Regulation 21, The Himachal Pradesh Electricity Regulatory Commission (Consumer Grievances Redressal Forum and Ombudsman) Regulations, 2013: Inspection
The Himachal Pradesh Electricity Regulatory Commission (Consumer Grievances Redressal Forum and Ombudsman) Regulations, 2013 - Regulation 21
Text of regulation 21
Inspection
21. Inspection. - (1) The Forum may direct the licensee to undertake an inspection or
engage a third party to undertake such inspection with regard to the grievance, as may be
required for expeditious redressal of the grievance or it may in special circumstances of a
case and recording reasons therefore and at the instance and request of the Complainant,
engage a third party (other than the licensee) to undertake inspection and obtain an
independent report.
(2) The expenses of such third-party inspection, except expenses of inspection at
the request of the Complainant, shall be borne by the licensee, and to the extent reasonable
and justifiable, such expenses shall be allowed as pass through expense in the
determination of tariff in accordance with the relevant Regulations of the Commission:
10 Compendium of HPERC Regulations, March 2021
Provided that if inspection is taken up at the request of the Complainant, the
expenses shall be deposited in advance by him, which may or may not be refunded by the
Forum depending on whether the grievance is found to be of substance or not.
Previous and next
Questions people ask
Is regulation 21 of the Himachal Pradesh Electricity Regulatory Commission (Consumer Grievances Redressal Forum and Ombudsman) Regulations, 2013 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Consumer Grievances Redressal Forum and Ombudsman) Regulations, 2013 is recorded.