Regulation 3, Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014: DSM Objectives
Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014 - Regulation 3
Text of regulation 3
DSM Objectives
3. DSM Objectives—
The objectives include:
(i) Power shortage mitigation;
(ii) Seasonal peak reduction;
(iii) cost effective energy savings;
(iv) Lowering the cost of electricity;
(v) Reduction in emissions of greenhouse gases etc.
The Key Elements are:
• Promotion of energy efficient appliances;
• Promotion of energy efficiency in new commercial buildings;
• State-wide education and awareness campaign for energy conservation;
• Improvement in process and operational efficiency in the industrial sector;
• Public procurement of energy efficient appliances;
• Feeder segregation;
• Strategic unitization of energy conservation fund and DSM fund approved
by the regulator;
• Strengthening of SDA.
4. Assessment of technical potential for DSM
4.1. The Distribution Licensee in the State shall carry out assessment of potential for
DSM in the State one year before the start of every Tariff Control Period.
Notwithstanding above provision, the first assessment of technical potential for DSM
shall be carried out within six months of the date of these Regulations which shall be
utilized for ongoing tariff period.
4.2, Distribution Licensee shall be guided by methodology developed by Bureau
while assessing of technical potential for DSM.
Previous and next
Questions people ask
Is regulation 3 of Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014 still in force?
No repeal of Uttar Pradesh Electricity Regulatory Commission (DEMAND SIDE MANAGEMENT) Regulations 2014 is recorded.