Regulation 23, The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011: Interest on Working Capital
The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 - Regulation 23
Text of regulation 23
Interest on Working Capital
[23. Interest on Working Capital.—(1) The working Capital shall cover:—
(a) O&M expenses for one month;
(b) receivables for two months State Load Despatch Centre charges as approved
by the Commission;
(c) maintenance spares @ 15% of O&M Expenses for one month.
1
Subs. vide Not No. HPERC-F(1)-3/2018 dated 22
nd
November, 2018 published in the R H.P. dated
27
th
November, 2018 at p. 6277-6283 and before its substitution read as under:
“ 23. Interest on working capital.- (1) The working capital shall cover-
(a) Operation and maintenance expenses for one month;
(b) Maintenance spares @ 40% of R&M expenses for 1 month; and
(c) Receivables equivalent to two months of the State Load Despatch Centre charges as approved by the
Commission.
(2) Rate of interest on working capital to be computed as provided hereinafter in these regulations shall
be on normative basis and shall be equal to the1[average Base Rate of State Bank of India for the last six months
prior to the filing of the MYT petition plus 350 basis points.
(3) The interest on working capital shall be payable on normative basis notwithstanding that the
Power System Operation Company has not taken working capital loan from any outside agency or has
exceeded the working capital loan based on the normative figures.”
20 Compendium of HPERC Regulations, March 2021
(2) Rate of interest on working capital to be computed as provided hereinafter in
these regulations shall be on normative basis and shall be equal one (1) Year State Bank of
India (SBI) MCLR / any replacement thereof as notified by RBI for the time being in effect
applicable for one (1) Year period, as may be applicable as on 1st April of the Financial
Year in which the Petition is filed plus 300 basis points.
(3) The interest on working capital shall be payable on normative basis
notwithstanding that the Power system Operation Company/ State Load Despatch Centre has
not taken working capital loan from any outside agency or has exceeded the working capital
loan based on the normative figures.]
Previous and next
Questions people ask
Is regulation 23 of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 is recorded.