Mid-term Performance Review and Review at the End of the Control Period
[39. Mid-term Performance Review and Review at the End of the Control Period .-
(1) Mid-term performance review- The transmission licensee shall make an
application for mid-term Performance Review within 120 days before the commencement
of the fourth year of the Control Period i.e. FY 2017-18:-
The scope of the mid-term Performance Review shall be a comparison of the actual
performance with the approved forecast of Aggregate Revenue Requirement and expected
revenue from tariff and charges The transmission licensee shall submit to the Commission
all information together with audited account statements, extracts of books of account and
such other details as the Commission may require to assess the reasons for and extent of
any variation in performance from the approved forecast. The mid-term review shall
comprise of the following:
1
Subs. vide Not. no. HPERC/F(5)(3)(1)(Trans) dated 1st November,2013 published in the R H.P. dated 4th
November, 2013 at p. 4608 to 4616. Before its substitution read as under:
“39. Review at the end of the Control Period
(1) Towards the end of the control period, the Commission shall review if the implementation of the principles laid down
in these regulations has achieved their intended objectives. While doing this, the Commission shall take into account,
among other things, the industry structure, sector requirements, consumer and other stakeholder expectations and the
licensee’s requirements at that point in time. Depending on the requirements of the sector to meet the objects of the
Act, the Commission may revise the principles for the next control period.
(2) The end of the control period shall be the beginning of the next control period and the licensee shall follow the same
procedure, unless required otherwise by the Commission. The Commission shall analyse the performance of the
licensee with respect to the targets set out at the beginning of the control period and based on the actual performance,
expected efficiency improvements and other factors prevalent, determine the initial values for the next control period.”
Compendium of HPERC Regulations, March 2021 29
(i) True-up of previous Control Period
(ii) A comparison of the actual/ audited performance with the approved forecast
for first two financial years of the Control Period, subject to the prudence
check including pass-through of impact of uncontrollable factors;
(iii) Review of controllable parameters
(iv) Review of ARR for the balance of the control period in case of any major
change in uncontrollable and/ or controllable parameters
(v) Review of transmission charges on account of modification in ARR for the
balance control period.
(2) Review at the end of control period - The transmission licensee shall also
make an application for Comprehensive Review after the end of the third Control Period
on availability of audited accounts for each year of the control period. The comprehensive
review shall be based as per the principles laid down under these Regulations for various
parameters of ARR:
Provided that the transmission licensee shall submit to the Commission information
in such format as may be stipulated by the Commission, together with the audited account
statements, extracts of books of account and such other details as the Commission may
require to assess the reasons for and extent of any variation in financial performance from
the approved forecast of Aggregate Revenue Requirement and expected revenue from
tariff and charges.
(3) Towards the end of the control period, the Commission shall review if the
implementation of the principles laid down in these regulations has achieved their intended
objectives. While doing this, the Commission shall take into account, among other things,
the industry structure, sector requirements, consumer and other stakeholder expectations
and the licensee’s requirements at that point in time. Depending on the requirements of the
sector to meet the objects of the Act, the Commission may revise the principles for the next
control period.
(4) The end of the control period shall be the beginning of the next control period
and the licensee shall follow the same procedure, unless required otherwise by the
Commission. The Commission shall analyze the performance of the licensee with respect
to the targets set out at the beginning of the control period and based on the actual
performance, expected efficiency improvements and other factors prevalent, determine the
initial values for the next control period.]
Previous and next
Questions people ask
Is regulation 39 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 is recorded.