Regulation 7, The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012: Recovery of expenditure for additional loads
The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 - Regulation 7
Text of regulation 7
Recovery of expenditure for additional loads
7. Recovery of expenditure for additional loads.- (1) Save as provided in sub-
regulation (2), where an existing consumer availing permanent connection for electricity
applies for additional connected load or contract demand, as the case may be, in excess of
the connected load or contract demand, already sanctioned in his favour, the recovery
shall be made as under:-
(a) in relation to the expenses/charges for the cost of service line under regulation
4 –
(i) if the existing service line has sufficient spare capacity, after meeting the
requirements of all the connections released and/or committed to be
released through the same service line and redundancy of about 30% of
the total capacity of such line, no additional cost shall be recovered for
the service line;
(ii) if sufficient spare capacity is not available, in accordance with the
preceding sub-clause (i), in the service line for meeting the additional
connected load or contract demand, the cost of strengthening the existing
service line, or of providing a new service line, shall be recovered from
the applicant:
[
Provided that the cost to be recovered under sub-clause (ii) shall not
exceed the cost of providing a new service line for the total connected load
or contract demand under regulation 4 of these Regulations;
(b) in relation to the infrastructural development charges under regulation 5 :-
1
[ (i) if the provisions of sub-regulation (3) of regulation 5 are not attracted,
then, subject to succeeding sub-clause (iii), such charges shall be
recovered only for the additional connected load/contract demand in
1
Subs. vide ‘Not. No. HPERC/419 dated 23rd January, 2017 published in the R H.P. dated 6
th
February,
2017 at p. 6943-6945and before its substitution it stood as under:-
“(i) if the supply voltage for the total load remains unchanged as per the standard supply voltages fixed by the Commission under
the applicable Tariff Order of the Commission and the provisions of sub-regulation (3) of regulation 5 are not attracted, then,
subject to succeeding sub-clause (iii), such charges shall be recovered only for the additional connected load/contract
demand in accordance with sub-regulations (2) and (9) of regulation 5, regulations 14 and 15 of these Regulations ; and
(ii) if the supply voltage gets changed, but provisions of sub-regulation (3) of regulations 5 are not attracted, then the
recoverable amount shall be worked out and recovered in accordance with sub-regulations (2) and (9) of regulation 5 for the
total revised connected load or contract demand, as the case may be, sanctioned at the new voltage; and”
8 Compendium of HPERC Regulations, March 2020
accordance with sub-regulations(2) and (9) of regulation 5, regulations
14 and 15 of these regulations;
(ii) if the licensee permits clubbing of two or more electricity
connections, existing at same or different voltages, but in the name of
same person and at the same or contiguous premises, as a single
connection in the name of the same person and at the same premises,
and at a voltage not less than 11kV and also not lower than the
Standard Supply Voltage, corresponding to the combined connected
load/contract demand, the sum total of sanctioned connected
load/contract demand, of such connections shall be considered as the
existing connected load/contract demand for computing the additional
connected load or contract demand for the purpose of sub-clause (i) of
this sub-regulation:
Provided that no refund on account of the charges mentioned in
clause (i) shall be allowed if such existing connected load/contract demand
is more than the combined connected load/contract demand for the new
connection and in such an event, the consumer shall be deemed to have
surrendered such reduction in the connected load/contract demand and he
shall not be entitled to claim at any subsequent stage any relief for
restoration of the connected load/contract demand so surrendered:
Provided further that when such clubbing of loads is permitted under
this clause, consumer shall not be eligible to avail the benefit of temporary
reduction in the contract demand as per provisions of the Supply Code for a
period of 365 days from the release of new connection after clubbing of the
existing electricity connections:
Provided further that the licensee shall have the right to use,
maintain and own the service line or any other electrical system, vacated
by the consumer due to such clubbing of existing electricity connections in
accordance with regulation 11 and the said works shall become the property
of the licensee.
Explanation- For the purposes of sub-clause (ii)-
(1) “person” shall have the same meaning as is assigned to it under
clause (49) of the Section 2 of the Act and two or more companies formed
and registered or deemed to have been formed and registered under the
Companies Act, 2013 (18 of 2013), having electricity connections in their
respective names, shall also be considered to be entitled for clubbing of
their electricity connections, if—
(a) (i) all such companies having electricity connections in their names are
the subsidiary companies of the same holding company; or
(ii) one of such companies is a holding company and the other company
is the subsidiary company of that holding company; and
(b) the new connection, after clubbing of existing connections, is sought
in the name of any of such subsidiary companies, which are already
availing connections sought to be clubbed, or in the name of the
holding company of such subsidiary companies;
Compendium of HPERC Regulations, March 2021 9
(c) the conditions laid down in sub-clause (ii), read with
succeeding para (3) of this Explanation, in relation to the existence
of the electricity connections sought to be clubbed, as well as for
release of new connection, at the same or contiguous premises, are
met;
(2) the terms “Company”, “holding company” and “subsidiary
company” shall have the same meanings as are assigned to them under
the Companies Act, 2013 (18 of 2013);
(3) “premises” shall have the same meaning as is assigned to it under
clause (51) of section 2 of the Act and the existing electricity connections
which are sought to be clubbed, shall also be considered to be entitled for
clubbing, even if the same are being availed at two or more such premises;
if –
(i) all such premises at which such connections are being availed are
contiguous to each other and are not separated by any such other
premises, land, plots or roads etc., not solely occupied by such
consumers or by the person seeking new connection after clubbing of
existing electricity connections; and
(ii) the new connection, after clubbing of existing connections, is sought to
be released for the premises encompassing the contiguous premises for
which such connections are already existing; and which is intended to
be occupied only by such person in whose name the new connection is
sought. However there shall be no restriction to enlarge such premises
while releasing the new connection so long as the new premises, after
clubbing of connections, is entirely continuous and is to be occupied by
the new applicant;
1[(2) Save as provided in sub-clause (ii) of Clause (b) in sub-regulation (1), in
case of reduction of the connected load or contract demand, not attributed to clubbing of
loads as per the said sub-clause (ii), including provision thereto, by a consumer-]
(i) the licensee shall maintain adequate spare capacity in the service line for a
period of 365 days reckoned from the date of such reduction, so as to meet
the load if the said consumer subsequently applies for restoration of his
connected load or contract demand so reduced, during the said period of 365
days;
(ii) the infrastructural development charges leviable under sub- clause (i) of
clause (b) of sub-regulation (1) shall be charged only for the additional
quantum of connected load or contract demand, exceeding the total quantum
which was being availed by him prior to such reduction, if the said
consumer subsequently applies for restoration of his connected load or
2
[contract demand so reduced if the consumer clears all such outstanding dues,
if any, as have been billed to him, also including those related to the
1
Subs. beginning of sub-regulation (2) for word “Save as provided in Clause (b) in sub-regulation (1) in
case of reduction of the connected load or contract demand, by a consumer-”vide Not. No. HPERC/419 dated 5
th
September, 2018 published in the R H.P. dated 7
th
September, 2018 at p.4503-4504.
2
Subs. vide Not. No. HPERC/419 dated 5
th
September, 2018 published in the R H.P. dated 7
th
September, 2018 at p.4503-4504 and before its substitution it stood as under:-
“contract demand so reduced, during the said period of 365 days;”
10 Compendium of HPERC Regulations, March 2020
infrastructure development charges which were payable by him at the time of
release of original connection.]
(3) Where a consumer having temporary connection for electricity seeks a
permanent connection, the matter shall be dealt with in accordance with respective
provisions for disconnection of temporary connection under regulation 8 and for providing
a new connection under relevant provisions of these Regulations.
Previous and next
Questions people ask
Is regulation 7 of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 is recorded.