Regulation 4, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012: Eligibility Criteria
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 - Regulation 4
Text of regulation 4
Eligibility Criteria
4. Eligibility Criteria.- A project shall be eligible for being considered to be based on
renewable sources of energy on the fulfillment of the following criteria:-
(a) Wind power project.– using new wind turbine renewable energy generators.
(b) Small hydro project.– located at the sites approved by the State
Government or its agency; using new plant and machinery; and the installed
power plant capacity to be lower than or equal to 25 MW at single location.
(c) Biomass power project based on Rankine cycle technology .- Biomass
power projects using new plant and machinery based on Rankine cycle
technology and using biomass fuel sources, provided use of fossil fuel is
restricted only up to 15% of total fuel consumption on annual basis.
(d) Non-fossil fuel based co-generation project.- The project shall qualify to be
termed as a non-fossil fuel based co-generation project, if it is using new
plant and machinery and is in accordance with the definition and also meets
the qualifying requirement outlined below:-
Topping cycle mode of co-generation – Any facility that uses non-fossil
fuel input for the power generation and also utilises the thermal energy
generated for useful heat applications in other industrial activities
simultaneously:
Compendium of HPERC Regulations, March 2021 7
Provided that for the co-generation facility to qualify under topping cycle mode,
the sum of useful power output and one half the useful thermal output be greater than
45% of the facility’s energy consumption, during season.
Explanation. - For the purposes of this clause-
(i) ‘Useful power output’ is the gross electrical output from the
renewable energy generator. There will be an auxiliary
consumption in the cogeneration plant itself (e.g. the boiler feed
pump and the FD/ID fans).
In order to compute the net power output it would be necessary to subtract the
auxiliary consumption from the gross output. For simplicity of calculation,
the useful power output is defined as the gross electricity (kWh) output from
the renewable energy generator.
(ii) ‘Useful thermal output’ is the useful heat (steam) that is provided to
the process by the cogeneration facility.
(iii) ‘Energy consumption’ of the facility is the useful energy input that is
supplied by the fuel (normally bagasse or other such biomass fuel).
(iv) ‘topping cycle’ means a cogeneration process in which thermal
energy produces electricity followed by useful heat application in
industrial activities.
(e) Solar PV and Solar Thermal Power Project. – Based on Technologies
approved by the MNRE.
(f) Biomass Gasifier based Power Project.– The project shall qualify to be
termed as a biomass gasifier based power project, if it is using new plant and
machinery and having a grid connected system that uses 100% producer gas
engine, coupled with gasifier technologies approved by the MNRE.
(g) Biogas based Power Project.– The project shall qualify to be termed as a
biogas based power project, if it is using new plant and machinery and
having grid connected system that uses 100% biogas fired engine, coupled
with biogas technology for co-digesting agriculture residues, manure and
other bio-waste as may be approved by the MNRE.
1
[(h) ‘Municipal Solid Waste (MSW) based power projects’- the project shall
qualify to be termed as a Municipal Solid Waste (MSW) based power project,
if it is using new plant and machinery based on Rankine cycle technology and
using Municipal Solid Waste (MSW) as fuel sources; and
(i) ‘Refuse Derived Fuel (RDF) based power projects’- the project shall
qualify to be termed as a Refuse Derived Fuel (RDF) based power project, if
it is using new plant and machinery based on Rankine cycle technology and
using Refuse Derived Fuel (RDF) as fuel sources.]
1
Ins. clauses “(h) and (i)” vide Not. No. HPERC/428 dated 11
th
April, 2016 published in the R.H.P.
dated 13
th
April, 2016 at p. 235-237.
8 Compendium of HPERC Regulations, March 2021
CHAPTER-II
PROMOTION OF GENERATION FROM RENEWABLE ENERGY SOURCES
Previous and next
Questions people ask
Is regulation 4 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 is recorded.