Regulation 23, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011: Depreciation
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 - Regulation 23
Text of regulation 23
Depreciation
23. Depreciation.- (1) The value base for the purpose of depreciation shall be the
capital cost of the asset admitted by the Commission.
(2) The salvage value of the asset shall be considered as 10% and depreciation shall
be allowed up to maximum of 90% of the capital cost of the asset.
4[(2-a) The salvage value for IT equipment and software shall be considered as NIL
and 100% value of the assets shall be considered depreciable.]
(3) Depreciation shall be calculated annually based on Straight Line Method and at
rates specified in Appendix-I to these regulations for the assets of the transmission system:
Provided that, the remaining depreciable value as on 31
st
March of the year closing
after a period of 12 years from date of commercial operation shall be spread over the
balance useful life of the asset.
1
Ins. sub-regulation (7) vide Not. No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published in the R
H.P. dated 27
th
November, 2018 at p. 6256-6264.
2
Subs. vide Not No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published in the R H.P. dated
27
th
November, 2018 at p. 6256-6264. Before its substitution read as under:
“(21) Working Capital.- The Commission shall calculate the working capital requirement for the transmission licensee
containing the following components: -
(a) O&M expenses for 1 month;
(b) maintenance spare @ 40% of repair and maintenance expenses for one month; and
(c) receivables for two months based on the projected annual transmission charges.”
3
Subs. vide Not No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published in the R H.P. dated
27
th
November, 2018 at p. 6256-6264. Before its substitution read as under:
“(22) Interest Charges on Working Capital .- Rate of interest on working capital to be computed as provided hereinafter
in these regulations shall be on normative basis and shall be equal to the 3[Average Base Rate of State Bank of India for
the last six months prior to the filing of the MYT petition plus 350 basis points]. The interest on working capital shall be
payable on normative basis notwithstanding that the licensee has not taken working capital loan from any outside agency
or has exceeded the working capital loan based on the normative figures.”
4
Add. sub-regulation (2-a) vide Not No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published
in the R H.P. dated 27
th
November, 2018 at p. 6256-6264.
22 Compendium of HPERC Regulations, March 2021
(4) For transmission project which are in operation for less than 12 years, the
difference between the cumulative depreciation recovered and the cumulative depreciation
arrived at by applying the depreciation rates specified in this regulation corresponding to
12 years, shall be spread over the period up to 12 years, and the remaining depreciable
value as on 31
st
March of the year closing after a period of 12 years from date of
commercial operation shall be spread over the balance useful life of the asset.
(5) For the project in operation for more than 12 years, the balance depreciation to
be recovered shall be spread over the remaining useful life of the asset.
(6) Depreciation shall be chargeable from the first year of commercial operation.
In case of commercial operation of the asset for part of the year, depreciation shall be
charged on pro rata basis.
1
Previous and next
Questions people ask
Is regulation 23 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 is recorded.