Section 110, The Andhra Pradesh Capital Region Development Authority Act, 2014.
The Andhra Pradesh Capital Region Development Authority Act, 2014. (11 of 2014) - Section 110
Text of section 110
110. Application for development permission: (1) Any person or body
intending to carry out any development of land for the purpose of layout or
for sub-division into plots or for construction, reconstruction, addition or
alteration of any building shall apply in writing to the Commissioner for
development permission in such form and containing such particulars and
accompanied by such plans, documents, ownership documents for the land
or plot and on payment of fees and charges as may be prescribed by the
rules and regulations of the Act in addition to statutory provisions made
under the respective Acts of the Local bodies;
1 Ins. by Act 6 of 2015, s.4 (w.e.f.18-4-2015)
2 Subs. by Act 34 of 2018, s.4 (w.e.f. 19-11-2018)
79
(2) On receipt of the application for Development Permission under
sub-section (1), the Commissioner, after making such enquiry as consider it
necessary in relation to any matter concerning the master plan,
infrastructure plan, development plan and regulations, area development
plan, notified development scheme, layout regulations, development
promotion regulations, aesthetics, architectural and urban design control
briefs, landscaping stipulations or in relation to any other matter, may issue
a development permission order either,-
(a) granting permission unconditionally, or
(b) granting permission subject to such conditions
and as it may consider necessary, or
(c) refuse permission citing the grounds of such
refusal which shall be recorded in writing in the
order.
(3) No compensation shall be payable for the refusal of a
permission or for the imposition of modifications or conditions in granting
permission.
(4) If within sixty days after the receipt of such application made
under this section for development permission for layout or such similar
land development scheme or construction of building or of any information
or further information required, the Commissioner has neither granted or
refused permission, such permission shall be deemed to have been granted
and the applicant after intimating the Commissioner in writing, may proceed
to carry out the development but not so as to contravene any of the
provisions of the Act or plans or schemes or any rules or regulations made
under the Act.
(5) If any person carries on any development work or retains the
use of any building or work or continues the use of land in contravention of
the provisions under the Act, or of any development permission granted
under the Act, the Commissioner may direct such person, by notice in
writing, to stop further progress of such work or to discontinue any use and
may, after making an inquiry in the prescribed manner, remove or pull
down any building or work carried out and restore the land to its original
condition or as the case may be, take any measure to stop such use.
(6) Any expenses incurred by the Commissioner under sub-section
(5) shall be a sum due to the Authority under the act from the person in
default.
80
(7) The development permission order may among other conditions
contain the implementation of master plan and infrastructure plan and
regulations, area development plan, notified development scheme, layout
regulations, development promotion regulations layout regulations,
development promotion regulations, road network and other communication
network system and the area of land affected and to be surrendered free of
cost to the Authority for development in accordance with such sanctioned
Plan or regulations.
(8) In such layouts and such other similar site development,-
(a) such development permission shall be considered
only if the same is undertaken through a licensed
developer;
(b) the licensed developer shall be required to
mortgage fifteen percent of the plotted saleable land
to the Authority as surety for carrying out the
developments and complying with other conditions
as per specifications and in the given time period, in
the failure of which, the Commissioner shall be
empowered to sell away the mortgaged plots and
utilize the amount so realized for completion of the
development works.
Previous and next
All sections of The Andhra Pradesh Capital Region Development Authority Act, 2014.
Questions people ask
Is section 110 of the Andhra Pradesh Capital Region Development Authority Act, 2014. still in force?
No repeal of the Andhra Pradesh Capital Region Development Authority Act, 2014. is recorded.