Regulation 38, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012: Operation and maintenance expenses
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 - Regulation 38
Text of regulation 38
Operation and maintenance expenses
38. Operation and maintenance expenses.- (1) Normative annual O&M expenses for the
control period shall be as follows:-
S.
No.
Category of Project Annual O&M expenses
Rupees in Lac per MW
(i) Above 100 kW to 2 MW capacity 25
(ii) Above 2 MW to 5 MW capacity 22
(iii) Above 5 MW to 25 MW capacity 18
CHAPTER -VI
OTHER PARAMETERS
Previous and next
Questions people ask
Is regulation 38 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.