Rule 16, TAMIL NADU INFRASTRUCTURE DEVELOPMENT RULES 2012: Manner of managing the Project Preparation Fund
TAMIL NADU INFRASTRUCTURE DEVELOPMENT RULES 2012 - Rule 16
Text of rule 16
Manner of managing the Project Preparation Fund
16. Manner of managing the Project Preparation Fund:- (1) The Project
Preparation Fund shall be a Fund of the Board;
(2) The balances of the Project Preparation Fund shall be maintained in the
public account or part of the Government cash balances in a separate bank
account or both as may be decided by the Board.
(3) The power to sanction expenditure from the Project Preparation Fund
shall be delegated as follows:
(a) Upto Rs.5 lakhs - CEO;
(b) From Rs.5 lakhs
upto Rs.50 lakhs
- A Sub-committee of the Executive
Committee comprising Principal
Secretary to Government (Finance
Department), the CEO and one
other member to be nominated by
the Executive Committee;
(c) From Rs.50 lakhs
upto Rs.5 Crores
- The Executive Committee;
(d) Above Rs.5 Crores - The Board:
Provided that the expenditure sanctioned by authorities other than the
Board shall be reported to the Board at its next meeting;
(4) The CEO of the Board shall be the drawing and disbursing officer of the
Fund and shall maintain accounts in the appropriate form.
7
Previous and next
← Rule 15Use of Project Preparation FundRule 17 →Recovery of expenditures made through Project Preparation Fund
All provisions of TAMIL NADU INFRASTRUCTURE DEVELOPMENT RULES 2012
Questions people ask
Is rule 16 of TAMIL NADU INFRASTRUCTURE DEVELOPMENT RULES 2012 still in force?
No repeal of TAMIL NADU INFRASTRUCTURE DEVELOPMENT RULES 2012 is recorded.