Capital Cost
20. Capital Cost.- (1) The norms for the capital cost in case of SHPs shall be as specified
in Chapter-V of these Regulations and in case of other renewable technologies, shall be as
stipulated under relevant orders of the Commission under regulation 17.
(2) The norms for the capital cost shall be inclusive of all the expenses required to
be incurred as per prudent practices upto the commissioning of the project, including, but
not limited to, the cost of capital works, land, preparation of the Detailed Project Report,
Survey and Investigation, plant and machinery, civil works, erection and commissioning,
financing and interest during construction, land acquisition, resettlement and rehabilitation,
statutory and non-statutory clearances and evacuation infrastructure up to inter-connection
point ( also including interconnection facilities), insurance charges against the risks during
construction stage etc and also all taxes, levies and duties on all such components/works
capital works:
Provided that any cost pertaining to allotment of the project, including upfront
premium and any other amount charged by the State Government while granting extension
or capacity enhancement or/and any liquidated damages/penality imposed in accordance
with the Power Purchase Agreement executed with the licensee, will not form part of the
capital cost:
Compendium of HPERC Regulations, March 2021 23
Provided further that for project specific tariff determination, the renewable energy
generator shall submit the itemwise break-up of capital cost along with its petition in the
manner specified under regulation 18 and the capital cost admitted by the Commission shall
be taken into consideration.
Previous and next
Questions people ask
Is regulation 20 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.