Regulation 9, The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011: Tariff Framework
The Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 - Regulation 9
Text of regulation 9
Tariff Framework
9. Tariff Framework.- (1) The Commission shall adopt Multi Year Tariff framework
for approval of fees and charges for the State Load Despatch Centre during the control
period.
(2) The Power System Operation Company/State Load Despatch Centre shall file
multiyear application for determination of SLDC fees and charges with the Commission as
per the timelines defined in Appendix-I to these regulations and the Commission shall
process the same in accordance with these regulations and the Conduct of Business
Regulations.
(3) The application shall include statements containing Aggregate Revenue
Requirement (ARR) for the previous year, base year and the projections for the control
period. The information for the previous year should be based on audited accounts.
(4)The applicant shall, immediately after the application is admitted by the
Commission, post complete application on its website, and shall keep it on the website till
its disposal by the Commission.
(5) The application made shall be supported by affidavit of the person acquainted
with the facts stated in the application.
(6) The applicant shall, in the manner as may be directed by an order made by the
Commission, publish a notice of the application in atleast two daily newspapers, one in the
English language and one in the Hindi language, having wide circulation in the State.
(7) Based on the applicant’s objections/ suggestions from public and other
stakeholders on the application, the Commission may, within 120 days of the receipt
of the application, complete in all respects, and after considering all suggestions and
objections from public and other stakeholders,-
(a) issue, an order with such modifications and/or such conditions, as may be
deemed just and appropriate containing, inter alia targets for controllable
items, the State Load Despatch Centre fees and charges for each year of the
control period; or
8 Compendium of HPERC Regulations, March 2021
(b) reject the application for reasons to be recorded in writing if such application
is not in accordance with the provisions of the Act and the rules and
regulations made thereunder or the provisions of any other law for the time
being in force.
(8) The Commission shall, within seven days of making the order determining
the fees and charges leviable by the State Load Despatch Centre, send a copy of the order to
the Power System Operation Company.
(9) The applicant shall publish the rates of fees and charges approved by the
Commission in the newspapers, having circulation in the area of supply, as the Commission
may direct. The publication shall, besides such other things as the Commission may
require, include a general description of the rates of fees and charges.
(10) An order determining the fees and charges leviable by the State Load Despatch
Centre shall, unless amended or revoked, continue to be in force for such period as may be
specified in the said order.
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Levy and Collection of Fees and Charges by State Load Despatch Centre) Regulations, 2011 is recorded.