Regulation 4, The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012: Expenses for providing service line
The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 - Regulation 4
Text of regulation 4
Expenses for providing service line
4. Expenses for providing service line.- The distribution licensee shall recover all
expenses reasonably incurred on the works related to laying of service line to the premises
of the applicant as well as the cost of providing terminal equipment and other arrangements
(except the cost of meter, CT and PT) at the applicant’s premises:
Provided that the distribution licensee may, with the approval of the Commission,
recover the expenses on the basis of average or normative rates for providing the service
lines for the purpose of giving supply of electricity to one or more categories of applicants
based on connected load or contract demand, voltage level, nature of load, tariff
classification and length and specification of service lines:
Provided further that in cases where the normative rates have been approved by the
Commission for a particular period for a particular type of service line, the recovery for
laying of that type of service line shall be made by the distribution licensee only in
accordance with the rates and terms and conditions so approved by the Commission for
that period:
Provided further that the Commission may direct the licensee to recover the cost of
service line under this regulation at fixed per kilometer rates, based on the standard cost
data, for all or any of the categories:
Provided further that the average or normative rates shall, unless specifically
approved by the Commission, not apply to the temporary connections.
Previous and next
Questions people ask
Is regulation 4 of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 is recorded.