Rule 7, The Rajasthan Transparency in Public Procurement Rules, 2013: Procurement plan
The Rajasthan Transparency in Public Procurement Rules, 2013 - Rule 7
Text of rule 7
Procurement plan
7. Procurement plan.- (1) A procurement plan shall be prepared by every procuring entity for
each of the item of goods, works or services to be procured during the year in accordance with section
5.
(2) The Procurement plan shall specify the following:-
(a) Nature of Procurement – Goods / Works / Services;
(b) Major Specifications – Quantity / Type / Quality;
(c) Estimated Value;
1[(d) Source of Funds – State Fund/Central Assistance/Externally Aided project/Others;]
(e) Budget Code;
(f) Procurement Method likely to be followed;
(g) Timeframe for Bid Process; and
(h) Timeframe for Delivery of goods or services or Completion of work to identify the funds required in the next
financial year or subsequent financial years.
(3) The plan shall be based on inputs received for each item from officers at various hierarchical
level of the procuring entity.
Previous and next
All provisions of The Rajasthan Transparency in Public Procurement Rules, 2013
Questions people ask
Is rule 7 of the Rajasthan Transparency in Public Procurement Rules, 2013 still in force?
No repeal of the Rajasthan Transparency in Public Procurement Rules, 2013 is recorded.