Regulation 15, The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011: Capital Cost

The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 - Regulation 15

Text of regulation 15

Capital Cost

15. Capital Cost .- (1) The capital cost for a State Load Despatch Centre shall include the expenditure incurred or projected to be incurred during the control period, including Interest During Construction (IDC) and financing charges, any gain or loss on account of Foreign Exchange Rate Variation (FERV) during construction and Incidental Expenditure During Construction (IEDC) in line with the CAPEX plan: Provided that the value of the assets not in use shall not form part of the capital cost. (2) The capital cost admitted by the Commission after prudence check shall form the basis for determination of charges: Provided that prudence check may include scrutiny of the reasonableness of the capital expenditure, financing plan, IDC, IEDC, use of efficient technology, cost over- run and time over-run, and such other matters as may be considered appropriate by the Commission: Provided further that the capital cost appearing in the books of accounts of the Power System Operation Company for the State Load Despatch Centre as on the date of transfer along with the approved capital expenditure plan for the control period shall be the basis for determination of charges. 1 Added sub-regualtion (5) vide Not No. HPERC-F(1)-3/2018 dated 22 nd November, 2018 published in the R H.P. dated 27 th November, 2018 at p. 6277-6283. Compendium of HPERC Regulations, March 2021 13 1

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011

Questions people ask

Is regulation 15 of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 is recorded.