Section 8, UTTARAKHAND ENTERPRISES SINGLE WINDOW FACILITATION AND CLERANCE ACT
UTTARAKHAND ENTERPRISES SINGLE WINDOW FACILITATION AND CLERANCE ACT (5 of 2013) - Section 8
Text of section 8
8. (1) Application form and fee for clearance:--
Filing and
(a) any applicant, who desires to set up an enterprise in the State of
Disposal of
Uttarakhand, shall apply in Combined Application Form along with a
application
fee, as may be prescribed by the Government, to the Nodal Agency;
(b) the fee, prescribed as above, shall be in addition to the fee, if any,
prescribed under any Central law by any authority or department, and
shall be submitted along with the form, prescribed by any such
authority under that law;
(c) suitable exemption from fee may be notified by the Government for
applicants belonging to SC/ST/Women/ Physically Handicapped
categories and Micro Enterprises may also be exempted from paying
the fee.
Rates for fee:--
Small : Rs. 1000/-
Medium : Rs. 5000/-
Large/Heavy : Rs. 10000/-
(2) After the receipt of application for clearances, the authorized representative
of the Nodal Agency shall satisfy himself that the application given by the
applicant is complete in all respect. If it is so, he shall give an
acknowledgement in token of the receipt of the application.
(3) After an acknowledgement is given by the authorized representative of the
Nodal Agency, he shall enter the application for clearances in the register of
applications. The register of applications shall be checked up and certified to
be correct by the Head of the Nodal Agency at the end of each working day.
(4) The relevant parts of the application form shall be sent to the concerned
Competent Authority within a period as prescribed under section 10.
(5) The concerned Competent Authority shall process application form and
communicate its decision to the Nodal Agency within the period, as
prescribed under section 10.
(6) The concerned department or authority shall provide comments sought by the
Nodal Agency, within the period as prescribed, and, if the concerned
department or authority fails to provide comments within the aforesaid
period, it shall be deemed that the concerned department or authority has no
objection regarding the application for clearance.
(7) Power of Competent Authority to call for additional information:-
(a) before communicating its decision, if the Competent Authority deems it
necessary to ask for any additional information from the applicant, it may
seek the same within a period as prescribed under section-10 after the
receipt of application for clearances under intimation to the Nodal
Agency;
(b) the additional information, sought, shall be furnished by the applicant
direct to the Competent Authority under intimation to the Nodal Agency
within the period, specified in this regard by the competent authority.
However, such additional information would be sought once only, and not
time and again in piecemeal;
(c) in the case of seeking any additional information, the period, specified for
communicating the decision by the competent authority to Nodal Agency,
shall be counted from the date of receipt of additional information;
(d) in case, it is found by the Nodal Agency that the additional information,
sought by the Competent Authority, is uncalled for or the same is sought
after the expiry of the period, specified under clause (a) above, then it
shall be construed that the additional information was not required at all,
and the period for communicating the decision in this regard, shall be
reckoned from the date, the application for clearances was originally
submitted;
(e) the status report of the applications for clearances shall be placed before
The State Empowered Committee, or as the case may be, District
Empowered Committee by the respective Nodal Agencies;
(f) the State Empowered Committee, or as the case may be, District
Empowered Committee shall respectively, communicate its decision of
approval or rejection;
(g) the status report of the applications for clearances shall be monitored by
The State Empowered Committee, or as the case may be, District
Empowered Committee once in a month.
1{ Effect of in 8A Approval (in-principle approval) issued by the State Empowered Committee or
principle District Empowered Committee, as the case may be, in accordance with
approval section 8(7)(F) of the Act, except to the approvals/licenses
/permissions/acknowledgment to be issued at the level of the Central
Government or any of its departments/ organizations and appropriate
Government or Competent authority under Central Laws as laws related to
environment conservation Labour Industry etc. shall be effective for all
purposes except for micro and small enterprises as if it were an
approval/licenses /permission/acknowledgment as defined in section 10(1) of
the Act for a period of three years from the date of its issue. The approval (in-
principle approval) shall be effective for all purposes for medium enterprises as
if it were an approval/licenses/permission /acknowledgment as defined in
section 10(1) of the Act for a period of three years from the date of its issue or
the date of commencement of commercial production, whichever occurs
earlier:
Provided that within the said period of three years, the applicant shall
has to obtain the requisite approvals licenses/permissions/acknowledgments as
defined under section 10(1) and if applicable under the Central Acts for the
establishment/operation of the concerned enterprise.
It shall be mandatory for the applicant to attach a self-attested affidavit of
fulfilling the standards of the Uttarakhand Building bye laws in force for the
time being after getting the map of the project checked through an authorized
architect or online software along with the Application Form:
Provided further that during the said period, the applicant shall have to
ensure necessary compliance for obtaining the necessary approvals licenses
/permissions/ acknowledgments for the establishment/operation of the
enterprise concerned. In case the necessary compliance is not ensured, legal
action shall be taken against him:
Provided also further that the letter of approval (in-principle approval)
shall not entitle any person/institution or organization to use land other than the
land use specified in the master plan, wherever such plan is in force. It shall
also not be entitled to use a restricted category as specified in section 132(a) of
the Uttar Pradesh Zamindari Abolition and Land Reforms Act, 1950
(Adaptation and Modification Order, 2001) i.e. pasture or such land on which
water is used and which is used to grow water chestnut or other produce or
such land which is not covered by riverbed and occasionally used for
agricultural purposes.}
----------------------------------------------------------------------
1- Inserted by section 6 of Uttarakhand Act no 08 of 2022.
Previous and next
All sections of UTTARAKHAND ENTERPRISES SINGLE WINDOW FACILITATION AND CLERANCE ACT
Questions people ask
Is section 8 of UTTARAKHAND ENTERPRISES SINGLE WINDOW FACILITATION AND CLERANCE ACT still in force?
No repeal of UTTARAKHAND ENTERPRISES SINGLE WINDOW FACILITATION AND CLERANCE ACT is recorded.