Text of regulation 27
Operation and maintenance expenses
27. Operation and maintenance expenses.- (1) Operation and maintenance expenses mean
the expenditure incurred on operation and maintenance of the project, or part thereof, and
includes, without limitation, the expenditure on manpower, establishment (including
employees expense, administrative and general expenses), repairs, spares, consumables,
1
Add. proviso vide Not. No. HPERC-438 –Vol-VIII, dated 11
th
Feb., 2015, published in R H.P. dated
19.02.2015 at p. 6291-929.
Compendium of HPERC Regulations, March 2021 27
insurance and overheads as well as the taxes, duties and other levies on any or all such
activities.
(2) Operation and maintenance expenses shall be determined for the tariff period
based on normative operation and maintenance expenses specified in Chapter-V of these
Regulations for the SHPs and as stipulated in relevant orders of the Commission for other
renewable technologies.
(3) Normative O&M expenses allowed under these Regulations shall be escalated at
the rate of 5.72% per annum over the tariff period.
Previous and next
Questions people ask
Is regulation 27 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.