viz, ----------------------------------- hectare of
standard measurement, whose detail description is following, is under acquisition:
Sl.
no.
Survey plot
no.
Type of
Title
Type
of
Land
Area under
Acquisition
(in acre)
Name &
Address
of person
interested
Boundary (Plot No.)
N. S. E. W.
-50-
This notification is made under the provisions of section-11(1) of The Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
(Act no. 30/2013), to all whom it may concern.
A plan of the land may be inspected in the office of the District Land Acquisition Officer --
------------------------ on any working day. The Government of Jharkhand/Collector -cum-
appropriate Government is pleased to authorise the District Land Acquisition
Officer......................... and his staff.................... to enter upon and survey land, take levels of any
land, dig or bore into the sub-soil & do all other acts required for the proper execution of their
work as provided and specified in section-12 of the said Act.
Under section- 11(4) of the Act, no person shall make any transaction or cause any
transaction of land i.e. sale/purchase, specified in the preliminary notification or create any
encumbrances on such land from the date of publication of such notification without prior
approval of the Collector.
Objections to the acquisition, if any, may be filed by the person interested within 60 (sixty
days) from the date of publication of this notification as provided under section- 15 of the Act
before District Land Acquisition Officer .......... ............. ....... .......................... Since the land is
urgently required for the project under section 40 or SIA study exempted public purpose project
under the Act, hence the appropriate Government has decided not to carry out the Social Impact
Assessment Study.
Date…………… Director/Collector
-51-
Previous and next
Questions people ask
Is form VI of the Jharkhand Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2015 still in force?
No repeal of the Jharkhand Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2015 is recorded.