Regulation 7, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011: Capital Investment Plan
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 - Regulation 7
Text of regulation 7
Capital Investment Plan
7. Capital Investment Plan.- (1) The Commission shall approve the system
augmentation plan submitted by the transmission licensee, based on the load growth
forecast during the control period. The same would be considered for computation of ARR,
wherein the amount of electricity transmitted by the transmission system shall be projected
considering the estimated growth plan of transmission customer and any plans of new
transmission system, based on network expansion plans within the State.
1 Ins. regulation 5-A vide Not No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published in
the R H.P. dated 27
th
November, 2018 at p. 6256-6264.
2 Ins. regulation 6-A vide Not No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published in
the R H.P. dated 27
th
November, 2 018 at p. 6256-6264.
Compendium of HPERC Regulations, March 2021 9
(2) Capital investment plan submitted by the licensee shall also provide details of
ongoing projects that will spill into the control period and new projects that will
commence during the control period but may extend beyond the control period.
(3) The capital investment plan shall be in conformity with the plans made by the
1
[CEA/CTU/STU/ Distribution Licensee(s)]. The investment plan shall be scheme-wise
and each scheme shall include-
(a) purpose of investment (i.e. replacement of existing assets, meeting load
growth, technical loss reduction, meeting reactive energy requirements,
improvement in quality and reliability of supply, etc);
(b) Capital Structure;
(c) Capitalisation Schedule;
(d) Financing Plan;
(e) Cost-benefit analysis;
(f) Improvement in operational efficiency envisaged in the control period.
2
[(4) For each year of the control period, the Commission shall watch over the actual
capital expenditure and capitalization vis-à-vis the approved capital expenditure and
capitalization schedule. In the normal course, the Commission shall not revisit the
approved capital investment plan (capital expenditure and the capitalization schedule)
during the control period and adjustments to depreciation, interest on capital loan and
return on equity on account of variations for the actual capital expenditure incurred and
capitalization done vis-à-vis approved capital investment plan (capital expenditure and
capitalization), shall be done during the mid-term performance review and at the time of
end of control period true up.]
(5) In case the capital expenditure is required for emergency work which has not
been approved in the Capital Investment Plan, the licensee shall submit an application
(containing all relevant information along with reasons justifying emergency nature of the
proposed work seeking approval by the Commission. The licensee shall take up the work
prior to the approval of the Commission provided that the emergency nature of the scheme
has been certified by its board of directors.
Previous and next
Questions people ask
Is regulation 7 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 is recorded.