Regulation 7, The Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive Systems based on Net Metering) Regulations, 2015: Procedure for making application and registration
The Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive Systems based on Net Metering) Regulations, 2015 - Regulation 7
Text of regulation 7
Procedure for making application and registration
7. Procedure for making application and registration. - (1) The eligible consumer
may make the application, delivered by post or by hand or through any electronic mode such
as online submission and e-mail etc., as per Form-1, to the local office of
1
[the distribution
licensee to install and connect] the rooftop solar system to the distribution system of the
distribution licensee. The distribution licensee shall make available format of the Form-1 on
its website and also at its local offices.
(2) The distribution licensee shall acknowledge the application
2
[as per the timelines
given in the Table-3 of sub-regulation (9) of this regulation] and take all necessary actions
including sending appropriate communications to the applicant:
Provided that where an application is received through electronic mode, the
acknowledgment and other communication shall be served through such electronic mode
also and its hard copy shall be sent to the applicant by post or by hand delivery.
(3) After checking the feasibility, the distribution licensee shall, except for the cases
covered under sub regulation (4), issue letter of approval to the applicant
3
[as per the
timelines given in the Table-3] of receipt of application. The consumer shall execute the
agreement with the licensee as per Form-2
4
[as per the timelines given in the Table-2;] from
1
Subs. of sub-regulation (1) for the words “the distribution licensee to connect” vide Not. No.
HPERC-H(1)-11/2015dated 6th November, 2018 published in R.H.P. dated 14th November, 2018 at p. 6010-6016.
2
Ins. vide Not. No. HPERC-H(1)-11/2015dated 6th November, 2018 published in R.H.P. dated 14th
November, 2018 at p. 6010-6016.
3
Subs. of sub-regulation (3) for the words “within 30 days” vide Not. No. HPERC-H(1)-11/2015dated
6th November, 2018 published in R.H.P. dated 14th November, 2018 at p. 6010-6016.
4
Subs. of sub-regulation (3) for the words “within 30 days” vide Not. No. HPERC-H(1)-11/2015dated
6
th
November, 2018 published in R.H.P. dated 14
th
November, 2018 at p. 6010-6016.
6 Compendium of HPERC Regulations, March 2021
the date of issuance of letter of approval. The eligible consumer shall thereafter set up
rooftop solar system plant and submit the work completion report alongwith Single Line
Diagram of the synchronizing and protection arrangement issued by the plant supplier/
Engineering Procurement Construction (EPC) contractor as per relevant standards and
specifications
1
[as per the timelines given in the Table-3]:
Provided that the distribution licensee may modify the Net Metering Connection
Agreement Form-2 or add such conditions to it, as it may find necessary;
Provided further that the distribution licensee may, on receipt of request from the
eligible consumer, grant extension for a maximum period of 3 (three) months if it is satisfied
with the progress made by eligible consumer towards installation of rooftop solar system;
Provided further that the approval accorded to the eligible consumer shall
automatically lapse if he does not execute the agreement with the licensee within the period
2
[***] as specified under sub-regulation (3) or rooftop solar system is not commissioned
within the permitted period. In such cases, the eligible consumer may apply afresh for
obtaining approval of the distribution licensee which shall be dealt at par with other
applications received by it in the time frame in which such fresh application is received.
(4) Before any application for setting up rooftop solar plant in the area, covered
under particular distribution transformer is rejected by the distribution licensee due to any
reason, the consumer shall be served with a 15 days notice to attend to the observations and
remove the deficiencies. In case the approval cannot be granted due to non-availability of
capacity, then the application of the consumer may be considered after availability of the
capacity, if the consumer opts so.
(5) The distribution licensee on the receipt of completion report and test result etc.
from the applicant and after site verification to satisfy itself about the fulfillment of
requirements for commissioning of rooftop solar system, shall install at the cost of eligible
consumer and jointly seal the bidirectional energy meter (net meter)
3
[ as per the timelines
given in the Table-3] and plant will be treated as commissioned for net –metering
commercial operations from the date of installation and first reading of such meter. 4[If the
distribution licensee has no stock of meters, the consumer will, upon intimation by the
distribution licensee, purchase the same.]
(6) The eligible consumer intending to avail financial assistance may get his grid
interactive rooftop solar PV project registered with Himachal Pradesh Energy Development
Agency (HIMURJA), being a State Nodal Agency, in online mode or otherwise and
HIMURJA shall acknowledge the same
5
[as per the timelines givenin the Table-4] from the
1
Subs. of sub-regulation (3) for the words “within 240 days” vide Not. No. HPERC-H(1)-
11/2015dated 6
th
November, 2018 published in R.H.P. dated 14
th
November, 2018 at p. 6010-6016.
2
Omitted the words “of 30 days” vide Not. No. HPERC-H(1)-11/2015dated 6
th
November, 2018
published in R.H.P. dated 14
th
November, 2018 at p. 6010-6016.
3
Subs. of sub-regulation (5) for the words “within 10 days” vide Not. No. HPERC-H(1)-11/2015dated
6
th
November, 2018 published in R.H.P. dated 14
th
November, 2018 at p. 6010-6016.
4
Added vide Not. No. HPERC-H(1)-11/2015dated 6
th
November, 2018 published in R.H.P. dated 14
th
November, 2018 at p. 6010-6016.
5
Subs. of sub-regulation (6) for the words “within one week” vide Not. No. HPERC-H(1)-11/2015dated 6th
November, 2018 published in R.H.P. dated 14th November, 2018 at p. 6010-6016.
Compendium of HPERC Regulations, March 2021 7
date of receipt of such request
1
[and, thereafter, if considered eligible, shall record in
principle approval and also take further action to grant subsidy , as per the timelines given in
the Table-4.]
(7) The distribution licensee shall delegate power to local offices, at par with power
delegated for load sanction and release of connection,
2
[ to avoid procedural delay in smooth
implementation of these regulations].
(8) The Commission may, if it finds it expedient to do so, revise, by order, the
procedure contained in these regulations.
3[(9) The distribution licensee, the eligible consumers, State Nodal Agency and the
Chief Electrical Inspector or any competent authority shall adhere to the timelines for
various activities pertaining to them as given in the following Tables-3 and 4, namely:—
Table-3
Activity Responsibility Timeline
(Maximum
Working Days)
Submission of application the consumer Zero date
Acknowledgment of application by the
distribution Licensee.
the distribution Licensee 02
Site Verification/Technical Feasibility &
Issuance of Letter of Approval
(LOA)/Termination*
the distribution licensee
15
Execution of Net Metering Agreement after
issuance of Letter of Approval (LOA).
the distribution licensee
and consumer
15-20
Intimation to the distribution licensee about
expected date of installation of Solar PV
System.
the consumer 30 days prior to
the expected
date of
installation.
Intimation to consumer, after receipt of
intimation from consumer about expected date
of readiness to procure meter if not available in
stocks of the distribution licensee.
the distribution
licensee
7
Installation of Rooftop Solar System including
solar meter and submission of Work
Completion Report/Certificate including
installation of Solar Meter.
the consumer 90-180 days
from issuance of
Letter of
Approval.
Inspection by the Chief Electrical Inspector, or
any other competent authority and intimating
deficiencies, if any.
the Chief Electrical
Inspector or any other
competent authority.
15-20
Removal of deficiencies, if any the consumer 15
1
Added vide Not. No. HPERC-H(1)-11/2015dated 6th November, 2018 published in R.H.P. dated 14th
November, 2018 at p. 6010-6016.
2
Subs. of sub-regulation (7) for the words “for purposes of procedure of these regulations” vide Not.
No. HPERC-H(1)-11/2015dated 6
th
November, 2018 published in R.H.P. dated 14
th
November, 2018 at p.
6010-6016.
3
Added sub-regulation (9) vide Not. No. HPERC-H(1)-11/2015dated 6th November, 2018 published in
R.H.P. dated 14th November, 2018 at p. 6010-6016.
8 Compendium of HPERC Regulations, March 2021
Issuance of Safety Certificate (informing the
distribution licensee) after inspection and
removal of deficiencies if any.
the Chief Electrical
Inspector or any other
competent authority.
5-10
Intimation to the distribution licensee, after
receipt of Safety Certificate to Install Meter.
the consumer 5
Inspection by the distribution licensee and
intimation of deficiencies, if any.
the distribution licensee 15-20
Removal of deficiencies, if any the consumer 15
Permission to synchronise the Solar Rooftop
PV System unit with the Grid.
the distribution licensee 5-7 days after
removal of
deficiencies.
Synchronizing the system with the Grid and
commissioning of the same after receipt of
permission from the distribution licensee and
sealing of meters by the distribution licensee.
the distribution licensee
and consumer
2
Billing Process after receipt of Safety
Certificate from the Chief Electrical Inspector
or any other competent authority.
the distribution licensee
after first
synchronization
with Grid.
*Note.— In case of any deficiency, the distribution licensee to communicate the
same to Consumer and provide an opportunity to rectify the same within a
period of 15 days and in such cases, this timeline shall be got extended
correspondingly.
Table-4
Activity
Responsibility Timeline (Maximum
Working Days)
Submission of Application for
registration and for subsidy after
obtaining Letter of Approval (LOA)
from the distribution licensee.
the consumer Zero date for Subsidy
Process
Acknowledgement of Subsidy
Application by the State Nodal Agency.
the State Nodal
Agency
02
In-Principle Approval for Subsidy the State Nodal
Agency
10
Inspection for release of subsidy on
receipt of request from the consumer &
intimation to be sent to the consumer
regarding deficiencies, if any.
the State Nodal
Agency *
7-10 days after
commissioning of Solar
Rooftop PV System.
Release of Subsidy the State Nodal
Agency
5-10 days after removal
of deficiencies, if any.
*Note.—Joint Inspection by the State Nodal Agency, for achieving the relevant
milestones under Table-3 and Table-4, the Chief Electrical Inspector or any
other competent authority and distribution licensee can reduce the timelines
substantially.]
Previous and next
Questions people ask
Is regulation 7 of the Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive Systems based on Net Metering) Regulations, 2015 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive Systems based on Net Metering) Regulations, 2015 is recorded.