Regulation 31, The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011: Business Plan Filings
The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 - Regulation 31
Text of regulation 31
Business Plan Filings
31. Business Plan Filings.-
2
[(1) The applicant shall file for the Commission’s approval,
during the year preceding the first year of the control period or by any other date as may be
directed by the Commission, a business plan and CAPEX plan approved by its Management
in accordance with these regulations.]
(2) The applicant shall file the application for approval of fees and charges for each
year of the control period consistent with the CAPEX Plan, not less than 120 days before the
commencement of the first year of the control period or such other date as may be directed
by the Commission.
(3) The filings for the State Load Despatch Centre fees and charges shall contain the
following:-
(a) the network usage forecast for each year of the control period, consistent with
the Business Plan;
(b) estimated budget for the control period;
(c) proposals for fees and charges for each year of the control period, and
the procedure thereof;
(d) proposal for allocation of fees and charges applicable to each of the
beneficiaries for the control period; and
(e) expected revenue from the fees and charges.
3
[31-A. Mid-term performance review and True up at the End of Control Period.-
A. Mid-term performance review
To ensure smooth implementation of the multiyear tariff (MYT) framework and to
address any mid-term changes on account of unexpected outcomes, the
1
For orders and formats see R.H.P. dated 2
nd
June, 2011 at p. 966-968 and R.H.P. dated 5
th
Nov., 2013
at p. 4626-4628.
2
Subs. vide Not. no. HPERC/F(5)(3)(1)(SLDC) dated 1
st
November,2013 (First Amendment)Reg.2013
published in the R H.P. dated 5
h
November, 2013 at p .o 4619 – 4626. Before its substitution sub- regulations
(1) read as under:
“(1) The applicant shall file for the Commission’s approval, on 1st April of the year preceding the first year of
the control period or any other date as may be directed by the Commission, a business plan and CAPEX plan
approved by its Management in accordance with regulations 12 and 13.”
3 Subs. vide Not. No. HPERC/F(5)(3)(1)(SLDC) dated 1
st
November,2013(First Amendment) Reg.
2013 published in the R H.P. dated 4
th
November, 2013 at p. no 4620-4626.
Compendium of HPERC Regulations, March 2021 23
Commission shall undertake mid-term review of power system operation
company’s performance during the control period;
(a) The power system operation company shall make an application for mid-term
performance review in accordance with the timelines specified in
Appendix-I. The scope of the mid-term performance review shall be a
comparison of the actual performance with the approved forecast of
Aggregate Revenue Requirement and expected revenue from tariff and
charges. The power system operation company shall submit to the
Commission all information together with audited account statements,
extracts of books of account and such other details as the Commission may
require to assess the reasons for and extent of any variation in performance
from the approved forecast. The mid-term review shall comprise of the
following:
(i) A comparison of the audited performance with the approved forecast
for first two financial years of the Control Period, subject to the
prudence check including mid-term correction due to any unforeseen
circumstances;
(ii) Determination of gains or losses for the first two years of the control
period;
(iii) Review of ARR for the balance years of the control period in case of
any major change in the parameters;
(iv) Review of SLDC tariff on account of modification in ARR for the
balance years of the control period.
B. True-up at the end of Control Period
The power system operation company shall file an application for true-up at the
end of the third Control Period on availability of audited accounts for each year
of the control period in accordance with the timelines specified in Appendix-I.
The true-up shall be based on the principles laid down under these Regulations
for various parameters of ARR:
Provided that the power system operation company shall submit to the
Commission information in such format as may be stipulated by the
Commission, together with the audited account statements, extracts of books of
account and such other details as the Commission may require to assess the
reasons for and extent of any variation in financial performance from the
approved forecast of Aggregate Revenue Requirement and expected revenue
from tariff and charges.]
16. Periodic Returns during the Control Period.- (1) The Power system Operation
Company shall submit periodic returns, as may be specified, containing operational and
cost data to enable the Commission to monitor the implementation of its MYT order.
(2) The Power system Operation Company shall submit to the Commission annual
statements of its performance and accounts including the latest report of audited accounts.
24 Compendium of HPERC Regulations, March 2021
PART-VIII
MISCELLANEOUS
Previous and next
Questions people ask
Is regulation 31 of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 is recorded.