Regulation 13, The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011: Capital Expenditure Plan (CAPEX plan)

The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 - Regulation 13

Text of regulation 13

Capital Expenditure Plan (CAPEX plan)

13. Capital Expenditure Plan (CAPEX plan) .- (1) The Commission shall approve the capital expenditure plan including scheme for augmentation submitted by the Power System Operation Company, based on the load growth forecast during the control period. The same would be considered for computation of ARR, wherein the amount of electricity handled by the State Load Despatch Centre shall be projected considering the estimated growth plan of its users and any plans of new transmission system, based on network expansion plans within the State. (2) Capital expenditure plan submitted by the Power System Operation Company shall also provide details of ongoing projects that will spill into the control period and new projects that will commence during the control period but may extend beyond the control period. (3) The capital expenditure plan shall be in conformity with the plans made by the transmission licensee and with the capital investment plans of the distribution licensee and the generating company(ies). The capital expenditure plan shall inter-alia include- (a) purpose of investment (i.e. replacement of existing assets, meeting load growth, technical loss reduction, meeting reactive energy requirements, improvement in quality and reliability of supply, etc) ; (b) Capital structure; (c) Capitalisation schedule; (d) Financing plan; (e) Cost-benefit analysis; (f) improvement in operational efficiency envisaged in the control period; 1 [(4) For each year of the control period, the Commission shall watch over the actual capital expenditure and capitalization vis-à-vis the approved capital expenditure and capitalization schedule. In the normal course, the Commission shall not revisit the approved capital investment plan (capital expenditure and the capitalization schedule) during the control period and adjustments to depreciation, interest on capital loan and return on equity on account of variations for the actual capital expenditure incurred and capitalization done vis-à-vis approved capital investment plan (capital expenditure and capitalization), shall be 1 Subs. vide Not. no. HPERC/F(5)(3)(1)(SLDC) dated 1 st November,2013 published in the R H.P. dated 4 th November, 2013 at p. 4619- 4626. Before its substitution is read as under: “(4) The Commission shall review the actual capital expenditure incurred and capitalisation at the end of each year of the control period vis-à-vis the approved capital expenditure and capitalisation schedule. In the normal course, the Commission shall not revisit the approved capital investment plan (capital expenditure and capitalisation schedule) during the control period and adjustment to depreciation, interest on capital loan and return on equity for the actual capital expenditure incurred and capitalisation vis-à-vis approved capital investment plan (capital expenditure and capitalisation) shall be done at the end of control period.” 10 Compendium of HPERC Regulations, March 2021 done during the mid-term performance review and at the time of true up at the end of control period.] (5) In case the capital expenditure is required for emergency work which has not been approved in the Capital Investment Plan, the Power System Operation Company shall submit an application (containing all relevant information along with reasons justifying emergency nature of the proposed work seeking approval by the Commission. The Power System Operation Company shall take up the work prior to the approval of the Commission provided that the emergency nature of the scheme has been certified by its Management. Provided that, for the purpose of this sub-regulation, such approved capital expenditure shall be treated as a part of actual capital expenditure incurred to the Power System Operation Company/State Load Despatch Centre as well as the approved capital expenditure by the Commission. 1[13-A. Consumer Contribution, Deposit Work, Grant and Capital Subsidy.—(1) The works carried out by the Power System Operation Company/State Load Despatch Centre after obtaining the estimated cost from the users shall be classified as Deposit Works. (2) Capital works undertaken by the Power System Operation Company/State Load Despatch Centre utilising grants received from the State and Central Governments, including funds under various schemes shall be classified under the category of Grants. (3) The works carried out with any other grant of similar nature or such amount received without any obligation to return the same and with no interest costs attached to such subvention shall also be classified as works performed through consumer contribution, deposit work, capital subsidy or grant. (4) The expenses on such capital expenditure shall be treated as follows:— (a) normative O&M expenses as specified in these regulations shall be allowed. However, any departmental charges taken by the Power System Operation Company/State Load Desptach Centre against deposit works and which are executed departmentally shall be adjusted in the employee cost; (b) the debt to equity ratio shall be considered in accordance with Regulation 17, after deducting the amount of financial support provided through consumer contribution, deposit work, capital subsidy or grant; (c) depreciation to the extent of works performed through consumer contribution, deposit work, capital subsidy or grant shall not be allowed as specified in Regulation 22; (d) provisions related to return on equity, as specified in Regulation 20, shall not be applicable to the extent of financial support provided through consumer contribution, deposit work, capital subsidy or grant; (e) provisions related to interest and finance charges, as specified in Regulation 21, shall not be applicable to the extent of financial support provided through consumer contribution, deposit work, capital subsidy or grant.” 1 Ins. regulation 13-A vide Not No. HPERC-F(1)-3/2018 dated 22 nd November, 2018 published in the R H.P. dated 27 th November, 2018 at p. 6277-6283 Compendium of HPERC Regulations, March 2021 11 1

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011

Questions people ask

Is regulation 13 of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 is recorded.