29. Rate contract.- (1) In addition to the conditions included in sub-section (1) of
section 36 for adopting the method of rate contract, a procuring entity may adopt the method
of rate contract, when it determines that by virtue of the nature of subject matter of
procurement, the need for that subject matter may arise on an urgent basis during a given period
of time.
13
(2) The procedure for rate contract shall be as under:-
(a) A procuring entity may award a rate contract by the method of open competitive
bidding. If it is not possible to adopt the method of open competitive bidding, the procuring
entity after recording reasons may adopt another method of procurement. An approximate
quantity of required goods, works or service during the period shall be indicated in the Notice
Inviting Bids, but no minimum quantity is guaranteed.
(b) The period of rate contract shall be generally one year, preferably a financial year
to match with budget provisions and levy of taxes. It may be a shorter period, if variations in
market prices are expected to be significant. It may also be a longer period up to maximum two
years, if the variations in market prices are not expected to be significant. The reasons for
selecting the period for rate contract shall be recorded.
(c) In the first stage single part or two part bids shall be invited in accordance with the
provisions of section 13.
(d) A rate contract shall be entered, for price without a commitment for quantity, place
and time of supply of subject matter of procurement, with the bidder of lowest priced bid or
most advantageous bid.
(e) In the second stage supply or work order shall be placed at the contracted price for
supply or execution of the required quantity of the subject matter of procurement mentioning
the place of supply or execution, delivery schedule, etc., as and when needed.
(f) Rate contracts may be entered with more than one bidder as parallel rate contracts
provided there is such provision in the bidding documents, in the order of their standing in final
evaluation, by giving them counter offer of prices of the lowest or most advantageous bidder,
in order to secure prompt delivery of goods or services or execution of works, if the quantity
of the subject matter of procurement required is beyond the capacity of the lowest bidder or the
subject matter of procurement is of critical or vital nature.
(g) The terms and conditions of the rate contract including provision for liquidated
damages shall be similar to those prescribed for procurement by open competitive bidding.
(h) The prices under a rate contract shall be subject to price fall clause. A clause
regarding price fall shall be incorporated in the terms and conditions of rate contract. Price fall
clause is a price safety mechanism in rate contracts and it provides that if the rate contract
holder quotes / reduces its price to render similar goods, works or services at a price lower than
the rate contract price to anyone in the State at any time during the currency of the rate contract,
the rate contract price shall be automatically reduced with effect from the date of reducing or
quoting lower price, for all delivery of the subject matter of procurement under that rate
contract and the rate contract shall be amended accordingly. The firms holding parallel rate
contracts shall also be given opportunity to reduce their price by notifying them the reduced
price giving them fifteen days time to intimate their acceptance to the revised price. Similarly,
if a parallel rate contract holding firm reduces its price during currency of the rate contract, its
reduced price shall be conveyed to other parallel rate contract holding firms and the original
14
rate contract holding firm for corresponding reduction in their prices. If any rate contract
holding firm does not agree to the reduced price, further transaction with it, shall not be
conducted.
(i) It should be ensured that new rate contracts become operative right after the expiry
of the existing rate contracts without any gap. In case it is not possible to conclude the new rate
contracts due to unavoidable reasons, the existing rate contracts may be extended on same
price, terms and conditions for a period not exceeding 3 months. In such cases it shall be
ensured that market prices have not fallen down during the period for the subject matter of
procurement or its constituents, to be procured under the rate contract.
(j) Except as otherwise provided in this rule all other provisions of Chapter-V shall,
mutatis mutandis, apply.
Previous and next
All provisions of The Rajasthan Transparency in Public Procurement Rules, 2013
Questions people ask
Is rule 29 of the Rajasthan Transparency in Public Procurement Rules, 2013 still in force?
No repeal of the Rajasthan Transparency in Public Procurement Rules, 2013 is recorded.