Rule 14, The Karnataka Town and Country Planning (Regularisation of unauthorised Development or Constructions) Rules, 2014.: Sequences of scrutinising the application
The Karnataka Town and Country Planning (Regularisation of unauthorised Development or Constructions) Rules, 2014. - Rule 14
Text of rule 14
Sequences of scrutinising the application
14. Sequences of scrutinising the application.- (1) The Competent Authority shall
scrutinise the application for different types of violated or unauthorised development, in the
following sequences, namely:-
(a) Land use violation;
(b) Unauthorised sub division of plot or layout (converted and non converted); and
(c) Unauthorised development of building.
Provided that if land use violation is not eligible to be regularised as per these rules, the
development under clause (b) and (c) for that property shall not be scrutinised or regularised.
Similarly if the development under clause (b) is not eligible to be regularised as per these rules, the
development under clause (c) for that property shall not be scrutinised or regularised.
(2) Application related to land use violation and unauthorised sub division of land (within
municipal limits) only, shall be forwarded to the concerned Urban Development Authority or
Planning Authority for clearance. The Urban Development Authority or Planning Authority after
collecting statutory fee as prescribed in the Act from the applicant in addition to the fee prescribed
under these rules, shall forward the opinion or clearance to the Competent Authority. The
Competent Authority after receiving the clearance from Urban Development Authority or Planning
Authority shall process and dispose off the buildings violations accordingly.
(3) Application related to regularisation of unauthorised developments beyond municipal
limits and within the Urban Development Authority or Planning Authority limits shall be processed
in accordance with these rules and the Competent Authority shall take necessary steps to process
and dispose them either in consultation with Local Authority or otherwise.
(4) The Competent Authority shall give an opportunity to the applicant of being heard and to
produce documents, if any, in support of his claims, in the event of any discrepancy between the
claims made by the applicant and the scrutiny report. The Competent Authority shall on completion
of the enquiry, pass a provisional order in Form-II.
(5) After scrutinising the application, the Competent Authority shall prepare a scrutiny report
in the prescribed forms for different types of unauthorised developments made (including fees
payable if such developments are eligible for regularisation).
(6) The Competent Authority shall intimate the applicant for payment of shortfall in
regularisation fees (for different types of unauthorised developments) and other fees or charges, if
any within such time limit, but not later than ninety days, as may be specified therein, or reject the
application as the case may be.
(7) Interest shall be levied on the shortfall of regularisation fees and other fees or charges
paid. Interest shall be calculated from the last date eligible for filling application up to the date of
payment.
(8) The applicant after remitting the amount as per the provisional order made under sub-
rule (4) shall inform the competent Authority regarding the remittance or compliance.
(9) If the application for regularisation is rejected, the Competent Authority shall, pass an
order in form IV for rejecting the application for regularisation stating the reason for rejection.
(10) In case, the application for regularisation is rejected, the fees remitted by the applicant, if
any, on his self assessment shall be refunded (excluding scrutiny fee) to the applicant without
interest within sixty days.
(11) On remittance of the shortfall in regularisation fees by the applicant, along with interest,
if applicable, the Competent Authority shall issue Regularisation Certificate in Form- III for the
different types of unauthorised developments.
5
Previous and next
Questions people ask
Is rule 14 of the Karnataka Town and Country Planning (Regularisation of unauthorised Development or Constructions) Rules, 2014. still in force?
No repeal of the Karnataka Town and Country Planning (Regularisation of unauthorised Development or Constructions) Rules, 2014. is recorded.