Regulation 16, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012: Capacity enhancement
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 - Regulation 16
Text of regulation 16
Capacity enhancement
16. Capacity enhancement. - (1) Where, after the allotment of the original project, the
capacity of a SHP is enhanced, with the approval of the State Government, the tariff for
sale of net saleable energy from such projects, shall be governed by the relevant provisions
of sub-regulations (2) to (7).
(2)Where neither the Commission has approved, nor the parties have executed, the
Power Purchase Agreement for the original capacity, the enhanced capacity shall be taken
into consideration while approving or executing the Power Purchase Agreement, as the case
may be.
(3)Where the Commission has approved, or the parties have otherwise executed, the
Power Purchase Agreement prior to the commencement of these Regulations –
(i) if the total capacity of the project, after enhancement, does not exceed 5 MW,
the tariff applicable as per the Power Purchase Agreement for the original
capacity shall be applicable for the net saleable energy for the enhanced
capacity subject to adjustment in tariff on account of free power in accordance
with sub-regulation (6);
(ii) if the original capacity of the project was not more than 5 MW but the capacity,
after enhancement, exceeds 5 MW, the tariff applicable as per the Power
Purchase Agreement for the original capacity shall be reduced by 10% to
account for the expected reduction in the expenses on normative basis and shall
then be adjusted to account for the free power in accordance with sub-
regulation (6) by taking into account the free power (in percentage) factored in
the tariff for the original capacity as per the Power Purchase Agreement and
free power (in percentage) to be allowed in the tariff:
Provided that a levellised rate based on the rate applicable as per power
purchase agreement for the original capacity, adjustments under this clause, the
duration of residual tariff period and the discount rate determined by the
Commission under these Regulations, shall be applicable for the residual tariff
period.
Compendium of HPERC Regulations, March 2021 17
(iii) if the original capacity of the project was more than 5 MW and the Power
Purchase Agreement spells out the rate applicable for sale of net saleable
energy, the tariff applicable as per the Power Purchase Agreement for the
original capacity shall be applicable for the net saleable energy for the
enhanced capacity subject to adjustment in tariff on account of free power in
accordance with sub-regulation (6);
(iv) if the original capacity of the project was more than 5 MW and the Power
Purchase Agreement does not spell out the rate applicable for sale of net
saleable energy, the Commission may, on joint application from the licensee
and the renewable energy generator, determine the project specific levellised
tariff, after accounting for the free power subject to maximum limits outlined in
sub-regulation(3) of regulation 35, by duly taking into account the Policy of the
State Government/ Regulations/practices prevalent in the timeframe in which
the Power Purchase Agreement was executed for the original capacity, and
such other factors/norms as it may consider appropriate.
(4) Where the Power Purchase Agreement for the original capacity of a small hydro
project covered in these Regulations is approved and executed after the commencement of
these Regulations, the generic levellised tariff as well as other associated terms and
conditions applicable for the relevant category of SHPs under which the enhanced capacity
of the SHPs falls shall be applicable for the entire capacity:
Provided that if such Power Purchase Agreement for the original capacity contains
provision for determination of project specific levellised tariff, the Commission may, on
application from both the parties, determine the project specific levellised tariff by taking
into account the norms applicable for the category of SHPs in which the enhanced capacity
of the project falls.
(5) Where the Power Purchase Agreement has been executed for the original
capacity and the renewable energy generator sells energy, under the relevant Regulations
governing REC mechanism, to the distribution licensee from the additional capacity under
REC mechanism with a provision to sell such energy to the licensee for the balance part of
the tariff period after exit from the REC mechanism, the following provisions shall apply :-
(i) the tariff for the entire net saleable energy for the residual part of the tariff
period shall be fixed/determined in accordance with sub regulation (3) or (4),
as the case may be;
(ii) during the interim period when the energy is sold partly under the Power
Purchase Agreement for the original capacity and partly through the REC
mechanism-
(a) unless provided otherwise in the Power Purchase Agreement for the
original capacity, the tariff applicable for the original capacity shall not
be subject to any adjustment, on account of variation in free power,
under sub-regulation (6),
(b) the total net saleable energy shall be apportioned in a firm ratio on the
basis of original capacity and the enhanced capacity.
18 Compendium of HPERC Regulations, March 2021
(6) In the cases covered by sub-regulations (3), (4) and clause (i) of sub-regulation
(5), the tariff shall be adjusted on account of variation in the free power in accordance with
sub- regulations (2) and (3) of regulation 35:
Provided that in case capacity enhancement is approved by the State Government,
the percentage rate of free power undergoes change due to-
(i) any change in general policy during the intervening period between the dates
of execution of Implementation Agreements for the original capacity and the
Supplementary Implementation Agreement for the enhanced capacity, e.g. on
account of Local Area Development, change in basic rates, change in the
category of the project based on the capacity etc; or
(ii) additional free power specifically for enhancement of capacity; the variations
in free power on account of item (i) shall only be considered for adjustment
in tariff as per sub-regulations (2) and (3) of regulation 35, but additional free
power for capacity enhancement as per item (ii) shall not be considered for
tariff adjustment.
(7) Where the parties fail to arrive at an understanding for sale/purchase of energy in
the manner specified in sub-regulations (3) to (6), the right of the distribution licensee for
the net saleable energy as per the original Power Purchase Agreement, duly taking into
account the data contained in the Detailed Project Report for the original capacity and power
generation on real time basis, shall remain protected and the renewable energy generator
shall be eligible to dispose off only the net incremental saleable energy (i.e. after duly
adjusting the licensee’s first right as aforesaid and the total quantum of free energy for the
enhanced capacity of the Project):
Provided that in such a case, the renewable energy generator shall also arrive at an
understanding with the distribution licensee about the modalities for energy accounting on
real time basis as well as on monthly and annual basis and based on the same, the renewable
energy generator shall also make the distribution licensee a party to any such agreement for
disposal of such incremental energy:
Provided further that in case the licensee and the renewable energy generator
mutually agree to purchase/sell the net incremental saleable energy at a specific rate and
jointly make an application to the Commission for determination of such rate, the
Commission may determine the specific levellised rate for such net incremental saleable
energy as per the provisions of this sub-regulation and by taking into account the provisions
of the regulations/practices prevalent in the time frame during which the capacity
enhancement was permitted by the State Government.
(8) Where, after the Commission has approved the power purchase agreement for
sale of power from a project based on a renewable technology other than SHP, the capacity
of the project is enhanced, the tariff for sale of net saleable energy from such project shall be
governed by such terms and conditions as may be included by the Commission, to address
such situations, in the terms and conditions fixed by it under regulation 17.
Previous and next
Questions people ask
Is regulation 16 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.