Text of regulation 35
Free Power
35. Free Power.-(1) The Commission shall consider appropriate structure(s) of free power
for determination of generic levellised tariffs for various categories of SHPs, as mentioned
in Regulation 32, duly keeping in view of the provisions of the State Hydro Policy for
allotment of sites for SHPs, National Hydro Policy, Tariff Policy and the limits specified
under sub-regulation (3):
Provided that in cases requiring determination of the project specific tariff, the
Compendium of HPERC Regulations, March 2021 29
Commission shall consider the structure of free power actually applicable to that project
subject to the above and the limits specified in sub-regulation(3).
(2) In case of any change in the structure of free power for a SHP from that
considered for the determination of generic levellised tariff or project specific levellised
tariff in accordance with sub-regulation (1) or in cases where the adjustment in tariff on
account of variation in free power has to be allowed as per the specific provisions contained
in these Regulations, including those covered in regulation 16 and sub-regulation (2) of
regulation 19, the distribution licensee shall adjust the tariff as per the following formula:-
Rate payable
for the month
for the net
saleable
Energy
(Rs/kWh)
= a X
(((100- b)
(100-c)
Where, -
“a” is the levellised tariff (in Rs/kWh) which is required to be adjusted under this
regulation
“b” is the free power (in percentage) taken into account or deemed as taken into
account for the month, in “a” in the corresponding month of the tariff period by
reckoning the date of commencement of operation of the project as the starting date
of the tariff period.
“c” is the free power (in percentage) to be allowed in the tariff for the month subject
to maximum limit of 13% free power(energy) and the provisions of sub- regulation
(3)
Where free power is applicable at different rates for different parts of a month, the
permissible free power (i.e “c”) shall be determined under this sub-regulation separately for
each such part and weighted average rate for the month as a whole shall be worked out by
considering the total quantum of energy for each day of the month.
(3) The free power (in percentage) to be taken into consideration for the purpose
of determination of tariff under sub-regulation (1) and/or any adjustment under sub-
regulation (2) shall be subject to the following: -
(i) The free energy to be taken into account for any part of the tariff period for
the purposes of sub-regulation (1), or to be allowed for any part of the tariff
period for the purposes of sub-regulation (2), shall not exceed 13% free
power(energy) which includes 12% free power to home State and 1%
additional free power for Local Area Development Fund, as stipulated in the
National Hydro Policy/ Tariff Policy.
(ii) Any quantum of free energy, if committed by the renewable energy generator
over and above the 13% free power (energy) for any period shall not be
factored into the tariff.
30 Compendium of HPERC Regulations, March 2021
(iii) Additional free energy, if any, to be provided by the renewable energy
generator to the State Government, on account of curtailment of waiver
period due to delay in commissioning of project as per provisions of
Implementation Agreement and/or for enhancement of capacity and/or for
any reason attributed to the renewable energy generator shall not be taken into
account even if the total free power for any period, including such additional
free power, does not exceed 13% free power(energy).
(iv) The quantification and adjustment of free energy as well the energy accounting
shall be made with reference to the energy projected/received at the
interconnection point.
(v) The free energy to be allowed for any period for the purpose of sub-regulation
(2) shall in no case be more than that actually deducted for that period in the
energy accounts, out of the total energy received at the interconnection point.
Previous and next
Questions people ask
Is regulation 35 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.