Rule 27, The Rajasthan Transparency in Public Procurement Rules, 2013: Procurement of works by work order system and piece work system
The Rajasthan Transparency in Public Procurement Rules, 2013 - Rule 27
Text of rule 27
Procurement of works by work order system and piece work system
27. Procurement of works by work order system and piece work system.- (1)
Works valuing less than rupees one lakh on each occasion may be procured, subject to a limit
of rupees five lakh during a financial year, by work order system.
Explanation: Work order system means method of procurement by giving order directly to a
registered bidder, to execute a work on scheduled rates in specified time.
(2) The procedure for procurement through work order system shall be as under:-
11
(a) in work order the quantity, rate and time of completion are invariably mentioned.
Penalty for failure to complete the work within the stipulated time is also specified. Maximum
work that can be allotted on a work order shall be less than rupees one lakh;
(b) work order shall be given to a registered bidder only;
(c) work order can be given only on the approved Schedule of Rates applicable to the
Division / Sub-Division concerned. The Superintending Engineer / Executive Engineer shall
ensure that the rates being allowed on work order are not in excess of open bid rates prevalent
in the area;
(d) work order can be given by officers as per delegation of financial powers; and
(e) work order agreement shall be executed, after obtaining performance security, in
the form specified for the purpose. A Register of Work Orders shall be maintained in the form
specified for the purpose.
(3) Works valuing below rupees one lakh on each occasion may be procured, subject to
a limit of rupees five lakh during a financial year, by piece work system.
Explanation: Piece work system means method of procurement at the rates sanctioned
by the Competent Authority without reference to the total quantity of work to be done within
a given period.
(4) The procedure for procurement through Piece Work System shall be as under:-
(a) Execution of work on Piece Work System should normally be avoided. Piece Work
System may be resorted to only in a uniform type of work in large quantities, like earth work
of canals, desilting, repair and maintenance of roads, etc.
(b) For determination of rates, open bids shall be invited by Additional Chief Engineer
concerned for each division under its control. The intention of the department in inviting such
bids for determination of Annual Rate Contract for entering into Piece Work Agreement should
be made clear at the time of invitation of bids. Registered bidders of all categories shall be
entitled to participate in such bids. After observing all required formalities of bids, the
Additional Chief Engineer shall sanction unit rates for the specified items of work, which shall
remain in force normally for one year or until the rates are revised but shall in no case remain
in force more than three months after completion of one year.\
(c) Once such unit rates have been sanctioned, Divisional Officers shall be competent
to enter into Piece Work Agreement below rupees one lakh at a time with a single registered
bidder of any category. Second Piece Work Agreement shall be entered into only after
successful completion of the earlier work. Piece Work Agreement shall be entered into with
the registered bidders allowed to operate in the said Division.
(d) In the Piece Work System, the Department is free to ask the bidders to cease the
work, and payments are made for the work actually executed as per designs, drawings,
specifications, after due measurements and checking of measurement as specified. The
maximum period of completion of each piece work is twenty one days which shall not be
extended in any case.
12
(e) In every Divisional office, a Register of Piece Work Agreements shall be maintained
in the form specified for the purpose. In the first week of every month, the Divisional Officer
shall submit copies of all Piece Work Agreements accepted by him during the previous month
to the Superintending Engineer, giving justification for the award of work on Piece Work
Agreement explaining the necessity / emergency instead of on regular contracts. The
Superintending Engineer, during his inspection and otherwise, shall ensure that the Divisional
Officers do not execute work on Piece Work Agreement in a routine manner and rates allowed
are not in excess of the running rates approved by the Additional Chief Engineer for the relevant
Division, and check with open bid rates of similar works on regular contract basis in the Sub-
Division / Division /Circle and that the system of record measurements of work done and check
measurements thereof is followed properly.
(f) The contract awarded on Piece Work System is exempted from depositing
performance security.
Previous and next
All provisions of The Rajasthan Transparency in Public Procurement Rules, 2013
Questions people ask
Is rule 27 of the Rajasthan Transparency in Public Procurement Rules, 2013 still in force?
No repeal of the Rajasthan Transparency in Public Procurement Rules, 2013 is recorded.