Regulation 15, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011: Initial Spares
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 - Regulation 15
Text of regulation 15
Initial Spares
[15. Initial Spares.—The capital cost may include initial spares capitalised as a
percentage of the original project cost, subject to the following ceiling norms:—
(a) Transmission Line 0.75%
(b) Transmission Sub-station (Green Field) 3.0%
(c) Transmission Sub-station (Brown Field) 4.5%
(d) Series Compensation devices and HVDC Station 3.5%
(e) Gas Insulated Sub-station (GIS) 4.0%
(f) Communication System 3%]
Previous and next
Questions people ask
Is regulation 15 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 is recorded.