Text of regulation 11

Preparation of DSM Program Document

11. Preparation of DSM Program Document-- 11.1. For each DSM program included in the DSM Plan, a detailed description shall be provided in a separate Program Document. The description shall include general information, technology, schedule for deployment, budget, cost effectiveness assessment, detailed implementation plan, estimation of savings, etc. 11.2. For each DSM program cost benefit analysis shall be carried out. 12. Approval of DSM Program Document- 12.1. Prior to implementing any DSM program, Distribution Licensee must obtain approval of the Commission. 12.2. Each Program Document shall include the following: i. Description of the program; ii. Objectives and rationale for the program; iii. Consumer segments and estimated level of participation; iv. Estimate of baseline; v. Assessment of program in line with Cost Effectiveness Guidelines issued by the Commission; vi. Mechanism for recovery of cost and performance incentives; vii. Marketing, delivery strategy and Implementation schedule; viii. Implementation mechanism e.g. Energy Service Companies, DSM Bidding, DSM Resource Acquisition, etc. ix. Monitoring and evaluation plan; x. Plan for Training/Seminars/Workshops to increase consumer awareness. 12.3. The Commission shall approve a DSM program if it is in line with the objectives set out in the Regulations. The Commission may direct modification to proposed or on- going programs to ensure consistency with the DSM Objectives, However, the Commission shall allow Distribution Licensee adequate time to notify consumers of program modification. 13. Implementation of DSM programs- 13.1. Distribution Licensee shall undertake effective implementation of DSM programs. 13.2. The implementation of the program shall be undertaken in the manner as approved by the Commission. 13.3. Distribution Licensee shall undertake implementation of quick gain DSM programs. 13.4. Distribution Licensee shall carry out implementation of activities assigned to it either by itself or through engagement of appropriate independent entity. While doing so, the Distribution Licensee shall ensure that continuity and consistency is maintained and interest of the consumers is not compromised. 14. Mechanism for Cost Recovery- 14.1. Distribution Licensee shall identify the net incremental costs, if any, associated with planning, design and implementation of programs. 14.2. Distribution Licensee may propose methodology for recovery of net incremental costs through tariff or any other mechanism. 14.3. In order to qualify for cost recovery, each program must be: i. Approval prior to implementation; ii. Implementation in accordance with the approved program plan and iii. Implemented cost effectively. 14.4. The Commission may direct the Distribution Licensee to undertake DSM programs that may not be cost effective but is highly beneficial to the society. The Commission may make available resources for such project. 15. Monitoring and reporting of DSM Programs- Distribution Licensee shall prepare plan and undertake monitoring and reporting of DSM programs as approved by the Commission while approving the DSM program. 16. Evaluation Measurement and Verification of DSM Program- 16.1. Distribution Licensee shall prepare plan for evaluation, measurement and verification savings from DSM programs. 16.2. Third party Evaluation Measurement and Verification of DSM programs may be undertaken by the Distribution Licensee with the approval of the Commission. While engaging the agency, the Licensee shall ensure that the Agency is not undertaking any other engagement which could conflict with the interests of the consumers in the State. 16.3. Distribution Licensee shall make available necessary information/data to the third party to measure and verify the savings from DSM programs. Chapter V DSM Plan and Program Completion Report 17. Reports on progress of DSM Plan and expenses incurred on implementation of DSM Plan shall be submitted by the Distribution Licensee every six months. 18. The Distribution Licensee will prepare and submit a detailed Program Completion Report and submit the same to the Commission within one month of completion of such program. 19. The Report shall cover the program expenses, achievements, outcomes and outputs, constraints and difficulties faced, conclusions, recommendations, lessons learned and way forward. Chapter VI Incentives 20. The Commission may provide incentives to Distribution Utilities for achieving DSM Objectives as identified in the Regulations. The Distribution utilities may provide incentives to the Consumers with the approval for the Commission to promote DSM activities. Chapter VII Miscellaneous 21. The Commission has made the Regulations vide order dated 25-3-2014 which shall come into effect from 4th April, 2014. The order has been annexed with these Regulations. 22. The Commission may, at any time add, vary, alter, modify or amend any provisions of these regulations. 23. If any difficulty arises in giving effect to the provisions of these Regulations, the Commission may, by general or specific order, make such provisions not inconsistent with the provisions of the Act, as may appear to be necessary for removing the difficulty. 24. The Commission may, from time to time, issue orders, practice directions and guidelines in regard to the specific objectives, targets, DSM Cells, Review/Approval and procedures to be followed for implementation of these regulations. 25. All disputes arising under these regulations shall be decided by the Commission based on an application made by the person aggrieved. By order of the Commission, A.K. SRIVASTAVA Secretary. BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order: 25-3-2014 PRESENT: 1. Hon'ble Sri Desh deepak Verma, Chairman. 2. Hon'ble Miss. Meenakshi Singh, Member 3. Hon'ble Sri Indu Bhushan Pandey, Member IN THE MATTER OF: "UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION (DEMAND SIDE MANAGENMENT) REGULATIONS, 2014" The following were present: 1. Sri Manoj Jain (Head Finance), NPCL 2. Sri Rajiv Goyal (Head Projects) NPCL 3. Sri Avadhesh Kumar Verma, Chairman (UPRVUP) & Member (SAC) Order (Date of Public Hearing 20-03-2014) 1. The Draft Uttar Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2014 was prepared in line with the model provided by the Forum of Regulators (FoR). 2. The draft was posted on UPERC's website on 6th March, 2014 and the comments were invited from CEA, CERC, BEE, SERCS, FOR, UPPCL and Discoms, 3. Through a public notice, published in Times of India and Dainik Jagran on 08-03-2014 comments were also invited from public. 4. Written comments from NPCL were received on 19-03-2014. 5. The public hearing was held in the Commission on 20-03-2014. 6. Based on written submission and discussions during the hearing, the Commission approves the Regulations to be effective from 4th April, 2014 which shall subsequently be sent for notification on the Gazette. (Indu Bhushan Pandey) (Meenakshi Singh) (Desh deepak Verna) Member Member Chairman Place: Lucknow Dated: 25-03-2014

Previous and next

All provisions of Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014

Questions people ask

Is regulation 11 of Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014 still in force?

No repeal of Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014 is recorded.