Regulation 14, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012: Project specific levellised tariff
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 - Regulation 14
Text of regulation 14
Project specific levellised tariff
14. Project specific levellised tariff.-(1) Where the parties have mutually agreed, in the
Power Purchase Agreement executed by them, for a project specific levellised tariff, the
Commission shall determine such tariff taking into consideration-
(i) prudent capital cost as may be admitted by the Commission duly keeping in
view normative capital cost under these Regulations, the cost approved in the
Detailed Project Report, the actual expenditure incurred as per auditor’s
certificate, the information furnished under regulation 18:
Provided that in case of delay in execution of the project, the
Commission shall consider the time over run cost as follows -
(a) where the delay is due to factors entirely attributable to the renewable
energy generator, the entire cost shall be borne by the renewable
energy generator;
(b) where the delay is due to force majeure, the Commission may allow
the net additional cost incurred on this account to the renewable
energy generator: and
(c) in a situation not covered under clauses (a) and (b), the Commission
may allow the additional cost, not exceeding 50% of the net additional
cost incurred due to time overrun:
Provided further that the renewable energy generator shall be deemed
to have subscribed to the requisite insurance policies covering the risks
during construction stage and also to have stipulated provisions for the
liquidated damages in the contracts relating to the construction of the
project, awarded by him, as per the prudent practices, and accordingly, in
case of any time and cost over runs, the Commission shall not allow any
amount which is or would have been recoverable by him on account of
such deemed provisions for Insurance and liquidated damages:
Provided further that any cost pertaining to allotment of the project,
including upfront premium and any other amount charged by the State
Government while granting extension or capacity enhancement or/and any
liquidated damages/penalty imposed in accordance with the Power Purchase
Agreement executed with the licensee, will not form part of the capital cost;
(ii) the normative annual capacity utilisation factor specified under Chapter-V of
these Regulations for the SHPs or the annual capacity utilisation factor
14 Compendium of HPERC Regulations, March 2021
worked out on the basis of data for 75% dependable year as per the
approved Detailed Project Report, whichever is higher;
(iii) the technology specific parameters as specified for the SHPs in Chapter V of
these Regulations and as may be laid down by the Commission for the other
renewable technologies as per regulation 17; and
1
[(iv) financial norms/principles, in relation to the Municipal Solid Waste (MSW)
based power projects and Refuse Derived Fuel (RDF) based power projects,
as may be adopted by the Commission in accordance with sub-regulation
(3A) of regulation 17 of these Regulations and in other cases, the ceiling
norms, except for capital cost, as specified in Chapter-IV of these
Regulations:]
Provided that if the licensee and renewable energy generator have, in
accordance with regulation 31, agreed to any improved norms, including
operation and maintenance norms, which may lead to overall reduction in the
levellised tariff, such improved norms shall apply for determination of the
project specific levellised tariff.
(2) Where the project specific levellised tariff, as determined under sub-
regulations(1)–
(i) exceeds the corresponding generic levellised tariff, duly adjusted for permissible
rate of free power if any, determined by the Commission in relation to the
control period in which the Power Purchase Agreement was approved by the
Commission, the distribution licensee shall have the option to exit from the
power purchase agreement, provided that this option shall not be available to the
distribution licensee if the renewable energy generator agrees to a tariff
corresponding to the generic levellised tariff;
(ii) is less than 95% of the corresponding generic levellised tariff, duly adjusted for
permissible rate of free power if any, determined by the Commission in relation
to the control period in which the Power Purchase Agreement was approved by
the Commission, the renewable energy generator shall have the option to exit
from the power purchase agreement, provided that this option shall not be
available to the renewable energy generator if the distribution licensee agrees to
keep the tariff within the aforesaid limit.
(3) Where the exit option is exercised by any party under sub-regulation (2) and
the interconnection point for that project falls under the control of the distribution licensee, it
shall, on request from the renewable energy generator, provide open access through its
system to the renewable energy generator as per the open access regulations.
Previous and next
Questions people ask
Is regulation 14 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.