Rule 9, M.P. State (Establishment of Thermal Power Plants) Land Management Rules 2011: Details of total land required / envisaged for the project with justification
M.P. State (Establishment of Thermal Power Plants) Land Management Rules 2011 - Rule 9
Text of rule 9
Details of total land required / envisaged for the project with justification
9. Details of total land required / envisaged for the project with justification:-
S. No.
lo
2.
~3.
4.
5.
6.
7.
8.
9.
Purpose
Main Plant
Coal Handling Plant (CHP)
Water system
Switchyard
Misc BoP facilities, stores, roads
Green Belt
Ash Disposal Area
Township
Corridors for Ash slurry, raw water & coal
Total
Area in acres
Justification of land requirement:
Previous and next
← Rule 3Please specify whether new venture / expansion projectRule 10 →Break-up of above land with present status of acquisition / allotment / purchase
All provisions of M.P. State (Establishment of Thermal Power Plants) Land Management Rules 2011
Questions people ask
Is rule 9 of M.P. State (Establishment of Thermal Power Plants) Land Management Rules 2011 still in force?
No repeal of M.P. State (Establishment of Thermal Power Plants) Land Management Rules 2011 is recorded.